AmerGen ArnerGen Energy Company. LLC Telephone: 717-948-8000 An Exelon Company Three Mile Island Unit 1 Route 441 South, PO. Box 480 Middletown, PA 17057 February 6, 2004 5928-04-20034 U. S. Nuclear Regulatory Commission Att: Document Control Desk Washington, DC 20555

SUBJECT:

THREE MILE ISLAND NUCLEAR STATION, UNIT NO. (TMI- 1)

DOCKET NO. 50-289 OPERATING LICENSE NO. DPR-50 LONG RANGE PLANNING PROGRAM (LRPP)

ANNUAL UPDATE OF INTEGRATED SCHEDULE "ABC" PROJECT LISTING Pursuant to License DPR-50 Condition No. 2.c.9, AmerGen Energy Company, LLC (AmerGen) hereby submits the required annual update of projects listed in each category (A, B, and C) as defined by the LRPP integrated schedule. The attachments to this letter include: 1) the ABC project listing; and, 2) a summary of changes since the last submittal forwarded by AmerGen Letter No. 5928.03-20023, dated February 15, 2003. An abstract of the attachments follows:

1. Attachment A - A new project listing of Category A, B, and C projects annotated by an asterisk (*) to identify new projects and by a double asterisk (**) to identify changes in Budget Authorization (B/A) number assignments. Completed projects have been removed from the schedule listing. Remaining projects are ongoing or are scheduled consistent with cycle/year commitments. Any changes in schedule are reflected on Attachments A and B.

4 I

5928-04-20034 Page 2

2. Attachment B - A summary listing of Category A and B projects which have been completed, deferred, changed in scope, or otherwise changed with explanations, as appropriate. The Attachment B listing also contains Category C project completions. Please note that changes to the Category C scope or schedule do not impact the Category A and B schedules.

Pursuant to the LRPP for TM - 1, AmerGen will assume that the NRC is in agreement with the above Category A and B changes, unless we are notified otherwise within 15 days of receipt. If additional information is needed, please contact Adam Miller, of TMI-1 Regulatory Assurance at (717) 948-8128.

Sincerely, G. H. Gellrich Plant Manager GHG/awm Attachments File No. 04020 cc: NRC Administrator Region I NRC TMI - 1 Senior Resident Inspector NRC TMI - 1 Project Manager Chairman, Board of Supervisors, Londonderry Township, Dauphin County, Pennsylvania Board of County Commissioners, Dauphin County, Pennsylvania Pennsylvania Department of Environmental Resources, Bureau of RadiatiorProtection

ATTACHMENT A TMI -1 PROJECT LISTING INTEGRATED SCHEDULE ANNUAL UPDATE (February, 2004)

.I TMI -1 PROJECT LISTING NRC INTEGRATED SCHEDULE CATEGORY "A" PROJECTS STATUS AS OF 1114/04 OBS BIA NUMBER DESCRIPTION CYCLEIYEARS CLASSIFICATION 1 Technical WHEN HANDLING IRRADIATED FUEL IN THE On-Going commitment (License NRR Specification 3.8.11 REACTOR BUILDING, A SHIFTLY CHECK AND A Amendment #236, dated 10/2/01)

DAILY VERIFICATION (ONCE PER 24 HOURS) SHALL BE PERFORMED TO CONFIRM THAT THE FUEL TRANSFER CANAL WATER LEVEL IS >23 FEET ABOVE THE REACTOR VESSEL FLANGE.

Legend:

  • *New Projects
  • ** B/A Number Change

TMI-1 PROJECT LISTING NRC INTEGRATED SCHEDULE CATEGORY "B" PROJECTS Status as of 1/14/04 OBS B/A NUMBER DESCRIPTION CYCLE/ CLASSIFICATION YEARS 2 TRFuel OTSG EDDY CURRENT TESTING 16R NRR ECT 100% OF TUBES WITH BOBBIN COIL WITH ADDITIONAL MRPC 2005 INSPECTIONS. SCOPE ALSO INCLUDES TUBE REPAIRS 3 TR Fuel BASELINE OUTAGE 16R NRR PERFORM OUTAGE ACTIVITIES INCLUDING PM, CM, REFUELING, TURBINE 2005 INSPECTION & OVERHAUL, ISI AND FAC ACTIVITIES AND OUTAGE PREPARATION AND SUPPORT 4 TR Fuel OTSG EDDY CURRENT TESTING 17R NRR ECT 100% OF TUBES WITH BOBBIN COIL WITH ADDITIONAL MRPC 2007 INSPECTIONS. SCOPE ALSO INCLUDES TUBE REPAIRS 5 TRFuel BASELINE OUTAGE 17R NRR PERFORM OUTAGE ACTIVITIES INCLUDING PM, CM, REFUELING, TURBINE 2007 INSPECTION & OVERHAUL, ISI AND FAC ACTIVITIES AND OUTAGE PREPARATION AND SUPPORT.

