September 11, 2003 LICENSEE:
Arizona Public Service Company (APS)
FACILITIES:
Palo Verde Nuclear Generating Station
SUBJECT:
MEETING WITH REPRESENTATIVES OF ARIZONA PUBLIC SERVICE COMPANY FOR PALO VERDE NUCLEAR GENERATING STATION, UNIT 2 (TAC NO. MB3696)
A meeting was held on Thursday, June 26, 2003, between the Nuclear Regulatory Commission (NRC) staff and the licensee for Palo Verde Nuclear Generating Station, Unit 2 (PVNGS-2).
The meeting was held at the request of the licensee. The notice for the meeting was issued on June 2, 2003, and stated that there may be discussions on proprietary information presented by the licensee during the meeting. is the list of attendees. Enclosure 2 is the handout from the licensee.
BACKGROUND The licensee submitted an application dated December 21, 2001, to amend the Technical Specifications for PVNGS-2 in support of the replacement steam generators and subsequent operation at an increased maximum power level of 3990 MWt, a 2.94 percent increase from the current 3876 MWt. The application was for a power uprate (PUR) of 2.94 percent.
In the staffs review of the licensees application, as supplemented by letters dated March 13, August 27, August 29, September 4, September 6, October 11, December 10, and December 23, 2002, and March 11, 2003, it identified a concern related to the small break loss-of-coolant accident (SBLOCA) analyses for PVNGS-2 at the increased power level of 3990 MWt. In its submittal dated October 11, 2002, the licensee provided results of the SBLOCA analyses using CENPD-137, Supplement 2-P-A, "Calculative Methods for the ABB CE Small Break LOCA Evaluation Model," dated April 1998 (the S2M methodology). This S2M methodology was approved for use by PVNGS-2 in Amendment 140 issued March 12, 2002.
The amendment added CENPD-404-P-A, "Implementation of ZIRLO Cladding Material in CE Nuclear Power Fuel Assembly Designs," dated September 12, 2001, which includes the S2M methodology, to the core operating limits report of the Technical Specifications. This S2M methodology superseded the previously approved SBLOCA methodology for PVNGS-2 in CENPD-137, Supplement 1-P-A, "Calculative Methods for the CE Small Break LOCA Evaluation Model," dated January 1977 (the S1M methodology).
The NRC staffs concern was that the approval of the S2M methodology did not cover power levels above the current 3876 MWt, for PVNGS-2 up to the proposed power level of 3990 MWt.
The licensee requested the meeting to address the NRC staffs concern.
MEETING
SUMMARY
The agenda for the meeting was the following:
Introduction Westinghouse S2M Methodology for SBLOCA Information Needed by the Staff NRC staff caucus Conclusion The introduction by the licensee is given in Enclosure 2. The licensee provided a background to the meeting, its goals for the meeting, and what it believed was the success path to achieving the stated goals.
The licensee presented proprietary information addressing the NRC staff's review of the S2M methodology, which was approved in the NRC staff's letter dated December 16, 1997. The licensee stated that the information is from CENPD-137, Supplement 2-P-A, the proprietary topical report on the S2M methodology. The differences between the S1M and S2M methodologies, and the sensitivity study comparing the two methodologies that was used during the NRC staffs review of the S2M methodology were presented. The specific results of the sensitivity study for (1) the standard plant in CENPD-137, Supplement 2-P-A, at the power level in the topical report, which is less than the PVNGS-2 PUR, and (2) PVNGS-2 at the PUR power level were also presented.
The NRC staff did not accept the proprietary information from the licensee because it did not want the meeting to be the means by which the information addressing its concern on S2M at the PVNGS-2 PUR power level is submitted on the PVNGS-2 docket. The NRC staff, however, did conclude from the meeting that the information presented in the meeting did address its concern about the use of the S2M methodology for the PVNGS-2 PUR. It requested that the licensee submit the information so that the staff could address the concern in the Safety Evaluation for the proposed amendment. The licensee agreed to submit the information.
The licensee completed its presentation and the meeting was adjourned.
/RA/
Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-529
Enclosures:
- 1. List of Meeting Attendees
- 2. Licensee Handout cc w/encls: See next page
ML032541113 NRC-001 OFFICE PDIV-2/PM PDIV-1/LA SRXB PDIV-2/SC NAME JDonohew:sab MMcAllister JUhle SDembek DATE 9/9/2003 9/5/03 9/8/03 9/10/03 LIST OF ATTENDEES AT MEETING OF JUNE 26, 2003 EXPECTATIONS OF AND INFORMATION NEEDED BY NRC STAFF CPC UPGRADE LICENSE AMENDMENT REQUEST REVIEW NAME AFFILIATION J. Donohew NRC/NRR/PDIV-2 H. Berkow NRC/NRR/PDIV B. Benney NRC/NRR/PDIV-2 F. Akstulewicz NRC/NRR/SRXB J. Uhle NRC/NRR/SRXB F. Orr NRC/NRR/SRXB S. Bauer APS T. Weber APS P. Crawley APS K. Greenspan APS M. Golbabai Westinghouse E. Jageler Westinghouse M. Gancavz Westinghouse J. Cleary Westinghouse Where:
= Arizona Public Service Company NRC
= Nuclear Regulatory Commission NRR
= Office of Nuclear Reactor Regulation PDIV-2
= Project Directorate IV, Section 2 SRXB
= Reactor Systems Branch LICENSEE HANDOUT FOR JUNE 26, 2003, MEETING ADAMS ACCESSION NO. ML031880484
Palo Verde Generating Station, Unit 2 cc:
Mr. Steve Olea Arizona Corporation Commission 1200 W. Washington Street Phoenix, AZ 85007 Douglas Kent Porter Senior Counsel Southern California Edison Company Law Department, Generation Resources P.O. Box 800 Rosemead, CA 91770 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 40 Buckeye, AZ 85326 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavillion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Chairman Maricopa County Board of Supervisors 301 W. Jefferson, 10th Floor Phoenix, AZ 85003 Mr. Aubrey V. Godwin, Director Arizona Radiation Regulatory Agency 4814 South 40 Street Phoenix, AZ 85040 Mr. Craig K. Seaman, Director Regulatory Affairs/Nuclear Assurance Palo Verde Nuclear Generating Station P.O. Box 52034 Phoenix, AZ 85072-2034 Mr. Hector R. Puente Vice President, Power Generation El Paso Electric Company 2702 N. Third Street, Suite 3040 Phoenix, AZ 85004 Mr. John Taylor Public Service Company of New Mexico 2401 Aztec NE, MS Z110 Albuquerque, NM 87107-4224 Ms. Cheryl Adams Southern California Edison Company 5000 Pacific Coast Hwy Bldg DIN San Clemente, CA 92672 Mr. Robert Henry Salt River Project 6504 East Thomas Road Scottsdale, AZ 85251 Terry Bassham, Esq.
General Counsel El Paso Electric Company 123 W. Mills El Paso, TX 79901 Mr. John Schumann Los Angeles Department of Water & Power Southern California Public Power Authority P.O. Box 51111, Room 1255-C Los Angeles, CA 90051-0100 Brian Almon Public Utility Commission William B. Travis Building P. O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Mr. Gregg R. Overbeck Senior Vice President, Nuclear Arizona Public Service Company P. O. Box 52034 Phoenix, AZ 85072-2034