ML031110256

From kanterella
Jump to navigation Jump to search
7/24 - 25/2002 Davis Besse Lessons Learned Task Force Meeting
ML031110256
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/25/2002
From:
Office of Nuclear Regulatory Research
To:
References
FOIA/PA-2003-0018
Download: ML031110256 (14)


Text

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

-NROPreecisional Art Howell Ron Lloyd Joe Donoghue Bob Haag Tom Koshy Pat Castleman Russ Bywater Joelle Starefos Sonia Eischen (State of Ohio; Observer)

David Timm (Office of Inspector General)

Using modified IAEA approach. Fact Level. What Level. Conclusion Level.

a NRC failed to adequately assess svmptomsof RCS leakage.

12 A

CAC/Rad Monitor cleaning known by NRC through BC level 13 A

BA on head known by SRI during RFO12 16 A

RIII (Grant) knowledge of Rad Monitor 18 A

BCs logs on CAC/RMs & discussed in morning meetings 19 A

CAC cleaning observed by inspectors (DRS) 20 A

PM knew about CACs 22 A

DRP BC listed CAC cleaning (2001) 23 A

RIII didn't see CAC/RM cleaning as important 38 A

No one suggested NRC look at RCS leakage in containment during PIR 41 A

3 inspection reports discussing RMs without conclusions 52 A

RIII didn't view leakage as a problem 58 A

Multiple cleaning of CACs 76 A

No documentation of CAC evaluation inspection 77 A

No NRC doc of RM leak detection reliability insp.

1 of 14 IU

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NC PreDCciioa-83 A

No open items for CAC/RM or BA on head 87 A

Pzr safety valve mod increased leakage; NRC accepted without question 88 A

Assumed Pzr safety valve leakage was reason for CAC fouling 97 A

CR for CACJRM not seen as safety-sig would be screened out 98 A

NRC Briefing package for Merrified didn't include BA problems 107 A

TS requirements for CACIRM were relaxed 118 A

BC didn't tell RI to pursue BA issues 125 A

RA knew of CAC issues b

NRC failed to follow-up on Generic Communications.

59 B

62001 not used for DB (precursor events) 61 B

62001 used 15 reactors (all RIV PWRs) 62 B

No insp followup of GL97-01 66 B

NRC followup for 88-05 audited 10 plants; DB acceptable 129 B

TI on BU2001-01 didn't address BA issues 132 B

2515 IP do not look at BA/GC followup 133 B

The old inspection program (9000 series) looked at OE issues 154 B

  1. of Generic Comm (NRC) not corrected with # of events 156 B

MD8.5 can't be followed because it hasn't been updated 160 B

No NRC programmatic guidance for effectiveness review of generic comm.

161 B

Sample/shotgun method for verification of generic comm implementation 164 B

IP62001 deleted w/o considering why it existed 165 B

NRC generated 17 boric acid generic communication 187 B

11/93 SER recommended inspection (visual) or leak detection system 189 B

11/93 SER recognized circumferential cracking, but didn't make recommendations 2of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002) vNR C PieDe7isiona 1

190 B

Staff action plan GL97-01 can't be found 201 B

GL97-01 closeout for DB based on generic info 202 B

DB was the only B&W licensee that didn't do inspections (ref GL97-01) NRC 232 B

1972 requested enhanced ISI for BA corrosion c

NRC failed to understand implications of BA corrosion.

14 C

Licensee stated that NRR knew about BA on head 15 C

SRI saw CR on BA on head 28 C

BA CRs not selected for PIR 29 C

Abbreviated version (issue) of BA CRs not represented 33 C

No apparent NRC followup of 96, 98 PCAQs 42 C

Aware of BA on RPV head and didn't inspect 43 C

SRI knew of flange leaks 45 C

Neither of Residents received training on BA 49 C

DRP BC and former SRI (only) knew of flange leaks 50 C

Flange leaks not pursued 65 C

1992 precursor insp no perf issues/no F/U of BA control prog 95 C

RIII saw RC-2 as a material control problem -vs-boric acid prog prob 105 C

NRC doesn't review owner's group input 116 C

BC/SRI/RI didn't observe RPV head videos 128 C

RI reviewed CR/equivalent in some manner 130a C

BA buildup not a safety issue by NRC 155 C

NUREG 6245 (CRDM crack) NRC not aware of B&W content 169 C

NRC 1993 SER addressed RVH nozzle cracks as not immed. safety issue 197a C

Risk significance of BA on RPV head is low NRC 3 of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRC PreDecisional' 222 C

