ML040920125
| ML040920125 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 03/24/2004 |
| From: | NRC/RGN-II |
| To: | |
| Shared Package | |
| ML040920119 | List: |
| References | |
| Download: ML040920125 (18) | |
Text
NRC CY2003 Annual Assessment Meeting Shearon Harris Apex, North Carolina Apex, North Carolina March 24, 2004 March 24, 2004
A public forum for discussion of the licensees A public forum for discussion of the licensees performance performance NRC will address the licensee performance issues NRC will address the licensee performance issues identified in the annual assessment letter identified in the annual assessment letter Licensee will be given the opportunity to respond to Licensee will be given the opportunity to respond to the information in the letter and inform the NRC of the information in the letter and inform the NRC of new or existing programs to maintain or improve new or existing programs to maintain or improve their performance their performance
Agenda Introduction Review of Reactor Oversight Process National Summary of Plant Performance Discussion of Plant Performance Results Licensee Response and Remarks NRC Closing Remarks Break NRC available to address public questions
Region II Organization Luis Reyes Regional Administrator Loren Plisco Deputy Regional Administrator Victor McCree Director Division of Reactor Projects Leonard Wert Deputy Director Charles Casto Director Division of Reactor Safety Harold Christensen Deputy Director Paul Fredrickson Branch Chief Regional Specialists Shearon Harris Resident Inspectors Randy Musser Philip OBryan Project Engineer George MacDonald
NRC Performance Goals Maintain safety and protect the environment Enhance public confidence Improve effectiveness, efficiency, and realism of processes and decision making Reduce unnecessary regulatory burden
Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas
Examples of Baseline Inspections
Equipment Alignment
~92 hrs/yr
Triennial Fire Protection
~200 hrs every 3 yrs
Operator Response
~125 hrs/yr
~80 hrs/yr
Rad Release Controls
~100 hrs every 2 yrs
Worker Radiation Protection ~100 hrs/yr
Corrective Action Program
~200 hrs every 2 yrs
Corrective Action Case Reviews ~60 hrs/yr
Performance Thresholds Safety Significance Green:
Very low safety issue White:
Low to moderate safety issue Yellow:
Substantial safety issue Red:
High safety issue NRC Inspection Efforts Green:
Only Baseline Inspection White:
May increase NRC oversight Yellow:
Increased NRC oversight Red:
Increased NRC oversight and other NRC actions
Action Matrix Concept Licensee
Response
Regulatory
Response
Degraded Cornerstone Multiple/Rep.
Degraded Cornerstone Unacceptable Performance Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2003 Licensee Response 75 Regulatory Response 22 Degraded Cornerstone 2
Multiple/Repetitive Degraded Cornerstone 3
Unacceptable 0
Total 102*
- Davis-Besse under a special restart inspection process
- 3500 hours0.0405 days <br />0.972 hours <br />0.00579 weeks <br />0.00133 months <br /> of inspection related activities
- Resident inspector daily inspections
- Problem Identification and Resolution inspection
- Special Inspection on potential loss of shutdown cooling
- Engineering inspections
- Emergency preparedness inspection
- Reactor operator requal exam inspection
- Radiation protection inspections
- Reactor vessel upper head inspection
- Security inspections
Shearon Harris CY2003 Assessment Results Plant performance was within the Regulatory Response Column of the NRCs Action Matrix All inspection findings were classified as very low safety significance (Green)
One performance indicator was White: Unplanned Reactor Scrams----Harris received additional NRC oversight
Significant Findings and PIs Significant PI---Unplanned Reactor Scrams---White Four reactor trips in CY2003 NRC Supplemental Inspection determined corrective actions adequate and no evidence of common cause Potential Significant Findings Nine fire protection issues evaluated as being Green Potential loss of reactor shutdown cooling evaluated as being Green
Shearon Harris Annual Assessment Summary Progress Energy operated Shearon Harris in a manner that preserved public health and safety All cornerstone objectives were met with one White PI identified (Unplanned Reactor Scrams)
NRC plans baseline inspections at Shearon Harris for the remainder of CY 2004 A Supplemental Inspection on the Unplanned Reactor Scrams PI was conducted in CY2003
Resident inspector daily inspections Reactor containment sump blockage inspection Reactor operator initial exam Emergency preparedness inspection NRC pilot engineering design inspection Security inspection Maintenance inspection Reactor vessel lower head inspection Radiation protection inspection
NRC CY2003 NRC CY2003 Annual Assessment Meeting Annual Assessment Meeting Shearon Harris Apex, North Carolina March 24, 2004
Contacting the NRC
Report an emergency (301) 816-5100 (call collect)
Report a safety concern:
(800) 695-7403 Allegation@nrc.gov
General information or questions www.nrc.gov Select What We Do for Public Affairs
Reference Sources
Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html
Public Electronic Reading Room http://www.nrc.gov/reading-rm.html
Public Document Room 1-800-397-4209 (Toll Free)