|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] Category:Report
MONTHYEAR3F0324-03, Enclosures 10 - 17: Crystal River, Unit 3, Response to Request for Additional Information2024-03-31031 March 2024 Enclosures 10 - 17: Crystal River, Unit 3, Response to Request for Additional Information ML24090A0042024-03-29029 March 2024 Enclosure 6, Part 1: Crystal River, Unit 3 - Appendix E – CHAR-05 Site Characterization of Buildings ML24030A7472024-02-13013 February 2024 Audit Report Attachment - Crystal River Unit 3 Nuclear Generating Plant LTP ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24090A0052023-10-10010 October 2023 Enclosure 6, Part 2: Crystal River, Unit 3, DD Survey 23-10-0096 ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23160A2972023-06-0909 June 2023 CR3 Site Characterization Survey Report (CHAR-01) Impacted Open Land Survey Areas 3F0623-02, Maintenance Support Building2023-06-0909 June 2023 Maintenance Support Building ML23160A2982023-06-0909 June 2023 Site Characterization Surveys ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 3F0522-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20222022-05-17017 May 2022 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2022 3F0520-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20202020-05-18018 May 2020 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2020 3F0320-01, NRC Commitment Change Report - March 20202020-03-17017 March 2020 NRC Commitment Change Report - March 2020 ML19343A8252019-12-0606 December 2019 Letter from Erika Bailey, Oak Ridge Institute for Science and Education, to John Hickman, NRC, Forwarding Independent Confirmatory Survey Summary and Results for the 3,854-Acre Area Partial Site Release at the Crystal River Energy Complex ML19022A0762019-01-22022 January 2019 Partial Site Release Request ML19029A0092018-11-0707 November 2018 Reference 16 - Defueled Safety Analysis Report DSAR-R002 ML18303A2942018-06-21021 June 2018 Golder Associates, Inc. - Citrus Combined Cycle Project - CFR 122.21(r) Report 3F0518-03, Safety Analysis Report and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20182018-05-24024 May 2018 Safety Analysis Report and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2018 ML16176A3392016-10-28028 October 2016 Decommissioning Lessons Learned Report and Transmittal Memorandum ML19029A0102016-06-28028 June 2016 Reference 3 - Crystal River, Unit 3, Historical Site Assessment Rev. 00 3F0616-02, Nrg Commitment Change Report - June 20162016-06-14014 June 2016 Nrg Commitment Change Report - June 2016 ML13343A1782013-12-31031 December 2013 Report P23-1680-001, Rev. 0, Site-Specific Decommissioning Cost Estimate for Crystal River Unit 3 Nuclear Generating Plant. 3F0113-08, Attachment D: ANP-3195(NP), Revision 0, Response for Crystal River Unit 3, EPU Licensing Amendment Report NRC Reactor Systems Branch Requests for Additional Information (Non-Proprietary) and Attachment E: Location of Reactor Systems RAI Re2013-01-31031 January 2013 Attachment D: ANP-3195(NP), Revision 0, Response for Crystal River Unit 3, EPU Licensing Amendment Report NRC Reactor Systems Branch Requests for Additional Information (Non-Proprietary) and Attachment E: Location of Reactor Systems RAI Res 3F1112-01, Alion Technical Report ALION-PLN-ENER-8706-02, Rev. 0, Crystal River 3: Bypass Fiber Quantity Test Plan2012-11-0707 November 2012 Alion Technical Report ALION-PLN-ENER-8706-02, Rev. 0, Crystal River 3: Bypass Fiber Quantity Test Plan 3F1112-02, 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 2502012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 250 ML12314A3932012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 81 of 250 Through Page 173 of 250 ML12314A3922012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 1 of 250 Through Page 80 of 250 3F0912-01, ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C2012-09-30030 September 2012 ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip.2012-06-30030 June 2012 Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip. ML12314A3912012-05-31031 May 2012 17877-0002-100, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment 2 ML12205A3582012-05-31031 May 2012 Attachment D to 3F0712-03, Technical Report, ANP-3114(NP), Rev. 0, CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies. ML12284A1382012-05-25025 May 2012 Report EGS-TR-HC589-01, Seismic Qualification Test Report for Structural Verification Testing of Iccms Cabinet Assembly. 