ML033010295
| ML033010295 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 07/31/2003 |
| From: | Progress Energy Co |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| FOIA/PA-2003-0358, FOIA/PA-2004-0277 | |
| Download: ML033010295 (24) | |
Text
t
~~~~~* U.i Harris Nuclear Plant Safe Shutdown Validation Fire Protection Project Plan Nuclear (lJ\\ilGeneration W
Progress Energy
0
- Attendees I. Abdy Khanpour - Manager, Engineering
- John Caves - Supervisor, Licensing
. Tony Maness Supervisor, Fire Protection M. %
Progress Energy 2
I Agenda I
- Overview Of Fire Protection Inspection Findings, Root Causes, Corrective Actions
- SSA Validation Project
- Organization
) Goals
) Tasks
) Milestones
- Latest Discoveries M.
@J Progress Energy 3
I Focus Team l. Team Members o Supervisor P FP Program Manager
) SSA Program Manager
) Operations - STA
- FP Staff Augmentation Engineer
- Staff Augmentation Configuration Management
- Matrix additional staff as needed o Progress Energy Fleet Steering Committee Ag
$Progress Energy 4
S.,
Overview of Inspection Findings
- Failure To Protect Cables Potentially Affected By Fires
- Inconsistency Between Safe Shutdown Analysis And Implementing Procedure
- Some Non-feasible Manual Actions
- Technical Compliance o 8 Hr Battery Backed Emergency Lighting i Manual Actions Not Approved
< § Progress Energy 5
Summary of Root Causes l *Post-Fire Circuit Analysis
- Errors In Analysis o Procedures. Allowed Use Of Manual Action In Lieu Of Circuit Protection Fo'r 3.G.2 Fire Areas From Initial Plant Licensing Efforts In Remote Shutdown P HNP Understanding Of Standards For Acceptability, Of Manual Actions Changed In August 2002 based on industry OE (ANO and NRC/NEI meetings) sG -Progress Energy 6
Summary of Root Causes I
. Operational Implementation
) AOP-036, Safe Shutdown Validation
) Lack Of Specific Criteria For Manual Action Feasibility
- Assessments Focused On Conventional Fire Protection - Barriers, Detection, Suppression, Equipment Impairments M.,
Progress Energy 7
Fire Protection Corrective Actions I
. Immediate Actions Completed
) Established Fire Watch Identified Issues Coverage For
).Revised Safe Sh Procedures utdown Operating o Assigned 1 Additional Auxiliary Operator To Shift Staffing M De-Energized MOV (MCC-1 El Eliminate Hot Short Potential 2)To P Plexiglas Cover Removed For TDAFW Fuse M. %
Progress Energy 8
E.k -
I I
Project Plan Goals E
I. Validate SSA Design o Reduce Reliance On Manual Actions Correct Identified Deficiencies Ensure SSA Is Properly Reflected In Operating and Maintenance Procedures
) Configuration Controls Protects The.
Design Basis
- Improve Reliability Of Fire Protection Equipment C.
§J Progress Energy 9
Project Plan Goals (cont)
I
- Ensure SSA Is Consistent With Fleet Circuit Analysis On Multiple Circuit Failures dq. %
§j Progress Energy 10
Project Plan Tasks 1.
Sixteen Plan Tasks
- 1. Project Initiation
- 2. Modifications Proposed Modifications v Cable Protection v Circuits In MCCs v 8 Hour Battery Backed Lighting Progress Energy 11
Project Plan Tasks (cont)
- r.
I
- 2. Modifications (cont)
Modifications in Progress v ACP Room Cable Protection Remove Thermo-Lag Enclosure Add Fire Wrap to Cable Tray 6r v VCT Outlet Valve Cable Protection t1~~~.
i Armored Cable
. 0 el
(w"'I i
Reroute M.""G k4 Progress Energy 12
g a
I -
Project Plan Tasks (cont)
I
- 3. Oversight/Gap Analysis NGG Fleet FP Strategic Plan
- 4. SSA Validation Developed Project Scoping Document NE Selection idation S1-0 Kick Off Of Val' Major Milestones Additional Discoveries Document in Corrective Action Program
,,G Progress Energy 13
Project Plan Tasks (cont)
I
- 5. Thermo-Lag Configurations ACP Room V Current Modification 4 Cable Spread Room V Modification Completed C
Progress Energy 14
g Project Plan Tasks (cont)
- 6. Hemyc/MT Fire Barrier Wrap SSA Validation V Identify functions where protection is needed and Hemyc wrap is credited V Monitoring Industry and NRC testing
- 7. Fire Hazards Analysis (FHA)/SSA Integration Resolve Identified Deficiencies 8, NFPA Code Compliance Resolve Identified Deficiencies FI mProgress Energy 15
4 Project Plan Tasks (cont)
- 9.
Fire Protection QA Inspection Hold Point Identify Inspection Attributes V Update Implementing Procedures 1 0. Enhance Transient Combustible/Fixed Combustible Loading Controls SSA Integration Revise Combustible Control Program M.0
§A Progress Energy 16
Project Plan Tasks (cont)
I 1 1. Penetration Seals Improve program V Adopt Wisconsin Electric Internal Conduit Seal Testing V Enhanced Pen Seal Report Generation Tool T Drawing M.
-KI Progress Energy 17
~~~~~~~~~~~~~~~~~~*
Project Plan Tasks [cont)
- 12. Surveillance Optimization Evaluation And Improve Performance Based Assessment
- 13.
Miscellaneous FP Program Deficiencies Manage and Prioritize FP Backlog
- 14. Fire Response/Operational Implementation
+
Improve Operations Response To Fires
.j
@ Progress Energy 18
6 Project Plan Tasks (cont)
I 1 5v Effectiveness Review Self-Assessment
- 16. Allocation Of Funds Administrative J. %_
@i Progress Energy 19
Design Validation l
- Validation of SSA P Develop Safe Shutdown Equipment List
- Perform Circuit Analysis o Load SSD Program Manager Database o Perform Compliance Fault Tree Analysis o Manual Action Feasibility P Revise Safe Shutdown Procedure P Revise Admin Control Procedures CG
@Progress Energy 20
I ft b
I a
4 SSAIFire Protection Major Milestones Best Estimate SSA Tasks Start Finish o SSA Project Kick-Off Mtg 5/20/03 5/20/03
) Discovery Phase 6/9/03 1/5/04 P Manual Action Identification/Feasibility Analysis 10/17/03 3/9/04 r
- EC Approval 6/9/04 Q EC Turnover - Implementation Of New SSA 6/10/04 9/30/04
- 5/21/03 12/15/03
) Charging System 7/7/03 12/31/03 C
Progress Energy 21
1l s
U*X x
.a
-
Latest Discoveries 1 Current State:
- HNP SSD Analysis does not include components as part of the analysis.
o 1 CT-1 02 - Cnmt Sump To Cnmt Pump 1 B-SB Isol Vlv CIV Spray o 1 CT-1 05 - Cnmt Sump To Cnmt Spray Pump 1A-SA Isol Vlv CIV C
KI Progress Energy 22
g a
- t v6 Latest Discoveries l Real or Potential Consequences:
- Valves are required to remain shut to prevent transfer of water from the RWST to the containment recirculation sump.
- Water used for charging would not be available from its alternate suction source (i.e., the RWST) credited by the SSA.
CG
§Progress Energy 23
S X) 4
SUMMARY
- 1. HNP is committed to resolving Fire Protection Program and Safe Shut Down Program concerns C
Progress Energy 24