MONTHYEARML0318102952003-06-30030 June 2003 Environmental Assessment and Finding of No Significant Impact Technical Specifications Table 3.3-1, Reactor Trip System Instrumentation Project stage: Other ML0323701192003-10-0101 October 2003 Issuance of License Amendments Table 3.31, Reactor Trip System Instrumentation Project stage: Approval ML0327511302003-10-0101 October 2003 Technical Specification Pages for Salem Nuclear Generating Station, Units 1 and 2, Issuance of License Amendments Table 3.31, Reactor Trip System Instrumentation Project stage: Approval ML0330100252003-10-28028 October 2003 Correction to Amendment No. 259, Table 3.3-1, Reactor Trip System Instrumentation Project stage: Other 2003-10-28
[Table View] |
Similar Documents at Salem |
---|
Category:Environmental Assessment
MONTHYEARML20150B6832020-11-23023 November 2020 Encl: Environmental Assessment (Memo to File: Envir. Assessment and Finding of No Significant Impact for Exelon Generation Co., LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Salem ISFSI) ML20156A0672020-07-0202 July 2020 Biological Assessment of Impacts to Atlantic Sturgeon and Its Critical Habitat for Salem Nuclear Generating Station, Units 1 and 2, Continued Operation ML19312A4352020-01-15015 January 2020 Environmental Assessment and Finding of No Significant Impact Related to Changes to Emergency Plan Staffing Requirements ML1033502712010-12-13013 December 2010 Biological Assessment for License Renewal of the Hope Creek Generating Station, Unit 1, and Salem Nuclear Generating Station, Units 1 & 2 ML1000500392010-01-29029 January 2010 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Environmental Assessment and Finding of No Significant Impact LR-N09-0249, Request for Exemption from Physical Security Requirements (Non-Safeguards Version)2009-11-0303 November 2009 Request for Exemption from Physical Security Requirements (Non-Safeguards Version) ML0318102952003-06-30030 June 2003 Environmental Assessment and Finding of No Significant Impact Technical Specifications Table 3.3-1, Reactor Trip System Instrumentation ML0311301032003-04-22022 April 2003 Environmental Assessment and Finding of No Significant Impact, Exemption from Appendix R, Sections III.G.3 and III.L.3, Requirements for Fire Areas 1(2)-FA-AB-64B, and 1(2)-FA-AB-84B, and 1(2)-FA-AB-84C ML0311101712003-04-17017 April 2003 Environmental Assessment, Administrative and Editorial Changes to Technical Specifications ML0300207522003-01-0303 January 2003 Environmental Assessment & Finding of No Significant Impact Request for Exemption to 10 CFR 55.59 2020-07-02
[Table view] Category:Finding of No Significant Impact
MONTHYEARML19312A4352020-01-15015 January 2020 Environmental Assessment and Finding of No Significant Impact Related to Changes to Emergency Plan Staffing Requirements ML1000500392010-01-29029 January 2010 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Environmental Assessment and Finding of No Significant Impact ML0318102952003-06-30030 June 2003 Environmental Assessment and Finding of No Significant Impact Technical Specifications Table 3.3-1, Reactor Trip System Instrumentation ML0311301032003-04-22022 April 2003 Environmental Assessment and Finding of No Significant Impact, Exemption from Appendix R, Sections III.G.3 and III.L.3, Requirements for Fire Areas 1(2)-FA-AB-64B, and 1(2)-FA-AB-84B, and 1(2)-FA-AB-84C ML0311101712003-04-17017 April 2003 Environmental Assessment, Administrative and Editorial Changes to Technical Specifications ML0300207522003-01-0303 January 2003 Environmental Assessment & Finding of No Significant Impact Request for Exemption to 10 CFR 55.59 2020-01-15
[Table view] Category:Letter
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 ML24296B1932024-10-23023 October 2024 Project Manager Assignment LR-N24-0068, Core Operating Limits Report - Cycle 282024-10-21021 October 2024 Core Operating Limits Report - Cycle 28 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) IR 05000272/20244032024-09-25025 September 2024 And Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 05000272/LER-2024-001, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location 2024-09-25
[Table view] |
Text
June 30, 2003 Mr. Roy A. Anderson President & Chief Nuclear Officer PSEG Nuclear, LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 -
ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RE: TECHNICAL SPECIFICATIONS TABLE 3.3-1, REACTOR TRIP SYSTEM INSTRUMENTATION (TAC NOS. MB8445 AND MB8446)
Dear Mr. Anderson:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for amendments to the Salem Nuclear Generating Station, Unit Nos. 1 and 2, Technical Specifications (TSs) dated April 10, 2003. The proposed license amendments would allow for changes to the description of the P-7 permissive interlock in TS Table 3.3-1, Reactor Trip System Instrumentation.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Robert J. Fretz, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
Environmental Assessment cc w/encl: See next page
June 30, 2003 Mr. Roy A. Anderson President & Chief Nuclear Officer PSEG Nuclear, LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 -
ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RE: TECHNICAL SPECIFICATIONS TABLE 3.3-1, REACTOR TRIP SYSTEM INSTRUMENTATION (TAC NOS. MB8445 AND MB8446)
