MONTHYEARML0330202682002-10-24024 October 2002 Technical Specification Pages, Amendment 150 Project stage: Other ML0312700902003-04-25025 April 2003 Responses to Request for Additional Information to Proposed Amendment to TS 3.2.4, Departure from Nucleate Boiling Ratio, 3.3.1, Reactor Protective System Instrumentation - Operating, 3.3.3, Control Element Assembly Calculators Project stage: Response to RAI ML0312108382003-05-0505 May 2003 & 05/15/2003, Palo Verde, Units 1, 2 & 3, Forthcoming Meeting with Arizona Public Service Co., to Discuss Additional Information Needed for Review of Amendment Request Project stage: Meeting ML0312705492003-05-0707 May 2003 05/14-15/2003, Palo Verde, Units 1, 2, & 3, Meeting Notice with Arizona Public Service, Upgrading Core Protection Calculator System. Change in Time & Discussion of Proprietary Information Project stage: Meeting ML0313505732003-05-14014 May 2003 Meeting Handouts to Discuss the Licensee'S Application Dated November 7, 2002, to Upgrade the Core Protection Calculator System Project stage: Meeting ML0316813092003-06-17017 June 2003 Request for Withholding Information from Public Disclosure, Core Protection Calculator Upgrade Amendment Request Project stage: Withholding Request Acceptance ML0317502262003-06-24024 June 2003 Summary of Meeting with Arizona Public Service Co. for Palo Verde Units 1, 2 & 3 Project stage: Meeting ML0322407112003-08-12012 August 2003 8/12/03 - Palo Verde Ngs, Units 1,2, & 3 - Notice of Consideration of Issuance of Amds to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing. (Tacs. MB6726/6727/6728) Project stage: Other ML0325215182003-09-0808 September 2003 07/17/2003 Summary of Meetings with Arizona Public Service Co for Palo Verde Nuclear Generating Station Tacs MB6726, MB6727, MB6728 Project stage: Meeting ML0329012052003-10-15015 October 2003 Palo Verde Ngs, Units 1, 2&3- Request for Withholding Information from Public Disclosure for Core Protection Calculator Upgrade Amend Request.(Tac. MB6726/MB6727/MB6728) Project stage: Withholding Request Acceptance ML0330303632003-10-24024 October 2003 Ngs, Units 1, 2 & 3 - Issuance of Amds 150 (3) on the Core Protection Calculator System Upgrade (Tacs. MB6726/MB6727/MB6728) Project stage: Approval ML0332103022003-11-17017 November 2003 Letter, Correction to Amendment No. 150 Project stage: Other 2003-05-14
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24038A1742024-02-0707 February 2024 Pre-submittal Meeting Slides ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML24003A8532024-01-0303 January 2024 January 4, 2024 Presubmittal Meeting Presentation-Risk Informed Process for Evaluations (RIPE) License Amendment Request for Safety Injection Tank (SIT) LCO (EPID: L?2023?LRM-0108) ML23240A3232023-08-31031 August 2023 APS Presentation Slides for Pre-Submittal Meeting on 8/31/23, Alloy-600 Management Program Plan ML23192A0102023-07-11011 July 2023 NRC RIPE 7-11-23 Public Meeting Presentation Slides ML23144A0252023-05-25025 May 2023 APS Presentation Slides for Pre-Submittal Meeting on 5/25/23, Przr Surge Line ML23093A0252023-04-30030 April 2023 April 5, 2023, Presubmittal Meeting Presentation - Containment Temperature and Safety Injection Tank Volume Requirements LAR ML23090A1392023-04-0404 April 2023 April 4, 2023 Presubmittal Meeting Presentation - LAR to Adopt TSTF-266, Eliminate the Remote Shutdown System Table of Instrumentation and Controls (EPID: L?2023?LRM-0017) ML23055B0572023-03-0101 March 2023 March 1, 2023 Presubmittal Meeting Presentation - Request for Use of Mururoa V4F1 and MTH2 Supplied Air Suits (EPID: L?2023?LRM-0012) ML22096A0052022-04-0606 April 2022 TSTF-487 LAR Pre-submittal Public Meeting Presentation