3F0512-01, NRC Commitment Change Report - May 20122012-05-14014 May 2012 NRC Commitment Change Report - May 2012 3F0112-04, Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR2012-01-0505 January 2012 Response to Request for Additional Information to Support NRC Steam Generator Tube Integrity and Chemical Engineering Branch Technical Review of the CR-3 Extended Power Uprate LAR ML12205A3572011-12-15015 December 2011 Attachment a to 3F0712-03, CR-3 LOCA Summary Report - EPU/ROTSG/Mark-B-HTP, Revision 4 3F1211-14, Summary of Changes to Evaluation Models and Peak Cladding Temperature for Large Break Loss of Coolant Analysis and Small Break Loss of Coolant Analysis2011-12-14014 December 2011 Summary of Changes to Evaluation Models and Peak Cladding Temperature for Large Break Loss of Coolant Analysis and Small Break Loss of Coolant Analysis 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip2011-10-25025 October 2011 ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip ML11237A0682011-08-0505 August 2011 Siemens Technical Report CT-27438, Missile Probability Analysis Report Progress Energy Crystal River 3, Revision 1A ML11207A4442011-06-15015 June 2011 Attachment 7- Crystal River Unit 3 Extended Power Uprate Technical Report 3F0511-02, Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models2011-05-0606 May 2011 Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models ML1101906672010-10-0404 October 2010 Levy, Units 1 and 2, Cola (Sensitive Material), Rev. 2 - Levy County Emergency Plan Part 02 - Draft (Redacted) 3F0910-01, CFR 50.46 Notification of Change in Peak Cladding Temperature for Small Break Loss of Coolant Accident Analysis2010-09-0808 September 2010 CFR 50.46 Notification of Change in Peak Cladding Temperature for Small Break Loss of Coolant Accident Analysis ML1019304172010-05-0606 May 2010 Tritium Database Report ML1010603472010-04-0909 April 2010 5.2.2.4.4. Quality Control and Nondestructive Testing ML1028710882010-03-12012 March 2010 7.6 Vibration Due to Cutting Tendons ML1028711112010-02-25025 February 2010 7.11 Added Stress from Pulling Tendons ML1028711102010-02-23023 February 2010 6.3 Thermal Effects of Greasing ML1028804682010-02-19019 February 2010 7.9 Inadequate Hydro Blasting Nozzles Rate Part 3 ML1028711212010-02-19019 February 2010 7.10 Hydrodemolition Induced Cracking 2024-03-31
[Table view] Category:Technical
MONTHYEAR3F0324-03, Enclosures 10 - 17: Crystal River, Unit 3, Response to Request for Additional Information2024-03-31031 March 2024 Enclosures 10 - 17: Crystal River, Unit 3, Response to Request for Additional Information ML24090A0042024-03-29029 March 2024 Enclosure 6, Part 1: Crystal River, Unit 3 - Appendix E – CHAR-05 Site Characterization of Buildings ML24030A7472024-02-13013 February 2024 Audit Report Attachment - Crystal River Unit 3 Nuclear Generating Plant LTP ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24090A0052023-10-10010 October 2023 Enclosure 6, Part 2: Crystal River, Unit 3, DD Survey 23-10-0096 3F0623-02, Maintenance Support Building2023-06-0909 June 2023 Maintenance Support Building ML23160A2982023-06-0909 June 2023 Site Characterization Surveys ML23160A2972023-06-0909 June 2023 CR3 Site Characterization Survey Report (CHAR-01) Impacted Open Land Survey Areas ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 3F0522-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20222022-05-17017 May 2022 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2022 3F0520-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20202020-05-18018 May 2020 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2020 3F0320-01, NRC Commitment Change Report - March 20202020-03-17017 March 2020 NRC Commitment Change Report - March 2020 ML19343A8252019-12-0606 December 2019 Letter from Erika Bailey, Oak Ridge Institute for Science and Education, to John Hickman, NRC, Forwarding Independent Confirmatory Survey Summary and Results for the 3,854-Acre Area Partial Site Release at the Crystal River Energy Complex ML19022A0762019-01-22022 January 2019 Partial Site Release Request ML19029A0092018-11-0707 November 2018 Reference 16 - Defueled Safety Analysis Report DSAR-R002 ML18303A2942018-06-21021 June 2018 Golder Associates, Inc. - Citrus Combined Cycle Project - CFR 122.21(r) Report 3F0518-03, Safety Analysis Report and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20182018-05-24024 May 2018 Safety Analysis Report and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2018 ML19029A0102016-06-28028 June 2016 Reference 3 - Crystal River, Unit 3, Historical Site Assessment Rev. 00 ML13343A1782013-12-31031 December 2013 Report P23-1680-001, Rev. 0, Site-Specific Decommissioning Cost Estimate for Crystal River Unit 3 Nuclear Generating Plant. 