Dear Mr. Anderson:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for amendments to the Salem Nuclear Generating Station, Unit Nos. 1 and 2, Technical Specifications (TSs) dated April 10, 2003. The proposed license amendments would allow for changes to the description of the P-7 permissive interlock in TS Table 3.3-1, Reactor Trip System Instrumentation.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Robert J. Fretz, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
Environmental Assessment cc w/encl: See next page DISTRIBUTION:
PUBLIC PDI-2 R/F CHolden GMeyer, Region I JClifford CRaynor RFretz JTappert OGC ACRS ADAMS Accession Number: ML031810295
- See previous concurrence OFFICE PDI-2/PM PDI-2/LA RLEP/SC* OGC* PDI-2/SC(A)
NAME RFretz CRaynor JTappert SUttal REnnis DATE 06/30/03 06/30/03 06/18/03 06/26/03 06/30/03 OFFICIAL RECORD COPY
PSEG Nuclear LLC Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Mr. Timothy J. OConnor Lower Alloways Creek Township Vice President - Operations c/o Mary O. Henderson, Clerk PSEG Nuclear - X15 Municipal Building, P.O. Box 157 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Mr. John T. Carlin Radiation Protection Programs Vice President - Engineering NJ Department of Environmental PSEG Nuclear - N10 Protection and Energy P.O. Box 236 CN 415 Hancocks Bridge, NJ 08038 Trenton, NJ 08625-0415 Mr. David F. Garchow Brian Beam Vice President - Projects and Licensing Board of Public Utilities PSEG Nuclear - N28 2 Gateway Center, Tenth Floor P.O. Box 236 Newark, NJ 07102 Hancocks Bridge, NJ 08038 Regional Administrator, Region I Mr. Gabor Salamon U.S. Nuclear Regulatory Commission Manager - Nuclear Safety and Licensing 475 Allendale Road PSEG Nuclear - N21 King of Prussia, PA 19406 P.O. Box 236 Hancocks Bridge, NJ 08038 Senior Resident Inspector Salem Nuclear Generating Station Jeffrie J. Keenan, Esquire U.S. Nuclear Regulatory Commission PSEG Nuclear - N21 Drawer 0509 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Ms. R. A. Kankus Joint Owner Affairs PECO Energy Company Nuclear Group Headquarters KSA1-E 200 Exelon Way Kennett Square, PA 19348
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION PSEG NUCLEAR, LLC SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (NRC) is considering the issuance of amendments to Facility Operating License Nos. DPR-70 and DPR-75, issued to PSEG Nuclear, LLC (the licensee), for operation of the Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, located in Salem County, New Jersey. Therefore, as required by Title 10 of the Code of Federal Regulations (10 CFR) Section 51.21, the NRC is issuing this environmental assessment and finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action would allow the licensee to make an editorial change to the Salem Technical Specifications (TSs) by revising the description of the P-7 permissive interlock defined in TS Table 3.3-1, Reactor Trip System Instrumentation, in accordance with the licensees application dated April 10, 2003.
The Need for the Proposed Action:
The proposed action would revise the description of the P-7 permissive interlock defined in TS Table 3.3-1 due to changes in the design of the high pressure turbine. As part of this design change, the pressure taps for transmitters PT505 and PT506 will be relocated.
Consequently, the description for the Turbine impulse chamber pressure will be changed to Turbine steam line inlet pressure. The proposed action is considered an editorial change.
Environmental Impacts of the Proposed Action:
The NRC has completed its evaluation of the proposed action and concludes, as set forth below, that there are no significant environmental impacts associated with the administrative and editorial changes to the Salem TSs.
The proposed action will not significantly increase the probability or consequences of accidents, no changes are being made in the types of effluents that may be released offsite, and there is no significant increase in occupational or public radiation exposure. Therefore, there are no significant radiological environmental impacts associated with the proposed action.
With regard to potential nonradiological impacts, the proposed action does not have a potential to affect any historic sites. It does not affect nonradiological plant effluents and has no other environmental impact. Therefore, there are no significant nonradiological environmental impacts associated with the proposed action.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the no-action alternative). Denial of the application would result in no change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resource than those previously considered in the Final Environmental Statement related to operation of Salem Nuclear Generating Station, Unit Nos. 1 and 2, dated April 1973.
Agencies and Persons Consulted:
On June 10, 2003, the staff consulted with the New Jersey State official, Mr. Rich Pinney of the New Jersey Department of Environmental Protection, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensees letter dated April 10, 2003. Documents may be examined, and/or copied for a fee, at the NRCs Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRCs PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 30th day of June, 2003.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Richard B. Ennis, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation