Letter Sequence Withholding Request Acceptance |
---|
|
|
MONTHYEARML0318808352003-07-24024 July 2003 Review of Request for Withholding Information from Public Disclosure, TAC Nos. MB7850 and MB7851 Project stage: Withholding Request Acceptance ML0332104192003-11-26026 November 2003 Amendment, Reactor Coolant System Pressure and Temperature Limits Project stage: Other ML0333607012003-11-26026 November 2003 Technical Specifications, Reactor Coolant System Pressure and Temperature Limits Project stage: Other ML0329010432003-12-29029 December 2003 Withholding from Public Disclosure, Enclosures to Ltrs Dated 07/31/2003 & 09/11/2003 Which Contained Information Regarding Proposed Change to Reactor Coolant System Pressure & Temperature Limits Project stage: Other 2003-12-29
[Table View] |
|
---|
Category:Proprietary Information Review
MONTHYEARML22200A0962022-07-22022 July 2022 Request for Withholding Information from Public Disclosure ML21279A0062021-10-13013 October 2021 Request for Withholding Information from Public Disclosure ML21084A1352021-04-0505 April 2021 Request for Withholding Information from Public Disclosure ML20317A1342020-11-12012 November 2020 Request for Withholding Information from Public Disclosure; Guarantees of Payment of Deferred Premiums ML19336A0192019-12-0303 December 2019 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML19078A1072019-03-27027 March 2019 Request for Withholding Information from Public Disclosure ML17320A1452017-11-20020 November 2017 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML16337A2762016-12-0909 December 2016 Calvert; Clinton; Dresden; LaSalle; Limerick; Nine Mile Point; Oyster Creek; Peach Bottom; Quad Cities; R.E. Ginna; Three Mile Island - Request for Withholding Information Regarding; Guarantees of Payment of Deferred Premiums ML16183A2862016-07-12012 July 2016 Second Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3 and Quad Cities Nuclear Power Station, Units 1 and 2 - Regarding the Transition to Areva Fuel (MF5736, MF5737, MF5738, MF5739 ML16098A3222016-04-27027 April 2016 Request to Withhold Emergency Preparedness Documents from Public Disclosure (CAC Nos. MF7504-MF7525) ML15260B3122015-09-24024 September 2015 Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 ML14246A5762014-09-17017 September 2014 Request for Withholding Proprietary Information from Public Disclosure (TAC Nos. MF2422, MF2423, MF2424, and MF2425) ML14128A5662014-07-29029 July 2014 Request for Withholding Proprietary Information from Public Disclosure ML13016A5002013-01-30030 January 2013 Request for Withholding Information from Public Disclosure for Braidwood Station, Units 1 & 2; Byron Station, Units 1 & 2; Clinton Power Station, Unit 1; Dresden Nuclear Power Station, Units 2 & 3; LaSalle County Station, Units 1 & 2 ML1110502342011-04-27027 April 2011 Withholding Proprietary Information from Public Disclosure, Dresden Mode 2 High Pressure Scram Elimination RAI Responses (TAC Nos. ME4844 and ME4845) (RS-10-021) ML0907103302009-04-30030 April 2009 Corp., Request for Withholding Information from Public Disclosure ML0728201572007-10-19019 October 2007 Request for Withholding Information from Public Disclosure Regarding Backup Stability Protection Methodology ML0722904432007-08-23023 August 2007 Request for Withholding Information from Public Disclosure - Request for License Amendment to Revise Safety Limit Minimum Critical Power Ratio - Dresden ML0626105142006-11-14014 November 2006 GE Request for Withholding Information from Public Disclosure ML0629903162006-11-0707 November 2006 Withholding from Public Disclosure, NF-BEX-06-167, Rev. 2 P-Attachment, Dresden Unit 3 Cycle 20 SLMCPR MD2706 ML0622904722006-10-13013 October 2006 Request for Withholding Information from Public Disclosure - Request for License Amendment to Increase Main Steam Safety Valve Lift Setpoint ML0614500612006-09-21021 September 2006 GE Company, Request for Withholding Information from Public Disclosure for Dresden and Quad Cities RS-05-179 Stramback Ltr ML0610103752006-09-21021 September 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 ML0615001032006-09-0505 September 2006 GE, Withholding from Public Disclosure, GENE-0000-0038-6481-01-R1-P, Exelon Steam Dryer Dynamic Time History Analyses: Dresden Unit 2 2004 Repair & Dresden Unit 3 2003 & 2004 Repair Dryer Configurations Using Loads from Plant Measurements, ML0507701992006-09-0505 September 2006 Withholding from Public Disclosure, C.D.I. Proprietary Report No. 04-09P, Rev. 5 and Presentation Entitled, Methodology