3F1112-01, Alion Technical Report ALION-PLN-ENER-8706-02, Rev. 0, Crystal River 3: Bypass Fiber Quantity Test Plan2012-11-0707 November 2012 Alion Technical Report ALION-PLN-ENER-8706-02, Rev. 0, Crystal River 3: Bypass Fiber Quantity Test Plan ML12314A3932012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 81 of 250 Through Page 173 of 250 ML12314A3922012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 1 of 250 Through Page 80 of 250 3F1112-02, 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 2502012-10-31031 October 2012 17877-0001-100, Rev. 1, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment, Task 1, Page 174 of 250 Through Page 250 of 250 3F0912-01, ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C2012-09-30030 September 2012 ANP-3156 Np, Crystal River 3 EPU Boric Acid Precipitation RAI Responses, Attachment C 3F0712-03, Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip.2012-06-30030 June 2012 Attachment E to 3F0712-03, Technical Report, ANP-3052, Rev. 2, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip. ML12205A3582012-05-31031 May 2012 Attachment D to 3F0712-03, Technical Report, ANP-3114(NP), Rev. 0, CR-3 EPU - Feedwater Line Break Analysis Sensitivity Studies. ML12314A3912012-05-31031 May 2012 17877-0002-100, CR-3 Inadequate Core Cooling Mitigation System Reliability Assessment 2 ML12284A1382012-05-25025 May 2012 Report EGS-TR-HC589-01, Seismic Qualification Test Report for Structural Verification Testing of Iccms Cabinet Assembly. ML12205A3572011-12-15015 December 2011 Attachment a to 3F0712-03, CR-3 LOCA Summary Report - EPU/ROTSG/Mark-B-HTP, Revision 4 3F1011-08, ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip2011-10-25025 October 2011 ANP-3052, Rev. 0, CR-3 EPU Feedwater Line Break Analysis with Failure of First Safety Grade Trip ML11237A0682011-08-0505 August 2011 Siemens Technical Report CT-27438, Missile Probability Analysis Report Progress Energy Crystal River 3, Revision 1A ML11207A4442011-06-15015 June 2011 Attachment 7- Crystal River Unit 3 Extended Power Uprate Technical Report ML1101906672010-10-0404 October 2010 Levy, Units 1 and 2, Cola (Sensitive Material), Rev. 2 - Levy County Emergency Plan Part 02 - Draft (Redacted) ML1010603472010-04-0909 April 2010 5.2.2.4.4. Quality Control and Nondestructive Testing ML1028711122010-02-19019 February 2010 7.9 Inadequate Hydro Blasting Nozzles Rate Part 1 ML1028804682010-02-19019 February 2010 7.9 Inadequate Hydro Blasting Nozzles Rate Part 3 ML1028711212010-02-19019 February 2010 7.10 Hydrodemolition Induced Cracking ML1028711132010-02-19019 February 2010 7.9 Inadequate Hydro Blasting Nozzles Rate Part 2 ML1028711452010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 1 ML1028711462010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 2 ML1028804582010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 3 ML1028711482010-02-0707 February 2010 7.2 Vibration Induced by Hydro Blasting Part 1 ML1028711492010-02-0707 February 2010 7.2 Vibration Induced by Hydro Blasting Part 2 ML1028702832010-02-0303 February 2010 6.6 Original Tensioning T(2) ML1028702912010-02-0202 February 2010 6.5 Inadequate RetensioningT1 ML1028704062010-01-27027 January 2010 Email - from: Dyksterhouse, Don (Don.Dyksterhouse@Pgnmail.Com) to: Lake, Louis Dated Wednesday, January 27, 2010 Design Basis Calculations Attachments: 0102-0135-02 Concrete Strength and Elastic.... Ro Final.Pdf; 0102-0135-03 Ro Final.Pdf; ML1028706922010-01-22022 January 2010 Ctl 059169 Final Report.Pdf ML1028805162010-01-16016 January 2010 Email - from: Miller, Craig L (Craig.Miller@Pgnmail.Com) to: Lake, Louis; Thomas, George; Carrion, Robert; 'Trowe@Wje.Com'; Sealey, Mac Cc: Williams, Charles R. Dated Saturday, January 16, 2010 1:19PM Subject: Failure Mode 2.6 for Review.. 2024-03-31
[Table view] |
Text
a0Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.6.2.19(d)
July 15, 2003 3F0703-09 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Pressure/Temperature Limits Report, Revision 4
Dear Sir:
Progress Energy Florida, Inc. (PEF) hereby submits the Crystal River Unit 3 Pressure/Temperature Limits Report (PTLR), Revision 4, as required by Improved Technical Specifications (ITS) 5.6.2.19(d). The changes made to the PTLR are administrative in nature.
No technical information was changed. The revision number for calculation F-97-0013 was corrected to Revision 4. In addition to the corrected revision number, several minor format changes were made to the graphs on pages 6 through 10 to improve readability.
No new regulatory commitments are made in this letter.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, t Ames H. Terry ()
ngineering Manager JHT/pei Attachment xc: NRR Project Manager Regional Administrator, Region II Senior Resident Inspector Progress Energy Florida, Inc.
Crystal River Nuclear Plant 15760 W. Powerline Street Crystal River, FL 34428
PROGRESS ENERGY FLORIDA, INC.
CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50-302 / LICENSE NUMBER DPR - 72 ATTACHMENT Pressure/Temperature Limits Report (PTLR)
Revision 4
TABLE OF CONTENTS Pag Supporting Information .................................... 3 References .................................... 4 Allowable Pressure/Temperature Rates ..................................... 5 Plant Heatup Curve .................................... 6 Plant Cooldown Curve .................................... 7 Plant Inservice Leak and Hydrostatic Testing Curve ......................... ........... 8 LTOP Curves .................................... 9 Plant Composite Curve..............10i ......................................................................... 10 P/T LIMITS REPORT, Rev. 4 Page 2 of 10 F97-0013 Rev. 4
1.0 Pressure/Temperature Limits (Ref.4)
This Pressure-Temperature Limits Report for CR3 has been prepared in accordance with the requirements of Technical Specification Section 1.1 and 5.6.2.19. The pressure/temperature (PiT) limits have been developed using the methodology provided in the references (Ref. 1, Ref.2, Ref.3). Additional limits have been included which support the LTOP Technical Specification 3.4.11.
The following pressure-temperature limits are included in this report:
1 Allowable plant heatup and cooldown rates 2 Plant heatup P/T curve 3 Plant cooldown PiT curve 4 Plant inservice leak and hydrostatic testing P/T curve 5 LTOP P/T curves 6 Composite PiT curve 2.0 Fluence and Limiting Material Information (Ref.5)
T/4 Location l weld LNB to US Circ. Weld (ID 40%)
material SA-1769 fluence 4.27E+18 n/cm2 ART 213.0 F 3/4T Location {
weld LNB to US Circ. Weld (OD 60%)
material WF-169-1 fluence 1.55E+18 n/cm2 ART 144.5 F__
3.0 PTS Evaluation Summary (Ref.6)
Inside Surface weld LNB to US Circ. Weld (ID 40%)
material SA-1769 fluence 7.08E+18 n/cm2 RTpts 239.9 F 4.0 Instrument Uncertainties The values referenced by this document do not include instrument uncertainties.
Uncertainties must be applied based on the specific instruments being used to measure the parameters of interest.
P/T LIMITS REPORT, Rev. 4 Page 3 of 10 F97-0013 Rev. 4
5.0 References
- 1. B&W Owners Group, topical report BAW-1543A, Rev. 2, "Integrated Reactor Vessel Surveillance Program," May 1985, and Addendum 1, July 1987.
- 2. B&W Owners Group, topical report BAW-10046A, Rev. 2, "Methods of Compliance With Fracture Toughness and Operational Requirements of 10CFR50, Appendix G," June 1986.
- 3. B&W Owners Group, topical report BAW-2241P, Rev. 0, "Fluence and Uncertainty Methodologies," May 1997.
- 4. FTI Document 32-5001746-01, "CR-3 32 EFPY PT Limits,"
November 2000.
- 5. FTI Document 32-5000218-00, "ART for 32 EFPY for CR-3,"
June 1997.
- 6. FTI Document 32-5000303-O0, "PTS Evaluation for CR3,"
June 1997.
P/T LIMITS REPORT, Rev. 4 Page 4 of 10 F97-0013 Rev. 4
ALLOWABLE HEATUP AND COOLDOWN RATES
- a. For the temperature ranges specified below, the heatup rates are:
- 1. T > 2800 F
- 70'F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, H. 2800 F 2 T > 850 F
- 50'F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, iil. 850F 2 T > 600 F
- 150 F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period
- b. For the temperature ranges specified below, the cooldown rates are:
- i. T > 2800 F S 500F in any 1/2 hour period, H. 0 280 F 2 T > 150OF < 250 F in any 1/2 hour period,
- 11. 1500F 2 T
- 250F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period and,
- c. A maximum temperature change of less. than or equal to 5 0F in any one hour period during hydrostatic testing operations above system design pressure.
These limits are referred to by Technical Specification 3.4.3.
PIT LIMiTS REPORT, Rev. 4 Page 5 of 10 F97-0013 Rev. 4
REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR HEATUP FOR FIRST 32 EFPY 2800 . ..
. . . ,. l . . . . . . . . .
1 1 DATA POINTS I .
r-i- I-I11 I l r i l
r Il1_1 1_ H
-i- r i r --- r-i
- l -riTi lii - I __ l -
i T -i-rr r-i- r- - r l i t -i- T-I I I I I I I I I I I -r r :- I s I I I I I I 2600 Point Temp Press A 60 368 j!L il
- J-j - ---n- lii r - 1 l111 j
lii
-r-r-t-
,,t ml r,, l i m-2 1 r- S
- l l
-,... - m-2400 B 120 368 l l i ~.I~~i lI ii I ..I. 1... L...L.. ...L I l II' i Ji 1 1I 1I II I5 l ii i I iI I l i i i C 140 383 D 160 416 2200 E 190 497 L I ~l .1l L ~I .I I 1 1I 1 li 2 2 1.1Ii1 l I1i i i
.I l11i i I .l l i i l l 2 l2 1 1 L 11 1 1 1 12@
F 220 547 2000 G 263 692 1 I1 1 5 1 1 1 1 1 1 IIl S Sll l 1 1 1 1 1- 1 . -15 H 300 909 I_*1 _1_ .._1 _ l__1,_1_*._1_ 1 -I_1_- --
1 -F I-I- _I_ _lF 1-+- _I _I_ . _ _I_.