6 T20228 REACTOR BUILDING TENDON SURVEILLANCE 2004- NRR PROVIDE CONTRACTOR AND PLANT SUPPORT FOR SURVEILLANCE PROGRAM. 2005 REF NUREG 135.1; TS 4.4.2.1 &16R 7 T20111 TMI PRA UPDATE 2004 NRR PERFORM PERIODIC UPDATE OF TMI PRA.

8 T20112 DEVELOP FIRE PRA 2004- NRR 2005 DEVELOP FIRE PRA FOR TMI.

Legend:

  • *New Projects
  • ** B/A Number Change

TMI-1 PROJECT LISTING NRC INTEGRATED SCHEDULE CATEGORY "C" PROJECTS Status as of 1/31/03 OBS B/A NUMBER DESCRIPTION CYCLE! CLASSIFICATION YEARS

  • 9 TI 0246 INCORE REPLACEMENT 16R NRR 2005
  • 10 T20161 ,

IST PROGRAM 10 YEAR CODE UPDATE 2004 NRR

  • 11 T00353 INSTALL NEW INVERTER INB TRAIN INVERTER ROOM 2004 MRC 12 T10128 BREAKER OVERHAULS 2004- MRC

. ~~~~~~~~~~~~~2006 ESTABLISH A SHOP AREA AND INSTALL NECESSARY EQUIPMENT TO

.____________ OVERHAUL AND REFURBISH BREAKERS.

13 T10141 SIMULATOR SOFTWARE UPGRADES 2004- MRC UPGRADE THE TMI SIMULATOR SOFTWARE TO LATEST VERSION OF OPEN SIM 2006 AND OPEN SIM IS AT THE SAME TIME UPGRADEING THERMAL HYDRAULICS SOFTWARE TO THOR 14 T10154 PURCHASE AND INSTALL AUX BOILERS 16R MRC PURCHASE AND INSTALL NEW AUX BOILERS TO UPGRADE MATERIAL 2005 CONDITION OF AUX BOILERS AND TO IMPROVE RELIABILITY.

15 T10181 REFURBISH NATURAL DRAFT COOLING TOWERS 16R MRC PERFORM MAJOR REPLACEMENT OF MATERIAL ON THE NDCTS TO MITIGATE 2005 DEGRADATION & MAINTAIN MATERIAL CONDITION

  • 17 T10249 INSTALL PZR HEATER BUNDLE 16R MRC 2005 18 T20112 BREAKER OVERHAULS 2004- MRC ESTABLISH AND IMPLEMENT BREAKER OVERHAUL PROGRAM AT TMI Legend:
  • *New Projects
  • **B/A Number Change

TMI-1 PROJECT LISTING NRC INTEGRATED SCHEDULE CATEGORY "C" PROJECTS

_______ _________________ ~~~~~~~~~~~~~~~Status as of 1/31/03

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _2 00 6 J_ _ _ _ _ _ _ _ _

19 T10181 REFURBISH NATURAL DRAFT COOLING TOWERS 17R MRC PERFORM MAJOR REPLACEMENT OF MATERIAL ON THE NDCTS TO MITIGATE 2007 DEGRADATION & MAINTAIN MATERIAL CONDITION II Legend:

  • *New Projects
    • B/A Number Change

ABC Classifications a) Meet NRC Requirements (NRR) - Activities that a) must be carried out to fulfill specific NRC requirements or b) have been committed to the NRCby the company or c) are such that if not accomplished would result in an NRC norvcompliance even though the specific activity is not required by the NRC.

b) Meet Environmental Requirements (ERR) - Activities that a) are specifically required by environmental regulatory agencies (State and Federal) or b) have been committed to environmental agencies by the company or c) are such that if not accomplished would result in a regulatory noncompliance even though the specific activity is not required by an environmental regulatory agency.

