ML033010295

From kanterella
Jump to navigation Jump to search
Slides for Harris Nuclear Plant Safe Shutdown Validation Fire Protection Project Plan Meeting
ML033010295
Person / Time
Site: Harris 
Issue date: 07/31/2003
From:
Progress Energy Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0358, FOIA/PA-2004-0277
Download: ML033010295 (24)


Text

t

~~~~~* U.i Harris Nuclear Plant Safe Shutdown Validation Fire Protection Project Plan Nuclear (lJ\\ilGeneration W

Progress Energy

0

  • Attendees I. Abdy Khanpour - Manager, Engineering
  • John Caves - Supervisor, Licensing

. Tony Maness Supervisor, Fire Protection M. %

Progress Energy 2

I Agenda I

  • Overview Of Fire Protection Inspection Findings, Root Causes, Corrective Actions
  • SSA Validation Project
  • Organization

) Goals

) Tasks

) Milestones

  • Latest Discoveries M.

@J Progress Energy 3

I Focus Team l. Team Members o Supervisor P FP Program Manager

) SSA Program Manager

) Operations - STA

  • FP Staff Augmentation Engineer
  • Staff Augmentation Configuration Management
  • Matrix additional staff as needed o Progress Energy Fleet Steering Committee Ag

$Progress Energy 4

S.,

Overview of Inspection Findings

  • Failure To Protect Cables Potentially Affected By Fires
  • Inconsistency Between Safe Shutdown Analysis And Implementing Procedure
  • Some Non-feasible Manual Actions
  • Technical Compliance o 8 Hr Battery Backed Emergency Lighting i Manual Actions Not Approved

< § Progress Energy 5

Summary of Root Causes l *Post-Fire Circuit Analysis

  • Errors In Analysis o Procedures. Allowed Use Of Manual Action In Lieu Of Circuit Protection Fo'r 3.G.2 Fire Areas From Initial Plant Licensing Efforts In Remote Shutdown P HNP Understanding Of Standards For Acceptability, Of Manual Actions Changed In August 2002 based on industry OE (ANO and NRC/NEI meetings) sG -Progress Energy 6

Summary of Root Causes I

. Operational Implementation

) AOP-036, Safe Shutdown Validation

) Lack Of Specific Criteria For Manual Action Feasibility

  • Assessments Focused On Conventional Fire Protection - Barriers, Detection, Suppression, Equipment Impairments M.,

Progress Energy 7

Fire Protection Corrective Actions I

. Immediate Actions Completed

) Established Fire Watch Identified Issues Coverage For

).Revised Safe Sh Procedures utdown Operating o Assigned 1 Additional Auxiliary Operator To Shift Staffing M De-Energized MOV (MCC-1 El Eliminate Hot Short Potential 2)To P Plexiglas Cover Removed For TDAFW Fuse M. %

Progress Energy 8

E.k -

I I

Project Plan Goals E

I. Validate SSA Design o Reduce Reliance On Manual Actions Correct Identified Deficiencies Ensure SSA Is Properly Reflected In Operating and Maintenance Procedures

) Configuration Controls Protects The.

Design Basis

  • Improve Reliability Of Fire Protection Equipment C.

§J Progress Energy 9

Project Plan Goals (cont)

I

  • Position HNP For Potential Future Development Of A Fire PRA
  • Ensure SSA Is Consistent With Fleet Circuit Analysis On Multiple Circuit Failures dq. %

§j Progress Energy 10

Project Plan Tasks 1.

Sixteen Plan Tasks

1. Project Initiation
2. Modifications Proposed Modifications v Cable Protection v Circuits In MCCs v 8 Hour Battery Backed Lighting Progress Energy 11

Project Plan Tasks (cont)

r.

I

2. Modifications (cont)

Modifications in Progress v ACP Room Cable Protection Remove Thermo-Lag Enclosure Add Fire Wrap to Cable Tray 6r v VCT Outlet Valve Cable Protection t1~~~.

i Armored Cable

. 0 el



(w"'I i

Reroute M.""G k4 Progress Energy 12

g a

I -

Project Plan Tasks (cont)

I

3. Oversight/Gap Analysis NGG Fleet FP Strategic Plan
4. SSA Validation Developed Project Scoping Document NE Selection idation S1-0 Kick Off Of Val' Major Milestones Additional Discoveries Document in Corrective Action Program

,,G Progress Energy 13

Project Plan Tasks (cont)

I

5. Thermo-Lag Configurations ACP Room V Current Modification 4 Cable Spread Room V Modification Completed C

Progress Energy 14

g Project Plan Tasks (cont)

6. Hemyc/MT Fire Barrier Wrap SSA Validation V Identify functions where protection is needed and Hemyc wrap is credited V Monitoring Industry and NRC testing
7. Fire Hazards Analysis (FHA)/SSA Integration Resolve Identified Deficiencies 8, NFPA Code Compliance Resolve Identified Deficiencies FI mProgress Energy 15

4 Project Plan Tasks (cont)

9.

Fire Protection QA Inspection Hold Point Identify Inspection Attributes V Update Implementing Procedures 1 0. Enhance Transient Combustible/Fixed Combustible Loading Controls SSA Integration Revise Combustible Control Program M.0

§A Progress Energy 16

Project Plan Tasks (cont)

I 1 1. Penetration Seals Improve program V Adopt Wisconsin Electric Internal Conduit Seal Testing V Enhanced Pen Seal Report Generation Tool T Drawing M.

-KI Progress Energy 17