I 325 1129 1800 J 350 1448 wa.
K 410 2772 r I -I r -- n- r, -r@ r r -r I I r -r T 1600 I II I o1 1 1 I II I t I1 I
- I I 1 I I I I1rI I I II 0.
a, 1400 Il r n. l -. Ill l I . . ,. .1 . 1 1
- i, - l -l ll - - 1 1 - I l S1 . . . . . , , .,,.
c i-II
' t'-
1I I - i 1 - -I
'- r i T -
-- wJ -i-I-i I I I 0 1200 _J_ t-=,_11, J-J J_-_1_ WLLJ__ .JLJJW JL__JL__XJL tlJLS___
a, _. . .+/- . . J . L .l . .l . L L . I ..
. I I.. L. . . J . L . .. ..J... L. .. L .S.. 1Jll1.Al. ..L .I. I .L ..L I ., L. ..I. .
1 . L L .. I.. I . L . L. .
1000 1 1 1 5I*
a - .
l I i- - -. 1 1 1 1 1 1lL... I .... . - -. l l J -L I 800 I l l s l ll l l l f l l lt i t > I' Il o l l I I Il 600
- 1 ~m 111. 1111 1 MUST be applied to this curve for 5
-nrs-
_- _l. ~s__ -r S- n Inr .t tr-r
'.' I II
-,_lrl_-
,.I ' I I.
-ir-s-
.r operational use (see note 2) 400
-n--TW--ngT~fi 1TT I Iat lill- t--
- - '*~~~~~~~~~~~~~~~~~~~~~~~~~~~~-'
,r-. -in~ r-r- -:4-ri-s -r T --r - -r o
T-r-
-- i
- r-, r-n ,r 200 1 1
_~~~~~~ 2 1 1 1 1 1 1 1 l Ii I III1 1 1 1 1 1 llllII 1lll 0
0 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)
NOTES:
- 1. The regions of acceptable operation are below and to the right of the limit curve.
- 2. Margins are Included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve.
Additional margins for instrument uncertainty are not included and must be applied to operating procedures based on the specific Instruments being used to monitor the RCS conditions.
- 3. Applicable for heatup rates of:
T > 280°F S 70°F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, 280°F 2 T > 85°F S 50°F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, 85°F 2 T > 60°F S 15°F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period
- 4. RC Pump Constraints for Heatup:
T > 263°F None, 263°F > T 2 220°F No more than 3 RCPs running, 220°F > T 2 85°F No more than 2 RCPs running, 85°F > T No RCPs running
- 5. Minimum Temperature for Criticality is 2 525°F (Reference Technical Specification 3.4.2).
- 6. This curve referred to by Technical Specification 3.4.3 P/T LIM1TS REPORT, Rev. 4 Page 6 of 1()
F97-0013 Rev. 4
REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR COOLDOWN FOR FIRST 32 EFPY a a 2800 . . . . . . . . . .
. . .. I . ...
. . . . V--l1lVTT1TiI Hg . . . HI 1
1 H*H 1
a*uu g i g. I H
H HI I I
1l III HI H II H i l l I I I
H HI i---
- - 1H DATA POINTS 'r7r n-r-r, n-ri-r -
- -rr,-rl-:-rn-r -rT-r r-r7 r 1r7-r-r -ri-,-r-I I I l lII HI ll lI Il I I I I I HI lI I I I II I 2600 - Point t Temp Press
.. A 60 313 ,-r-,- . ,-, T T - - -ri . r@. , ,-r-m. - - r, i, r1-,- -,~rl~r i-rn-r -,-rg-r -. Trh-r -r-rTir ------ i-r -- r- r-,-r 150 313 I . lI I ILI I I I:_,.,i .H _II .l i i II HI I II . - I I I I I -
2400 -
'C 187 355 ,,..H H H ii III -L.H JIL I Ill, -,, .I H, i 0 217 441 ,I ,.,, gl H ,,II I ,,,, HI , . l Hl l lll H ill HI Hl 2200 - H 230 543 240 599 L ..L.. . J ..L .J...H J _L..jJ_. .l..L J L 1-lL L J .L . .LL...'.. ..L.L...H.. L . L .. l ... I. .L.L. HL .
F , , H i l H H H H I H I I I H H I Hi g , H4 ,H- H Ii 2000- 263 710 Ill il l H l l . H . ll i ... H ll. . * ~~~~~~~~~I l Il H . . .g .L L H 267 725 Ll..._I_ J_ L J._ . _LJ_.I..L L J L _I_H L JL _. J_1 L.L.H _.L.L..JL _ ._L.AIL _. L.L...LL.