c) Meet Other Requirements (ORR) -Activities not covered by the NRC or environmental requirements but that are required by local, state, or federal ordinances, codes, court order or law suit settlement, or other guidance to which tie company is committed or if not accomplished would result in a violation of that ordinance, code or guidance, court order, etc.

d) Increase Safety Marqins (ISM) - Activities that if implemented, will improve nuclear plant or personnel safety but are neither required for regulatory compliance nor required by safety regulation codes or guidance.

e) Decrease Environmental Effects (E)- Activities that, if implemented, will result in an improved environmental quality but are neither required for regulatory complnce nor required by environmental regulations, codes or guidance.

f) Improve Radiological Conditions (RAD) - Activities that, if implemented, will result in improved radiological conditions, lower man-rem exposure rates, or radwaste control/reduction but aie neither required for regulatory compliance nor required by radiological regulations, codes or guidance.

g) Maintain Reliability/Capabilit (MRC) - Activities that, if implemented, will maintain power production at existing levels by preventing deterioratim of plant systems or equipment.

Includes activities in response to national codes or standards, insurance policies, equipment vendor specifications or nuclear industry high unavailability equipment data without which the plant could not operate prudently h) Improve Reliability/Capability (REL) - Activities that, if implemented, will increase power generation by improving availability or capacity factor to maximize energy output.

i) Improve Operational Effectiveness(IOE) - Activities that, if implemented, wIl improve staff efficiency or provide a direct economic payback in terms of reduced operating/maintenance costs.

j) Improve Personnel Facilities (FAC) - Activities that, if implemented, will improve working conditions and the usefulness of personnel facilies.

ABC Classifications (continued)

k) Provide Contingency Blanket (CUI) - Activities that, if implemented, will provide management flexibility to respond in a timely manner to emergent work requirements or the ongoing requirements to procure, replace orrepair minor items essential to support routine operations.

I) Improves Heat Rate Performance(HRP) - Activities that, if implemented, will increase power production by enhancing the heat rate efficiency.

m) General Working Conditions (GWC) - Activities, tools, and equipment that if implemented will improve working conditions, but will not demonstrate a direct economic payback.

ATTACHMENT B TMI - 1 PROJECT LISTING INTEGRATED SCHEDULE ANNUAL UPDATE (February, 2004)

ATTACHMENT B CHANGES TO TMI - 1 NUCLEAR GENERATING STATION INTEGRATED SCHEDULE ANNUAL UPDATE (February, 2004)

Category 'A' Projects Additions: None Completions: Item 2 (description shown below), which was associated with TMI- 1 Technical Specification 2.1, has been removed from the Category "A' Projects list, effective October 20, 2003. This commitment was established via issuance of the NRC Safety Evaluation Report (SER) associated with TMI - 1 License Amendment No. 238, issued October 23, 2001.

Subsequently, the NRC SER associated with TMI - 1 License Amendment No. 247, issued October 20, 2003, allowed removal of this commitment.

The NRC SER section 3.1 reads in part: " ... The staff reviewed the licensee's methodology for determining the Thermal Design Limit (TDL) and determined that it contains sufficient margin to account for transition core effects as well as other cycle-specific requirements. The staff finds that the licensee has determined an appropriately conservative TDL and, therefore, removal of the commitment isacceptable."

2. A minimum Reactor Coolant System (RCS) flow rate of 105.5% of design flow (105.5% of 352,000 gpm) is specified to offset potential mixed core DNBR penalty for TMI Unit-1 Cycle 14 and any subsequent cycle. This commitment expires when a mixed core penalty is no longer required or NRC-approved statistical core design methods are utilized which provide an alternative means of addressing transition core effects.

Deletions: None

ATTACHMENT B (Continued)

Category 'B' Projects Additions: None Completions: TR Fuel OTSG Eddy Current Testing- Completed in T1RI5 outage TR Fuel Baseline Outage- Completed in TI RI5 outage Deletions: None

ATTACHMENT B (Continued)

Category 'C' Projects Additions: T1 0246 Incore Replacement T20161 IST Program 10 year Code update T00353 Install New Inverter in B Train Inverter Room T10323 ANS Siren Acoustic Study/Upgrade T10249 Install Pressurizer Heater Bundle Completions: C12677 Complete Reracking Spent Fuel Pool A T10131 Purchase and install newReactor Vessel Head Deletions: None