Receipt of Availability of the License Renewal Application for the Arkansas Nuclear One, Unit 2
ML032940160
Person / Time
Site: Arkansas Nuclear 
(NPF-006)
Issue date: 10/21/2003
From: Kuo P
Division of Regulatory Improvement Programs
To: Anderson C
Entergy Operations
Anand R NRR/DRIP/RLEP, 415-1146
References
Download: ML032940160 (7)


Text

October 21, 2003 Mr. Craig G. Anderson Vice President, Operations ANO Entergy Operations, Inc.

1448 S. R. 333 Russellville, AR 72801

SUBJECT:

RECEIPT AND AVAILABILITY OF THE LICENSE RENEWAL APPLICATION FOR THE ARKANSAS NUCLEAR ONE, UNIT 2

Dear Mr. Anderson:

On October 15, 2003, the staff of the U.S. Nuclear Regulatory Commission (NRC) received the Entergy Operations, Inc. application for renewal of Operating License NPF-6 for the Arkansas Nuclear One, Unit 2. We are currently performing an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101, and will notify you of the results of our review. A schedule for the review will be provided at the time the application is determined acceptable for docketing.

We have enclosed for your information a copy of the notice relating to your application that is being sent to the Office of the Federal Register for publication.

I am pleased to announce the appointment of Gregory Suber as the project manager for the safety review and Thomas Kenyon as the project manager for the environmental review of your license renewal application. Please forward copies of all license renewal correspondence to Mr. Suber.

Mr. Thomas W. Alexion continues to remain responsible for NRC project management of all issues other than license renewal for Arkansas Nuclear One, Unit 2.

If you have any questions on this matter, please contact Mr. Gregory Suber by telephone at 301-415-1124 or via electronic mail at gxs@nrc.gov.

Sincerely,

/RA/

Pao-Tsin Kuo, Program Director License Renewal and Environmental Impacts Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-368

Enclosure:

As stated cc w/enclosure: See next page

October 21, 2003 Mr. Craig G. Anderson Vice President, Operations ANO Entergy Operations, Inc.

1448 S. R. 333 Russellville, AR 72801

SUBJECT:

RECEIPT AND AVAILABILITY OF THE LICENSE RENEWAL APPLICATION FOR THE ARKANSAS NUCLEAR ONE, UNIT 2

Dear Mr. Anderson:

On October 15, 2003, the staff of the U.S. Nuclear Regulatory Commission (NRC) received the Entergy Operations, Inc. application for renewal of Operating License NPF-6 for the Arkansas Nuclear One, Unit 2. We are currently performing an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101, and will notify you of the results of our review.

A schedule for the review will be provided at the time the application is determined acceptable for docketing.

We have enclosed for your information a copy of the notice relating to your application that is being sent to the Office of the Federal Register for publication.

I am pleased to announce the appointment of Gregory Suber as the project manager for the safety review and Thomas Kenyon as the project manager for the environmental review of your license renewal application. Please forward copies of all license renewal correspondence to Mr. Suber.

Mr. Thomas W. Alexion continues to remain responsible for NRC project management of all issues other than license renewal for Arkansas Nuclear One, Unit 2.

If you have any questions on this matter, please contact Mr. Gregory Suber by telephone at 301-415-1124 or via electronic mail at gxs@nrc.gov.

Sincerely,

/RA/

Pao-Tsin Kuo, Program Director License Renewal and Environmental Impacts Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-368

Enclosure:

As stated cc w/enclosure: See next page DISTRIBUTION:

See next page Accession no.: ML032940160

  • See Previous Concurrence C:\\ORPCheckout\\FileNET\\ML032940160.wpd OFFICE PM:RLEP LA:RLEP PM:RLEP SC:RLEP OGC PD:RLEP NAME RAnand*

LJenkins*

GSuber*

SLee*

RHoefling*

PTKuo DATE 10/20/03 10/20/03 10/20/03 10/20/03 10/20/03 10/21/03 OFFICIAL RECORD COPY

DISTRIBUTION: Letter to Craig Anderson w/FRN, Dated: October 21, 2003 Accession no.: ML032940160 HARD COPY RLEP RF R. Anand G. Suber E-MAIL:

PUBLIC W. Borchardt D. Matthews F. Gillespie RidsNrrDe R. Barrett E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden H. Nieh G. Holahan H. Walker S. Black B. Boger D. Thatcher G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Smith (srs3)

T. Kobetz R. Assa C. Munson RLEP Staff

7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION ENTERGY OPERATIONS, INC.

NOTICE OF RECEIPT OF APPLICATION FOR RENEWAL OF FACILITY OPERATING LICENSE No. NPF-6 FOR AN ADDITIONAL 20-YEAR PERIOD DOCKET NO. 50-368 The U.S. Nuclear Regulatory Commission (NRC or Commission) has received an application, dated October 14, 2003, from the Entergy Operations, Inc., filed pursuant to Section 104b of the Atomic Energy Act of 1954, as amended, and 10 CFR Part 54, to renew Operating License No. NPF-6 for the Arkansas Nuclear One, Unit 2. Renewal of the license would authorize the applicant to operate the facility for an additional 20-year period. The current operating license for the Arkansas Nuclear One, Unit 2, expires on July 17, 2018. The Arkansas Nuclear One, Unit 2, is a pressurized-water reactor designed by Combustion Engineering Company and is located in Pope County, Arkansas. The acceptability of the tendered application for docketing, and other matters including an opportunity to request for a hearing, will be addressed in subsequent Federal Register notices.

Copies of the application are available for public inspection at the Commissions Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor),

Rockville, Maryland, or electronically from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS) under accession number ML032890483. The ADAMS Public Electronic Reading Room is accessible from the NRC web site at http://www.nrc.gov/reading-rm/adams.html. In addition, the application is available on the NRC web page at http://www.nrc.gov/reactors/operating/licensing/renewal/applications.html,

2 while the application is under review. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRCs PDR Reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr@nrc.gov.

The license renewal application is also available to local residents near the Arkansas Nuclear One at the Ross Pendergraft Library and Technology Center at the Arkansas Tech University in Russellville, Arkansas.

Dated at Rockville, Maryland, this 21st day of October 2003.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Pao-Tsin Kuo, Program Director License Renewal and Environmental Impacts Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation

Arkansas Nuclear One, Unit 2 cc:

Executive Vice President

& Chief Operating Officer Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Director, Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Winston & Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Mr. Mike Schoppman Framatome ANP, Richland, Inc.

Suite 705 1911 North Fort Myer Drive Rosslyn, VA 22209 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 72801 Vice President, Operations Support Entergy Operations, Inc.

P. O. Box 31995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 Garry Young 1448 SR 333 Russellville, AR 72802 Mr. Fred Emerson Nuclear Energy Institute 1776 I St., N.W., Suite 400 Washington, DC 20006-3708