to Determine Unsteady Pressure Loading on Components in Reactor Steam Domes, Dated January 25, 2005 ML0615301212006-08-17017 August 2006 Continuum Dynamics, Inc. Request for Withholding Information from Public Disclosure, Bilanin Letter ML0614402522006-07-25025 July 2006 GE Company, Request for Withholding Information from Public Disclosure for Dresden and Quad Cities - Quintana Ltr ML0614406092006-07-0505 July 2006 Quad Cities, Units 1 and 2 - GE, Request for Withholding Information from Public Disclosure ML0608201332006-07-0505 July 2006 Quad Cities, Units 1 and 2 - GE, Request for Withholding Information from Public Disclosure ML0614401352006-07-0505 July 2006 General Electric Company, Request for Withholding Information from Public Disclosure ML0608905262006-05-0101 May 2006 GE Request for Withholding Information from Public Disclosure for Dresden, Units 2 and 3 and Quad, Units 1 and 2 ML0609603632006-05-0101 May 2006 General Electric, Withholding from Public Disclosure, GE-NE-0000-0032-1827P, Quad Cities Replacement Steam Dryer Instrumentation Acceptance Criteria, Dated April 2005 ML0610200462006-04-28028 April 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 ML0610102872006-04-28028 April 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dreden Nuclear Power Station, Units 1 and 2 (TAC Nos. MC0875, MC0876, MC0877 and MC0878 ML0609603942006-04-28028 April 2006 GE Request for Withholding Information from Public Disclosure Dresden and Quad by Letter Dated May 13, 2005 ML0607303242006-03-29029 March 2006 Company Request for Withholding Information from Public Disclosure ML0604002722006-03-16016 March 2006 Request for Withholding Information from Public Disclosure ML0604507082006-03-0808 March 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden, Units 2 and 3 and Quad Cities, Units 1 and 2 ML0518100572005-07-14014 July 2005 Withholding from Public Disclosure, Updated Responses to DNPS and QCNPS EPU RAIs 3B & 7, August 14, 2003 (GE Proprietary Information) ML0516601362005-07-0505 July 2005 7/5/05, Dresden and Quad Cities - Exelon Generation Company Request for Withholding Information from Public Disclosure ML0517503642005-07-0505 July 2005 7/5/05, Dresden and Quad Cities - Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 ML0514302632005-05-25025 May 2005 Quad Cities - Proprietary Determination for Handouts for April 14, 2005, Meeting with Westinghouse on Application of Optima2 Topical Reports ML0507703902005-03-24024 March 2005 Withholding from Public Disclosure, GE Proprietary Report GE-NE-0000-0011-0531-R3, Dresden and Quad Cities Neutron Flux Evaluation, Revision 3, Class III, Dated March 2005 ML0507701262005-03-23023 March 2005 GE, Withholding from Public Disclosure, GE Proprietary Reports GE-NE-0000-0002-9629-01R1, GE-NE-0000-0002-9600-01R2, GE-NE-0000-0002-9600-02R2 and GE-NE-0000-0002-9600-03R2 for Dresden Nuclear, Units 2 and 3, Quad Cities, Units 1 and 2 ML0405600102004-03-18018 March 2004 Withholding from Public Disclosure, Exelon 10/10/2003 Letter Responding to NRC Request for Additional Information Re Change to Technical Specifications Re Operability Requirements of Main Steam Safety Valves ML0404404252004-02-13013 February 2004 (Egc), Withholding Information from Public Disclosure, Jeffrey A. Benjamin 02/05/2004 Letter Addressing an Issue Related to EGC Plants ML0329010432003-12-29029 December 2003 Withholding from Public Disclosure, Enclosures to Ltrs Dated 07/31/2003 & 09/11/2003 Which Contained Information Regarding Proposed Change to Reactor Coolant System Pressure & Temperature Limits ML0318808352003-07-24024 July 2003 Review of Request for Withholding Information from Public Disclosure, TAC Nos. MB7850 and MB7851 ML0307602832003-03-31031 March 2003 Proprietary Information Review, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Unit 2 2022-07-22
[Table view] |
Text
July 24, 2003 Mr. David J. Robare General Electric Company, 175 Curtner Avenue San Jose, CA 95125
SUBJECT:
GENERAL ELECTRIC COMPANY, REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (TAC NOS. MB7850 AND MB7851)
Dear Mr. Robare:
By letter dated February 27, 2003, Exelon Generation Company, LLC, submitted an affidavit dated February 3, 2003, executed by you requesting that the following documents be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790:
- 1) Pressure-Temperature Curves for Exelon Dresden Unit 2, GE-NE-0000-0002-9629-01, Revision 0, Class III, and
- 2) Pressure-Temperature Curves for Exelon Dresden Unit 3, GE-NE-0000-0002-9600-01, Revision 0, Class III.
