ML032200274
ML032200274 | |
Person / Time | |
---|---|
Site: | Harris |
Issue date: | 07/31/2003 |
From: | Progress Energy Co |
To: | Office of Nuclear Reactor Regulation |
References | |
FOIA/PA-2004-0277 | |
Download: ML032200274 (24) | |
Text
Harris Nuclear Plant Safe Shutdown Validation Fire Protection Project Plan Nuclear Geiieratioii Group Progress Energy L O Enclosure 2
Attendees I Abdy Khanpour - Manager, Engineering John Caves - Supervisor, Licensing Tony Maness - Supervisor, Fire Protection qProgress Energy
$J Q
2
Agenda I Overview Of Fire Protection Inspection Findings, Root Causes, Corrective Actions SSA Validation Project D Organization D Goals D Tasks D Milestones Latest Discoveries 6- eProgress b , Energy 3
Focus Team 10 Team Members B Supervisor B FP Program Manager B SSA Program Manager B Operations - STA B FP Staff Augmentation Engineer B Staff Augmentat ion Configuration Management B Matrix additional staff as needed B Progress Energy Fleet Steering Committee 61- Progress Energy 4
Overview of Inspection Findings 0 Failure To Protect Cables Potentially Affected By Fires Inconsistency Between Safe Shutdown Analysis And Implementing Procedure Some Non-feasible Manual Actions Technical Compliance D 8 Hr Battery Backed Emergency Lighting D Manual Actions Not Approved a Progress Energy 5
Summary of Root Causes I o Post-Fire Circuit Analysis D Errors In Analysis B Procedures Allowed Use Of Manual Action In Lieu Of Circuit Protection For 3.G.2 Fire Areas From Initial Plant Licensing Efforts In Remote Shutdown D HNP Understanding Of Standards For Acceptability Of Manual Actions Changed In August 2002 based on industry OE (AN0 and NRC/NEI meetings)
+FProgress Energy
~2~
6
Summary of Root Causes 10 Operational Implementation D AOP-036, Safe Shutdown Validation D Lack Of Specific Criteria For Manual Action FeasibiIity Assessments Focused On Conventional Fire Protection - Barriers, Detection, Suppression, Equipment Impairments
$9progress Energy 7
Fire Protection Corrective Actions I Immediate Actions Completed B Established Fire Watch Coverage For ldentified Issues B Revised Safe Shutdown Operating Procedures Assi ned 1 Additional Auxiliary Operator B
7l To S ift Staffing B
6 De-Energized MOV MCC-1E l 2) To Eliminate Hot Short otential B Plexiglas Cover Removed For TDAFW Fuse p progress Energy
$ : Q 8
Project Plan Goals 10 Validate SSA Design B Reduce Reliance On Manual Actions B Correct Identified Deficiencies B Ensure SSA Is Properly Reflected In Operating and Maintenance Procedures B Configuration Controls Protects The Design Basis 0 Improve Reliability Of Fire Protection Equipment 6
q kiJ ProgressEnergy 9
Project Plan Goals (cont)
.1
~
Position HNP For Potential Future Development Of A Fire PRA 0 Ensure SSA Is Consistent With Fleet Circuit Analysis On Multiple Circuit Failures 6-b: Progress Energy 10
Project Plan Tasks
=Sixteen Plan Tasks
- 1. Project Initiation
- 2. Modifications
+ Proposed Modifications v Cable Protection v Circuits In MCCs v 8 Hour Battery Backed Lighting a Progress Energy 11
Project Plan Tasks (cont)
- 2. Modifications (cont)
+ Modifications in Progress v ACP Room Cable Protection I Remove Thermo-Lag Enclosure I Add Fire Wrap to Cable Tray v VCT Outlet Valve Cable Protection I Armored Cable I Reroute tb*r,: progress Energy 12
Project Plan Tasks (cont)
- 3. Oversight/Gap Analysis 4 NGG Fleet FP Strategic Plan
- 4. SSA Validation 4 Developed Project Scoping Document 4 N E Selection 4 Kick Off Of Validation 4 Major Milestones 4 Additional Discoveries V Document in Corrective Action Program 6 Progress Energy w,.
13
Project Plan Tasks (cont)
- 5. Thermo-Lag Configurations
+ ACPRoom V Current Modification
+ Cable Spread Room V Modification Completed 6- Progress Energy ukl 14
Project Plan Tasks (cont)
~~~~~~
I 6. HemydMT Fire Barrier Wrap
+ SSA Validation V Identify functions where protection is needed and Hemyc wrap is credited V Monitoring Industry and NRC testing
- 7. Fire Hazards Analysis (FHA)/SSA Integration
+ Resolve Identified Deficiencies
- 8. NFPA Code Compliance
+ Resolve Identified Deficiencies
- Progress Energy b14 15
Project Plan Tasks (cont)
Fire Protection QA Inspection Hold Point
+ Identify Inspection Attributes V Update Implementing Procedures IO. Enhance Transient Combustible/Fixed Combustible Loading Controls
+ SSA Integration
+ Revise Combustible Control Program 64-"
Q-Progress Energy 16
Project Plan Tasks (cont)
I I I . Penetration Seals
+ Improve program I Adopt Wisconsin Electric Internal Conduit Seal Testing I Enhanced Pen Seal Report Generation Tool I Drawing 6- 2Progress
~ ) Energy 17
Project Plan Tasks (cont) rp-+
I 2. Surveillance Optimization Evaluation And Improve
+ Performance Based Assessment
- 13. Miscellaneous FP Program Deficiencies
+ Manage and Prioritize FP Backlog
- 14. Fire Response/Operational Implementation
+ Improve Operations Response To Fires ui8 6 .Progress Energy 18
Project Plan Tasks (cont)
I I 15. Effectiveness Review
+ Self-Assessment
- 16. Allocation Of Funds
+ Administrative 6h
?? Progress Energy 19
Design Validation Validation of SSA D Develop Safe Shutdown Equipment List D Perform Circuit Analysis D Load SSD Program Manager Database D Perform Compliance Fault Tree Analysis D Manual Action Feasibility D Revise Safe Shutdown Procedure D Revise Admin Control Procedures 6-&s Progress Energy 20
SSNFire Protection Major Milestones Best Estimate B SSA Project Kick-Off Mtg 5/20/03 5/20/03 B Discovery Phase 6/9/03 1/5/04 B Manual Action Identification/Feasibility Analysis 10/17/03 3/9/04 I B EC Approval -- I 6/9/04 I B EC Turnover - Implementation Of New SSA 6/10/04 I 9/30/04 I B Self-Assessment Of New SSA FCable Protection Mods I I B ACP Room 5/2 1/03 12/15/03 B Charging System 7/7/03 12/3 1/03 Progress Energy L.
21
Latest Discoveries Current State:
HNP SSD Analysis does not include components as part of the analysis.
B ICT-102 - Cnmt Sump To Cnmt Spray Pump 16-SB lsol Vlv CIV B ICT-105 - Cnmt Sump To Cnmt Spray Pump 1A-SA lsol Vlv CIV
$- Progress Energy b~
22
Latest Discoveries I Real or Potential Consequences:
0 Valves are required to remain shut to prevent transfer of water from the RWST to the containment recirculation sump.
Spurious opening could result in inadvertent Iy t ransferring water from the RWST to the sump.
Water used for charging would not be available from its alternate suction source (i.e., the RWST) credited by the SSA.
g q Progress Energy
~2 23
SUMMARY
~
L H N P is committed to resolving Fire Protection Program and Safe Shut Down Program concerns
$?3 Progress Energy bb+
24