I l l H H i l IH l 1l 1 g H l Iii I Hl l i IH l l$
CD 1.800- I 280 865 i HI I Ii I iIH l i H
~~~~~~~~~
. L.1..
41'....
lX 300 1092 i ll l H l Ii I i s l I l l CD r -r -t -t-
,,, -t- - r i . -.,, I,, ., , . .,,. . . .4 .
=11 . K 320 1338 H II Hi l I H Il Ul 1. l i i i l i l i i I l H 1600- L 340 1666 C) 370 2297 il l Hi , i l -I - HF H gi g I F i i i -I - F I l l iF H
+- -FI -I-l (A
ce 1400- Hi i i .. H l
.l i H t . .Il I i Hi l i i . . Hi I l H H Hil l ii H l i il l i
@ll Hi H ll Ill H i Il l
- a. 1200 -
uM rs-r- -T-r*~ -,r-r -,- -r- -i-ri~ .r-- rr-,-r -r-.-r -,- -rri I i i i H l i i l .H i i Hl , i .i l , ,I I , ,i il ,i i Is I i C,)
C.) 1000- ... H i l . i. .H I i H. .H i Hi HI i H Hi Hi . . . . I l I
lH ll l 1 iT-,-rT-
,_ _ _, I ,; I I iri-i- - -rl rIl -,-ii r-.-r Tr--r -rir -- r -r T
_ . . i ll n-lrl-vHTJU-r- ll 1, , l .l I Hi l l l 800 p a1 H HIll H liiiH H a H
,I ,_ -- :_ . Li _ Lf
.j_ -----!E
!_ -1l ! L I I
H.I I l I III Hi HI ' lHIlll 1 i!i !0iIF ' i I, il H HI Specific Instrument Uncertainties --
600 . . . . . . . . . . . . . . . . . . . . . .. . . ... . . . . . . . .
MUST be applied to this curve for H H I.II l .i H I i I.l lI I i I..i I I I I I II I I IIIl jI- J _ ' I j.. I.l iII. i i I I i ll .llk . operational use (see note 2) +/-.
400 - -
I I i II I i - I _,I I~vIil , I l i l L T -L T '1 - . T1LI I -
._LA'
.l .~
-_1_ IJ_I-
.J..
H ill
-J_
I.J_Al l l
- I-I 6--
I l i
-LJL I I II. I4 _.. J.. L J i J. ... H.. .. . . . . L
. I...L. .. L ... H.... 4. . . . . L 4.. .L. . . . ~ . L. L .......
200 . . II. . . f--II- . .- 47
. --. I . . . . . . . .- . . I I I I . . . I I I . . . I I Ii 1 I IiII H I 1 I I I I I I I I I I I I lI I I I Il l I i iIi HI H I I I I HII I H I 0
HI l l 1 I _l
... ~~~~~~~~~~~~~~~~~~~~~~~~.
Il l I J liI l 1 . ....
I jI l I I I i Hi iJ H
I I l l I
0 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)
NOTES:
- 1. The regions of acceptable operation are below and to the right of the limit curve.
- 2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve.
Additional margins for instrument uncertainty are not included and must be applied to operating procedures based on the specific instruments being used to monitor the RCS conditions.
- 3. Applicable for cooldown rates of:
T > 280°F
- 50°F In any 1/2 hour period, 280°F 2 T > 150°F 5 250 F in any 1/2 hour period, 150°F 2 T 5 25°F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period
- 4. RC Pump Constraints for Cooldown:
T > 263°F None, 263°F > T > 90°F No more than 2 RCPs running, 90°F 2 T No RCPs running
- 5. This curve referred to by Technical Specification 3.4.3 P/T LDIITS REPORT, Rev. 4 Page 7 of 10 F97-0013 Rev. 4
REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR INSERVICE LEAK HYDROSTATIC TESTS FOR FIRST 32 EFPY 3800 . . . . ... ...I ~~~~~~~~~~~.
.. I I . -I I ..... ... ! . . .. I . .. .. ... ... I .,- , - .. I - T T-- .. . .- - .- -T...
-....-r
- DATA POINTS _ll mI I Ii i g lii 1 1m m l li lii Ioul 3600 _ Point Temp Press - -I- 4 ~-I- Fill,_1-1 ~~~~~~~~I
__1 iiI1- I 1 I _1_il 1- -I- i - Il-l -I-o1I-4 1 1- _-Ill 4 I 1_4 II- _-- I '
3400 A 60 439 lII iI t I l 1.1...
i liii 11r1 1111 I I- I II I I - 1
. B 140 439 -- ri-i n-rnr I l-ri-r -i-ro-r -l-r Jr -r -i-r -lrT-l r -r IF-1 -r1-I-?-
3200 C 160 455 Il 1_ ..11 , . ......11 , 1 . ....11 ...
1II , I 1 . L
... ~~~. .. L1. .. .. l.,, l .l ...
i i
- D 190 52.0 n-r 1-l- i,-rn~i- n-rnr i-rn-r n-rn - irvr - T-- r r-t-P-r -r1-I-r 3000 E 220 625 II I I I I 'I I 111 1 ,l Ii r 11. , 1 l, l, l , loll 11..