Slides ML22025A0012022-01-25025 January 2022 1/25/22 Pre-submittal Meeting Presentation Slides for RR-69 to Extend Containment Tendon Inspection by Three Months Beyond 2/8/22 ML21342A0502021-12-0808 December 2021 TSTF-567 LAR Pre-submittal Public Meeting Presentation Slides ML21320A1032021-11-17017 November 2021 RIPE Exemption 11-17-21 Pre-submittal Public Meeting Presentation Slides ML21194A2502021-08-10010 August 2021 RIC 2021 - Ai EPRI-Artificial Intelligence and Development at EPRI ML21131A0132021-05-13013 May 2021 License Transfer from Pnm to SRP, 5-13-21 Pre-submittal Public Meeting Presentation Slides ML21025A0032021-01-26026 January 2021 Risk-Informed Process for Evaluations (RIPE) - NEI Public Meeting Presentation Slides ML21025A0042021-01-25025 January 2021 Risk-Informed Process for Evaluations (RIPE) - NRC Public Meeting Presentation Slides ML20171A2352020-06-24024 June 2020 Inservice Testing - Supplemental Position Indication Relief Request - NRC Pre-Application Meeting - June 24, 2020 ML19192A0972019-07-11011 July 2019 License Amendment Request for Emergency Plan, July 11, 2019 ML18299A0722018-09-26026 September 2018 Ionizing Radiation Factsheet-Veterans - Information for Veterans and Their Families ML17320A1932017-11-15015 November 2017 NRC Public Meeting, Treatment of Mitigating Strategies in Risk Informed Decision Making ML17003A0332016-12-29029 December 2016 Enclosure 2 - APS Meeting Slides ML16357A6872016-12-20020 December 2016 One-Time License Amendment Request Unit 3 Train B Diesel Generator ML17003A0862016-11-0303 November 2016 Enclosure 2 Slides Regulatory Audit Report for November 2-3, 2016 ML16253A4112016-09-0707 September 2016 Palo Verde Nuclear Generating Station Generic Letter 2004-02 - September 7, 2016 ML16083A4722016-03-24024 March 2016 NRC Subsequent Pre-Submittal Meeting Next Generation Fuel - Palo Verde, Units 1, 2, and 3 ML16014A1102016-01-20020 January 2016 Draft APS Slides for January 20, 2015, Public Meeting with APS Regarding Upcoming Next Generation Fuel License Amendment Request for Palo Verde, Units 1, 2, and 3 ML15244B2632015-08-27027 August 2015 Slides for Public Meeting with Arizona Public Service Company to Discuss License Amendment Request for Palo Verde Regarding Revised Methodology for Spent Fuel Pool Criticality Analysis ML15236A1342015-08-26026 August 2015 Presentation Slides for Public Meeting with Arizona Public Service Generic Letter 2004-02 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML15159B2972015-06-0909 June 2015 Near-Term Task Force Recommendation 2.1 (R2.1) Seismic Hazard Evaluation - Arizona Public Service, Palo Verde Nuclear Generating Station Public Meeting - June 9, 2015 ML15156B3312015-06-0909 June 2015 Public Meeting Slides on R2.1 Seismic Hazard Re-Evaluation ML15156B3522015-06-0404 June 2015 Draft Slides for Public Meeting with Arizona Public Service Company Ongoing Resolution of Generic Letter 2004-02 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML15134A3592015-05-11011 May 2015 5/11/2015, Meeting Slide Regarding Pre-Submittal Meeting for Palo Verde Unit 1, 2, and 3 Updated Spent Fuel Pool Criticality Analysis ML15126A2072015-05-11011 May 2015 Presentation Slides for Prelicensing Meeting with Arizon Public Service Company to Discuss License Amendment Request for Palo Verde, Units 1, 2, and 3, ML15103A2882015-04-0909 April 2015 Presentation on Potential Relief Request About Pressure Boundary Leakage on Reactor Coolant Pump 2A Pipe Nozzle ML15070A2522015-02-18018 February 2015 Pre-Submittal Public Meeting Final Slides on Risk-Informed Completion Times. ML15042A4152015-02-11011 February 2015 Pre-Submittal Public Meeting Draft Slides on Risk- Informed Completion Times