~~~~~~~~~~~~~~~~~~*

Project Plan Tasks [cont)

12. Surveillance Optimization Evaluation And Improve Performance Based Assessment
13.

Miscellaneous FP Program Deficiencies Manage and Prioritize FP Backlog

14. Fire Response/Operational Implementation

+

Improve Operations Response To Fires

.j

@ Progress Energy 18

6 Project Plan Tasks (cont)

I 1 5v Effectiveness Review Self-Assessment

16. Allocation Of Funds Administrative J. %_

@i Progress Energy 19

Design Validation l

  • Perform Circuit Analysis o Load SSD Program Manager Database o Perform Compliance Fault Tree Analysis o Manual Action Feasibility P Revise Safe Shutdown Procedure P Revise Admin Control Procedures CG

@Progress Energy 20

I ft b

I a

4 SSAIFire Protection Major Milestones Best Estimate SSA Tasks Start Finish o SSA Project Kick-Off Mtg 5/20/03 5/20/03

) Discovery Phase 6/9/03 1/5/04 P Manual Action Identification/Feasibility Analysis 10/17/03 3/9/04 r

  • EC Approval 6/9/04 Q EC Turnover - Implementation Of New SSA 6/10/04 9/30/04
  • Self-Assessment Of New SSA 7/25/05 9/25/05 Cable Protection Mods P ACP Room
5/21/03 12/15/03

) Charging System 7/7/03 12/31/03 C

Progress Energy 21

1l s

U*X x

.a

-

Latest Discoveries 1 Current State:

  • HNP SSD Analysis does not include components as part of the analysis.

o 1 CT-1 02 - Cnmt Sump To Cnmt Pump 1 B-SB Isol Vlv CIV Spray o 1 CT-1 05 - Cnmt Sump To Cnmt Spray Pump 1A-SA Isol Vlv CIV C

KI Progress Energy 22

g a

  • t v6 Latest Discoveries l Real or Potential Consequences:
  • Valves are required to remain shut to prevent transfer of water from the RWST to the containment recirculation sump.
  • Spurious opening could result in inadvertently transferring water from the RWST to the sump.
  • Water used for charging would not be available from its alternate suction source (i.e., the RWST) credited by the SSA.

CG

§Progress Energy 23

S X) 4

SUMMARY

1. HNP is committed to resolving Fire Protection Program and Safe Shut Down Program concerns C

Progress Energy 24