Entergy Entergy Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213-8298 Tel 601 368 5758 Michael A. Krupa Director Nuclear Safety & Licensing CNRO-2003-00026 June 19, 2003 U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Entergy Operations, Inc.

Quality Assurance Program for Independent Spent Fuel Storage Installations Grand Gulf Nudear Station Docket No. 50-416 License No. NPF-29

REFERENCES:

River Bend Station Docket No. 50-458 License No. NPF-47

1.

Letter CNRO-98/00013 from Entergy Operations, Inc. to the NRC, "Consolidation of the Four Current Quality Assurance Programs into One Quality Assurance Program," dated April 30, 1998

2.

Letter from the NRC to Entergy Operations, Inc., Consolidation of

'Quality Assdrance(QA) Prograrms into One' Quality-' Ass'urance Program Ma'nual for all Entergy Sites - 'Arkansas' Nuclear One, Grand 'Gulf Nucle'ar Station, 'Rive'r Bend Station, and Waterford Steam

Electric' Station -' (TAC No.

M97893),"

dated November 6, 1998

3.

Letter CNRO-2003-00013 from Entergy Operations, Inc. to the NRC, Entergy Quality Assurance Program Manual, Revision 8,"

dated April 24, 2003

Dear Sir or Madam:

This letter serves as notification, as required by 10 CFR 72.140(d), that Entergy Operations, Inc. (Entergy) intends to apply its previously approved 10 CFR Part 50, Appendix B, Quality Assurance Program to activities involving storage of spent fuel at the independent spent fuel storage installations (ISFSls) being constructed at Grand Gulf Nuclear Station (GGNS) and River Bend Station (RBS). The Entergy Quality Assurance Program Manual (QAPM), which is used at all Entergy facilities, was originally submitted to the NRC for approval under the docket numbers for Arkansas Nuclear One, Units 1 and 2 (50-313 and 50-368), GGNS (50-416), RBS (50-458), and Waterford Steam Electric' Station, Unit 3 '(50-382) via Reference

  1. 1 on April 30, 1998. The NRC approved the QAPM, as' documented in Refeence #2, 'on November 6, 1998.

Entergy subrmitted Revisi6n 8 of the' QAPM on April 24, 2003 via Reference #3.

CNRO-2003-00026 Page 2 of 2 Should you have any questions regarding this letter, please contact Guy Davant at (601) 368-5756.

This letter contains no commitments.

Sincerely, MAKIGHD/bal cc:

Mr. P. D. Hinnenkamp (RBS)

- Mr. C. R.-utchinson (ECH)

Mr. G. D. Pierce (ECH)

Mr. G. A. Williams (GGNS)

Mr. P. J. Alter, Senior Resident Inspector (RBS)

Mr. T. P. Gwynn, NRC Region IV Regional Administrator Mr. T. L. Hoeg, NRC Senior Resident Inspector (GGNS)

Mr. S. C. O'Connor, NRC Spent Fuel Project Office Mr. B. K. Vaidya, NRR Project Manager (GGNS)

Mr. M. K. Webb, NRR Project Manager (RBS)