A nonproprietary copy of these documents has been placed in the Nuclear Regulatory Commissions (NRCs) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room (ADAMS).
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure because it is:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by General Electrics competitors without license from General Electric constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the versions of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
D. Robare Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2863.
Sincerely,
/RA/
Lawrence W. Rossbach Project Manager Project Directorate III, Section 2 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-237 and 50-249 cc: See next page
Dresden Nuclear Power Units 2 and 3 cc:
Site Vice President - Dresden Nuclear Power Station Vice President Exelon Generation Company, LLC Mid-West Regional Operating Group 6500 N. Dresden Road Exelon Generation Company, LLC Morris, IL 60450-9765 4300 Winfield Road Warrenville, IL 60555 Dresden Nuclear Power Station Plant Manager Exelon Generation Company, LLC Senior Vice President 6500 N. Dresden Road Mid-West Regional Operating Group Morris, IL 60450-9765 Exelon Generation Company, LLC 4300 Winfield Road Regulatory Assurance Manager - Dresden Warrenville, IL 60555 Exelon Generation Company, LLC 6500 N. Dresden Road Vice President - Licensing and Regulatory Morris, IL 60450-9765 Affairs Exelon Generation Company, LLC U.S. Nuclear Regulatory Commission 4300 Winfield Road Dresden Resident Inspectors Office Warrenville, IL 60555 6500 N. Dresden Road Morris, IL 60450-9766 Director - Licensing Mid-West Regional Operating Group Chairman Exelon Generation Company, LLC Grundy County Board 4300 Winfield Road Administration Building Warrenville, IL 60555 1320 Union Street Morris, IL 60450 Senior Counsel, Nuclear Mid-West Regional Operating Group Regional Administrator Exelon Generation Company, LLC U.S. NRC, Region III 4300 Winfield Road 801 Warrenville Road Warrenville, IL 60555 Lisle, IL 60532-4351 Manager Licensing - Dresden and Illinois Department of Nuclear Safety Quad Cities Office of Nuclear Facility Safety Exelon Generation Company, LLC 1035 Outer Park Drive 4300 Winfield Road Springfield, IL 62704 Warrenville, IL 60555 Document Control Desk-Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President, Nuclear Services Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
D. Robare Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2863.
Sincerely,
/RA/
Lawrence W. Rossbach Project Manager Project Directorate III, Section 2 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-237 and 50-249 cc: See next page DISTRIBUTION:
PUBLIC MBanerjee PDIII-1 R/F MRing, Region III WRuland BElliot, EMCB AMendiola SCoffin,EMCB LRossbach JUhle, DSSA PCoates DHassell, OGC ADAMS Accession Number: ML031880835
- See previous concurrences OFFICE PM:PDIII-2 SC:PDIII-2 DE/EMCB DE/EMCB DSSA/SRXB LA:PDIII-2 OGC NAME LRossbach AMendiola BElliot* SCoffin* JUhle* PCoates DHassell*
DATE 07/24/03 07/24/03 07/18/03 07/12/03 07/8/03 07/24/03 07/27/03 OFFICIAL RECORD COPY