ML14184B4112014-06-11011 June 2014 Nrc/Nei/Utility MTG 6/11/14 ML14149A5092014-04-23023 April 2014 4/23/14 Meeting Slide for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Re. Sig Tube Inspection ML14098A1832014-04-0202 April 2014 4/2/2014 Meeting Slide for Bottom-Mounted Instrument (Bmi) Relief Request 52 Pre-Submittal Meeting ML13309A7202013-11-0505 November 2013 Meeting Presentation for November 5, 2013 Public Meeting Regarding Incorporation of NEI 11-04 Into the QA Program at Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML13308B3322013-11-0404 November 2013 Meeting Presentation for November 4, 2013 Public Meeting Regarding Bmi Leakage ML13308C3402013-11-0404 November 2013 SG Unit 3 Telephone Call ML13025A2832013-01-29029 January 2013 NRC Comments on Draft Integrated Plans, Palo Verde ML12311A0492012-09-18018 September 2012 Part 26 Public Meeting NEI Presentation Slides ML12243A4352012-08-30030 August 2012 8/30/2012 Meeting RR 48 - Phased Array Ultrasonic Examination in Lieu of Radiography ML12243A4382012-08-30030 August 2012 8/30/2012 Meeting - RR 48 UT Vs Rt Discussion ML12243A4472012-08-30030 August 2012 8/30/2012 Meeting - RR 48 UT in Lieu of Rt for Nuclear Power Plant Applications ML12157A2722012-06-11011 June 2012 5/31/2012 Summary of Telephone Conference with Licensees Regarding Near Term Task Force Recommendation 2.1 Seismic Reevaluations - Diablo Canyon, 1 and 2, San Onofre, Units 2 and 3, Columbia Generating Station, and Palo Verde, Units 1, 2, a ML11188A0722011-07-0606 July 2011 NRC Meeting with NEI and Licensees June 28, 2011 Workshop Engineering Approach Rev F 2024-02-07
[Table view] |
Text
NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999)
TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting.
Do not include proprietary materials.
DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 06/14/2003 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:
Docket Number(s) 50-528, 50-529, and 50-530 Plant/Facility Name Palo Verde Nuclear Generating Station TAC Number(s) (if available) MB6726, MB6727, and MB6728 Reference Meeting Notice ML031270549 dated May 7,2003 Purpose of Meeting (copy from meeting notice) The staff requested the meeting to discuss the licensee's application dated November 7,2002, to upgrade the core protection calculator system.
NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE Jack Donohew Senior Project Manager OFFICE Office of Nuclear Reactor Regulation DIVISION Division of Licensing Project Management BRANCH Project Directorate IV Distribution of this form and attachments:
Docket File/Central File PUBLIC FOM68(-99 .R RNE NRCCE APRTi omwsdsge sn nom NRC FORM 658 (9-t1999) PRINTED ON RECYCLED PAPER This form was designed using InForrns
.' ; .p)J 0
Core Protection Calculator PVNGS Expectations and additional info. needed based on review status - May 14, 2003 Christopher Graham, NRC primary reviewer for PVNGS CPC 301 415-3201 cxq2(inrc. qov
Background
- Arizona Public Service (APS) Submittal (TS change request),
CPC
- Common Q system to replace existing digital platform
- SER Plant Specific Action Item (PSAI) responses for Common Q
- No Significant Hazards Review
- NRC provides initial set of RAI's to APS (3rd week March 03)
- Phone Con 3/27/03 (NRC, APS and Westinghouse)
- NRC provided discussion and guide to what will be reviewed
- NRC provided clarification to draft initial set of RAls
- NRC mentioned future intended visits to Westinghouse for software audit and PVNGS for review of APS involvement efforts for Common Q CPC procurement
00 t 0
Background
- Phone Con 4/24/03 (NRC, APS and Westinghouse)
- NRC expressed concern about scheduling and lack of documentation available at Rockville.
