FENOC FirstEnergy Nuclear Operating Company 5501 North State Route 2 Oak Harbor, Ohio 43449 Mark B. BezJlla 4u, MarkQ B.
ezilla 47B Vice President - Nuclear Fax: 416 Docket Number 50-346 License Number NPF-3 Serial Number 3035 March 1, 2004 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001
Subject:
Semiannual Fitness-For-Duty Report, July-December 2003 Ladies and Gentlemen:
Pursuant to 10 CFR 26.71 (d), "Recordkeeping Requirements," FirstEnergy Nuclear Operating Company (FENOC) submits the semiannual Fitness-For-Duty (FFD) report for the period of July through December 2003 for the Davis-Besse Nuclear Powver Station, Unit I (DBNPS).
Attachment I provides FENOC's DBNPS FFD Program Performance Data. Attachment 2 provides a summary of management actions taken by FENOC based on positive FFD testing results, presumptive positives, and a list of FFD event reports submitted by FENOC.
Should you have any questions or require additional information, please contact Mr. Gregory A. Dunn, Manager - Regulatory Affairs, at (419) 321-8450.
Sincerely, GMW/s
~-321-7676 S-321-7582 Attachments cc:
Regional Administrator, NRC Region III DB-1 NRC/NRR Senior Project Manager DB-1 Senior NRC Resident Inspector Utility Radiological Safety Board A btl
Docket Number 50-346 License Number NPF-3 Serial Number 3035 Attachment I Page 1 of2 First Energy Nuclear Operating Company Davis-Besse Nuclear Power Station Fitness-For-Duty Report July - December 2003
Docket Number 50-346 License Number NPF-3 Serial Number 3035 Page 2 of 2 Fitness for Duty Program Performance Data Personnel Subject to 10CFR 26 First Energy Nuclear ODerating Company Company December 31. 2003 6 Months Ending Davis-Besse Location (419) 321-8450 Phone G. A. Dunn, Manager - Regulatory Affairs Contact Name Cutoffs: Screen/Confirmation (nqlml)
ADDendix A to 10 CFR 26 Marijuana Cocaine Opiates 100/15 300/150 300/300 Amphetamines Phencyclidine Alcohol (%BAC) 1000/500 25/25 0.04 Long-Term Short-Term Testing Results Licensee Employees Contractor Personnel Contractor Personnel Average Number with Unescorted Access 851 0
374 Categories Tested Positive Tested Positive Tested Positive Pre-Access 147 1
0 0
195 1
For Post Accident 0
0 0
0 0
0 Cause Observed Behavior 1
0 0
0 1
0 Random 216 0
0 0
96 1
Follow-up 13 0
0 0
11 0
Other 0
0 0
0 1
0 Total 377 1
0 0
304 2
Breakdown of Confirmed Positive Tests for Specific Substances Marijuana Cocaine Opiates Amphe-Phency-Alcohol Refusal Mrjaa Ccie Oits tamines Clidinetoes Licensee Employees I
0 0
0 0
0 0
Long-Term Contractors 0
0 0
0 0
0 0
Short-Term Contractors 1
0 0
0 0
1 0
Total 2
0 0
0 0
1 0
Docket Number 50-346 License Number NPF-3 Serial Number 3035 Page 1 of 1 FENOC MANAGEMENT ACTIONS RELATING TO FITNESS-FOR-DUTY FENOC Personnel Contractor Personnel Referred to EAP 0
0 Management Sanctions 1
2 FENOC does not perform onsite initial drug screening tests; therefore, there are no unconfirmed positive results on which to base management actions.
FENOC FITNESS-FOR-DUTY REPORTS There were no Fitness-For-Duty reports submitted during this reporting period (July - December 2003).
Docket Number 50-346 License Number NPF-3 Serial Number 3035 Page I of I COMMITMENT IST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by Davis-Besse. They are described only as information and are not regulatory commitments. Please notify the Manager - Regulatory Affairs (419) 321-8450 at Davis-Besse of any questions regarding this document or associated regulatory commitments.
COMMITMENTS DUE DATE None N/A