ML033010300

From kanterella
Jump to navigation Jump to search
Slides for Harris Nuclear Plant Fire Protection Meeting
ML033010300
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/10/2003
From:
Progress Energy Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0358
Download: ML033010300 (1)


Text

-

V t

Harris Nuclear Plant Fire Protection (z u Nuclear Ge(wrcton d % ~~Group 03 Progress Energy Attendees Bob Duncan - Director, Site Operations

  • Abdy Khanpour - Manager, Engineering
  • Eric McCartney - Superintendent, Engineering
  • Terry Morton - Manager, Support Services
  • John Caves - Supervisor, Licensing
  • John Yadusky - Licensing Engineeer
  • George Attarian - Corporate Chief Engineer
  • Jeff Ertman - Corporate Fire Protection Engineer
  • . Steve Laur - Supervisor, PSA VN Proew Energy 2

1

Agenda Io Overview of Fire Protection Inspection Findings g

5=

F Summary of Root Causes-

  • Corrective Actions
15. Overview of Project Plan
  • KN~PrgressEnergy OG

~~~~~~~~~~~~~~~~~

Overview of Inspection Findings Il Failure to identify cables potentially affected by fires

  • Inconsistency between Safe Shutdown Analysis and implementing procedure
  • Some non-feasible manual actions
  • Technical compliance P Lignting f

_, 4 P Manual actions not approved J`

i Aim C~~~~~~~~~~~

Progress Energy I /°h /0 s s 3 Lava

^,

Ar aa on yl i

  • 2.I~

Harris Nuclear Plant Fire Protection

~~b ~~Nuclear Gen~eratonn d % ~~Group a Progress Energy Attendees

  • Bob Duncan - Director, Site Operations
  • Abdy Khanpour - Manager, Engineering
  • Eric McCartney - Superintendent, Engineering
  • Terry Morton - Manager, Support Services
  • John Caves - Supervisor, Licensing
  • John Yadusky - Licensing Engineeer
  • George Attarian - Corporate Chief Engineer
  • Jeff Ertman - Corporate Fire Protection Engineer
  • Steve Laur - Supervisor, PSA
  1. 9 Progress Energy 2

I

Summary of Root Causes Io Original licensing mid 1980s P Errors in analysis i Separation issues resolved with using manual actions as the first choice

  • Abnormal Operating Procedure (AOP) for safe shutdown was arinIap-roncied for both MCR fire and plant area fires o Applied a rigorous validation process for remote shutdown manual actions

I 0 5-j V--

4 I 5;-

6,'e-,ZA ff4c

74-3;q I

'A 5,

~~~-- V W r, r -

z,&

S pa SeK-, valley -

e

--:

0744.-

Y-A-

H And-°

-I+~~~

~~~~~~~~~A d,<

7'0

~~~~6-a A -

-0

/6

~~~q~IP t

Fire Protection Hugo etive ctions;l Im med~~iate actions completed_'

/

Co Assigned 1 Additional SSD AO To Shift Jo/i De-energized MOVs Where Possible To Eliminate Hot Short Potential Removed plexiglas cover for TDAFW fuse A

>- identified issues By,,

fo9. 0,e7/AJSr

,"A~

'~-(A e

~~~~~~~~~~~~~~~~7 VBI

- 401; f-

=

(ID On-Shift Staffing I* Developed drill scenarios fo,C~fire area usng Plant Simulator_

l Conducted drill scenarios with spurious usactuations inserted for all 5 shifts with 1 Auxiliary Operator

/ All crews successful in achieving shutdownj-P Success defined by remote shutdown time line P Will validate all remaining fire areas Hi Progress Energy MA-

~~~~~~~~~~~~~~~~~~~~8

/

7Z.4,A4.

1,

I~

POD ( 0 5 s { eC/7 06 W.

W, //

k le.,e

e,1 sArJe W

p A

Project Plan p

Goals c

I. Restore compliance for identified A

Irl r

I

*w deficiencies

  • Fire Hazards Analysis design validation P SSA validation P Clear documentation of compliance

.{VYalidation of fire response ox', Design adequately reflected in operational 4 -esponse procedures

< Training l

Progress Energy 9

Iffirl (#"I 6- -

";t-7V

............ 0 Oo,(,.0



JI

/19 pfo--4 IV Project Plan Goals

  • Improve syseliiy o Valida ram o Optimize surveillances and testing
  • Improve self-evaluation Establish program health monitoring schedule that verifies design basis through implementation on a periodic basis A Progress Energy 10 e/ 4e,'Ile 57',rrc.e 4i4ve_6-~

4

Project Plan Schedule I* SSA validation i Contractor selection in progress i Begin prior to Ri 1

) Expected completion irfmid 2004 USA~5'--

J MG V Progress Energy 12 5

4-9,7 2115)t lCS-168 Ad N'*

4-

Resolution le Immediate Design Changes P Design in progress

  • VCT outlet valve cables, 1 CS-1 65 & 166
  • Prote6t CSIP flow paths in all fire events
  • Eliminale-manual actions in ACP fire area
  • Utilz Intear~m~fire wrap, qualified to GL 86-10, YHupp e standards E Evaluating MCC hot short solutions
  • Cable reroutes
  • Valve interlocks ffa a Progress Er J

r,(6-r'

V'01

.4

Design Validation I

  • Validation of SSA

) Develop safe shutdown equipment list

  • Select SSEL cables i Load cable database r ~

Utilize automated software analysis methods

i.

Progress Energy 14 WC 4/iCr 6

41 Additional Program Improvements I* Administrative controls

  • Training and Qualification
  • Program manager o General engineering populatiolnD--t o Operations crews 2

s

, Sac

  • Station management

)

S;+,_

,,, 1 BURG~~~~~~~

B ssnErgy?

P XAtl 4t

'/z

6 4

A-19-4r,

\\-

- 54"

4

Risk Insight Io Fire areas identified in findings, except ACP room, have full detection and suppression

  • Affected cable routes are greater than 20 feet from fixed ignition sources

-NC C Progress Energy 16 cr-%

44ze 7

a Summary l

Original design used manual actions instead of separation

  • HNP now understands regulatory requirements and safety impact of manual actions
  • Aggressively pursuing resolution of known issues and validation of remainder of analysis Propose quarterly update meetings with Region 11
  • HNP will update LER as necessary to include additional discovery 17 Nill I/4 f r bn A J-

=

8