2800 F 263 956 J G 300 1242 I11, 1I ll -TI11 2600 j H 340 1767 0 4 I 370 2389 .lii,,. 11 , . 1 l 1 1Ill . .1 . l . l. l l
. lll . . . l1v
. .. l1 0 l ,,ll II I II 110
. . ll 1 1 2400 J 395 3115 lii illI I I11 1 ll f11 II gt l l mii e111 1111 2200 ,51 la M
c -r i-- -r-r -l -Ir,-r i- rT-I- T I- T -ri -- -
l, 2000 11-L 1 11L 1 I 1 I I rr LJ 4 1 rr -1 r~r'
-- - - L -rTo-r LIsrmr-rmr- -1 , L -rTl- i l -r7rr li i l .I-r1i-rr1 I I l...L. ..I.. !L L ..'.. .... Ls 0..27 I J I.I ....... J ..L..E L.. L i co 1800 .1 CC 1600 4_L1 J_J __LJ_ . A L.~lA -- LJI
- _ J_ L JL- J-_LJL -__JL__JL__ILllL___
1_
Q II I I rrI I II I I II II I I iT 1111 T11 r 1 1 I I I I I I I I a) 1400 Q' Ill I lIll l1 l l ii1111 1111 oli 11l II I 1200 1111 1111 f i l l 1 1 I 1 l 1 1 _ .... .... .. .
1000 .111 1111' ' ' , ...
1111 ....
liii .
liii ,Specific
-' Instrument Uncertainties 1 f l l l .o llI.1 Ii I rl . . I f f ilT~ I~T~I~
ifii~ .
'-i-I- .... -- .. I. .. ~~~~~~~4-.
rdioir-.'--,- -.I- rl - r,,....' r. MUST be applied to this curve for
800 T n ir L. n- r-- -I- T- operational use (see note 2) - '
600 JiJ0__& .J-L.-1L J...LI...l J1 -e '_LJ_. JLiJL 1L12.. ._.LL LL ._
_.'_ JLiiI _L1JL_ _'. .1.i .LJ...'..+/-
400 1 T1 D rI lI 1 -r i I - 1- - 1 1-200 . i ii r I I - I ' 11 1
- 1_, L.L...L ...LLI..L .LL.... _.__1__.._
..L..LL ..LAJ... .. J..+/- L.L._.__._. ...L.+/-...L.L.<:_1 ...LL.L..L. -.. _LL+/-.. .. _ 1I - 41I A
0 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)
NOTES:
- 1. The regions of acceptable operation are below and to the right of the limit curve.
- 2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve.
Additional margins for instrument uncertainty are not Included and must be applied to operating procedures based on the specific instruments being used to monitor the RCS conditions.
- 3. Normal heatup and cooldown restrictions should be used with this curve as applicable.
- 4. This curve referred to by Technical Specification 3.4.3 P/T LIMTS REPORT, Rev. 4 Page 8 of 10 F97-0013 Rev. 4
REACTOR COOLANT SYSTEM LOW-TEMPERATURE OVERPRESSURE PROTECTION LIMITS FOR FIRST 32 EFPY 1000 . -. . -- . - . . . . . . . . . . . . . : r. ::r--i-. . : -i- -, I 10 Minute Transient
.Analytical Limit
- -- I -- I--
I r- 4 I __1 I
- I
_1_4____
I- I": -I'- - -I- - - r - - P - :t- - :: - - - - - I - - t : - P- - - I- - -
-I - -I.. _1__: : - .1 - : t. -- I..- -I- - - - - .4 - - + - P. - : .. : -
Point Temp Press 4-I Point Temp Press 4. - - - - -- - - 4 - 4. - - - - I- -
900 -
A 60 300 4--
-I K 60 458 1. -
- L-:L _: 4 ~4 :~O ... ... L - L.....I...
B 85 300 -I L 85 458 1. L -J L L LI:L C 100 305 M 100 467 =A.L:.L -L D 125 317 N 125 487 L L L -- - I I 800- E 150 334 --
O 1S0 517 7~~~~~~
I I I I IITI--r I -Ir F 180 364 j-I P 180 567 r r I- I-; I I- ~ -r - -- T - -
G 200 393 -II-Q 200 617 700 - H 220 421 -I- R 220 664 I 240 471 S 240 751 cn 1--
J 263 551 -I-T 263 888 Cf 600 -- J -L __ L - -::
w - . - -. .l . .- 00- LI I
-- J - -1 I
__ L - :LL L L I I I . I 11__ :1::L::L::
I I I 0C co 500
- . ~~r--l--n__n__
-_l_-n--n--T-- *~ --r a--n-- d----r--r~n~~( --T- r r~-r-- --n---~ -r--r-L 400 ~-r-m--n__:_ _ L.-_-I-_-_ - -- -- -
300 --~A~ ~ ~ ~~~~~IL- Specific Instrument Uncertainties
. , I, . . . . . . .-- --r-n__-~~~~~~~~~-
__t__.---------
_ , 1 . -*--r^-i-_.---
. F--r----- ---- +----r-
__________ ----------------- MUST be applied to this curve for 200 I I- r operational use (see note 2) --
___J_ _J___ ___IJJ_ ____J_ _____t_
-pT - 1r1 _ _ _ _ _ _ _ _ _ _
100 .4--4 -I -I --- i -I~~~~~~~--------
. - .1., 1J..L....
, , . E__ -: 4 0
0 50 100 .- 150 200 250 300 RCS TEMPERATURE (degF)
NOTES:
- 1. The regions of acceptable operation are below and to the right of the limit curve.
- 2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve.
Additional margins for instrument uncertainty are not included and must be applied to operating procedures and Technical Specification Umits based on the specific Instruments being used to monitor the RCS conditions.
- 3. The LTOP curve applies to operation below the enable temperature of 263 0F.
- 4. The LTOP 10 Minute Transient Curve is established based on at least 10 minutes of operation of the limiting transient without exceeding the LTOP Analytical Umits with an initial pressurizer level of 160 in.
- 5. The PORV setpoint is established to protect the LTOP Analytical Umit Curve.
- 6. This curve referred to by Technical Specification 3.4.3.
P/T LIMTS REPORT, Rev. 4 Page 9 of 10 F97-0013 Rev. 4
REACTOR COOLANT. SYSTEM COMPOSITE PRESSURE-TEMPERATURE LIMITS FOR FIRST 32 EFPY 2800-I I. . . . I a_ ;_a I; i 1m;_;I
- I;i 1
1 la. 1- i £ _14 ;;; m m - m --a ;] l
~r m
.;11 i DATA POINTS -i iI- rv a- r i -r ar r-rr rT- r r~bTm ri r r?-r-II I ff I I I I 1i I m I IamImamI Ia aImII 2600 -
Point Temp IPress A 60 300 Vi- 1ai-1a ai-~i~i- ~mr i- i-r-- mT- i-ra1 i~aTT B 85 300 2400,- C 100 305 D 125 313 2200 - E 150 313 -I I I..- .... 4..L.L ..L IL -I iJ I -L I I F 187 355 2000 - G 200 393 H 220 421 I 240 471 0-.
J 263 551 K 263 692 wj 1600 - L 300 909 H 325 1129 .I..LJ..L
.J..LL..L ..a..J..L .... L.a.. ..... .J.L ..
L. . ... . L. .. . . . .L..... .L .LJ n) 1400 - N 350 1448 0 389 2322 0.U U,
ot 12000-I_
a- a ma a -m a1Ia a a a a m ~I' a1 ala 800 -
- {1rrrla-mal m.a l a Specific Instrument Uncertainties :
I MUST be applied to this curve for 600- a aa a aa a a a aIa a aI - a- -a a a a a ~.
a a a a ala- T a aaa maaa
-7 a Ia1Imaa ram a i ~mmmJaa Irama Iam mmi.qm -' a- mljamal a-amaIT-I
- a. operational use (see note 2) -t ma . Ia a . 1 1I 1 I 11a I .aI ¶aI a l I Ia I I . .
400-
-- ------ - - --- - a -- L .... L...- - - - - -. -L.m. . . ..
.L 200 LJ. ~..
J11 1 I .J....L.
.~.LL. -. l. £* ,.I.. . 1A -- L.J....L. - L1 -a-L - A L -LAL.A-1.
0 D50 100 15Q 200 I 250 ~: .3,00 '350 400 450. S00 550 600 RCS TEMPERATURE (degF)
NOTES
- 1. The regions of acceptable operation are below and to the right of the limit curve.
- 2. Margins are Included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve.
Additional margins for instrument uncertainty are not Included and must be applied to operating procedures and Technical Specification Umits based on the specific instruments being used to monitor the RCS conditions.
- 3. Normal heatup, cooldown, and LTOP restrictions should be used with this curve as applicable.
4- The COMPOSITE curve applies to heatup, cooldown, ISLH, and LTOP.
- 5. This curve envelopes the heatup, cooldown, ISLH, and LTOP curves referred to by Technical Specification 3.4.3.
PIT LIMTS REPORT, Rev. 4 Page 10 of 14 3 F97-0013 Rev. 4