- NRC re-stated its intent to perform safety evaluation in a timely manner consistent with APS ability to respond.
- NRC re-stated its intent to audit software and visit PVNGS as part of successful CPC review.
- NRC expressed intent to visit PVNGS during Site Acceptance Test consistent with approval of use of Common Q as CPC.
- APS and NRC discussed RAI questions
Documents needed
- NRC disseminated to APS first list of documents to be formally submitted
- System Requirements (SysRS) spec for CPC, CEAC, Generic FPDS
- Software Requirements spec (SRS) for CPC, CEAC, Generic FPDS
- Hardware description document (HDD) CPC
- Software Design description (SDD) DNBR and LPD Update and Static
- CPC timing analysis
- FMEA for Common Q CPCS
- CPCS preliminary hazards analysis - ICE 37731 *
- Functional Design requirements for a CPC - ICE 3208 *
- Functional requirements for a CEAC - ICE 3234 *
- Requirements traceability matrix *
- Docs not available for initial review
- APS expresses concern (May 9 or 12) about scope of review related to procedures requested
- Need APS procedures that govern/manage the system life-cycle activities that are used to obtain the CPC.
Docs reviewed at Rockville C &4 A%
A.,
(made available on April 29)
NRC review in varying levels of detail (from May 5)
- SysRS, SRS, SDD (DNBR and LPD) - static and update, HDD, FMEA, timing analysis, equipment layout and wiring diagrams.
- Test docs, including Factory Acceptance Test (FAT)
Iqw 0 Results
- The connection of the CPC to the PMS using TCP/IP, has this beenreviewed for non-safety to safety effect?
- Safety-Related MTP uses IRIG-B cards, are they safety related?
- Safety-Related MTP uses Win NT, what is the impact to MTP function? Andwill Win NT be considered APS SIL 1 software?
Safety-related MTP and OM uses C-527 cards, what is impact to MTP function?
Has the uncertainty analysis IAW procurement spec. been completed and what are the results?
Is software documentation as specified in procurement spec complete and correct?
Has timing analysis completely considered all aspects of timing delay in a 2oo4 digital system?
This includes the timing variation (worse case) that may exist due to process scheduling and the worse case processor clock timing that may exist due to proasssor drift. This also includes the worse case time delay that may exist in data transfer of penalty factor from the CEAC processor to the CPC processor.
Appendix 2 topical mentions 4 algorithms running in a CPC processor, SysRShas five.. .which is correct?
If the CPCS is part of a digital plant protection system, why isthe performance of overall time response testing not considered as discussed in APS response to PSAI 6.12 FMEA reviewed focuses on field device failures and failures at the card and communication link level, has a software hazards analysis been performed?
C,4 Plan/expectation Plan for resolving questions identified to date
- Phone calls with APS personnel
- System life-cycle activities
- Procurement spec. requirements
- Procurement spec. requirements
- Requests for further documents
- Software audit of application specific software of PVNGS CPC - Westinghouse in Windsor, Ct (1St or 3rd week in June)
- Westinghouse implementation of life-cycle to CPC
- Focus on 2-4 CPC functions that trace from FSAR/SysRS to actual algorithm.
>> Function block generation
>> Software behind custom function blocks
>> Examples: DNBR, LPD, FSAR timing
- PVNGS visit to review APS activities (3rdweek June or 3rd week July) at PVNGS
- Procurement Spec conformance
- APS involvement
- APS procedure compliance
- Site acceptance test
- Can these visit time proposals be supported by APS and Westinghouse?
NRC will work with APS to provide agenda items and dates.
- NRC will be available to answer questions and provide further detail as APS needs for additional RAI's and visits or anything else of concern.