NRC staff believed dry boric acid not corrosive 226 C

Postulated breech of RPV not considered 227 C

Industry and NRC were managing BA issue by leakage 228 C

NRC doesn't review all of the industry guidance on BA 229 C

NUMARC 1993 and NEI 1995 letters - GL88-05 will let the industry locate leaks before a real problem is identified 233 C

1993 2.206 Greenpeace response - cracking issues d

NRC failed to establish adequate requirements.

139 D

Enforcement history doesn't equate with OE 140 D

Lack of enforcement for RCS leakage 141 D

Enforcement/NRR trying to figure out what should be done for RCS leakage 142 D

1997 SONGS nozzle cracking cited Maintenance Rule 143 D

NRC response (policy) not consistent - SONGS/Oconee 145 D

No ASME Code requirement (of inspections/RCS leakage) 146 D

Code didn't require insulation to be removed for inspections 147 D

VC Summer had RCS leakage and didn't report it 149 D

Several "no color" issues design -vs-performance 205 D

12/31/2001 was an arbitrary date for shutdown; basis question 219 D

Code did not require insulation removal (VT-2) 243 D

Enhanced visual meant for circ, not axial cracking (vol NDE) 245 D

ANO a through wall CRDM crack is a statistical certainty 253 D

Several CRDM nozzles cracked, some through wall NRC e

NRC g

r mete rogras failed to adeguatelv assess DB performance 1

E Region viewed Davis-Besse as good performer.

4of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

AVRU e-Decisionatl 8

E PM inspection approach changing.

21 E

One PPR summary listed CAC cleaning 25 E

PI&R/40500 did not review area 26 E

PI&R samples began 1999 for 3/01 (gap issue) 27 E

Gap of 2 /2 years between CA inspections (missed events) 39 E

Inspection reports don't list all docs reviewed (6 years of reports) 44 E

RC-2 escalated enforcement didn't require closeout inspection 46 E

Inspection on RM didn't provide any performance issues 47 E

Neither the old/new insp programs found/discussed RM issues 51 E

Former SRI did not perform any followup on leak hunt plan RFO12 55 E

NRC prompted Lic regarding RCS leak on MUIA described as positive in IR 56 E

DB PIR viewed as the best by RIII 60 E

62001 cancelled in 10/01 67 E

NRC audit of BAC didn't include Rx head/instr 71 E

Not enough hours in ROP for (BA) inspections didn't allow some inspection 72 E

Verbatim comp. W/insp procedures (not there/can't do) 73 E

Can't go outside of the baseline unless you have a >green finding 74 E

Baseline inspection doesn't include structures or passive components 75 E

ROP eliminated good practice of containment closeout insp 82 E

ISI didn't look at A600 85 E

RIII issued SL3 for RC-2; would be a green finding today 86 E

RC-2 event would have not gone beyond baseline 96 E

RIII had differing -views for RC-2 followup 100 E

Some interviews indicated RIISRI not as visible in ctmt and CR post ROP 5of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

XRl C-Pre-Decisional 106 E

MC2515 AppD doesn't provide thorough guidance for review of CR 115 E

NRR PM limited visits to DB 121 E

NRC thought that the licensee was rigorous in their leak hunt 122 E

RI thought the RPV head was 100% cleaned 127 E

ALARA insp didn't show that CAC cleaning was largest dose 204 E

No process for verifying licensee info for continued operation 206 E

PM don't conduct site visits 207 E

Some PM haven't visited plants 208 E

PM didn't review commitment change reports 211 E

NRR not implementing procedures 212 E

LA/SE for RM for RCS leakage didn't consider DB OE 213 E

NRR perception was that DB was a good performer 224 E

Risk informed process didn't alert the NRC to a potential risk 225 E

Over-reliance on risk information -vs-deterministic 252 E

62001 intended for 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> every other outage 270 E

Kerosene burner not eval'd for ctmt 271 E

No oper eval for the clogging of CACs 272 E

Non-conservative assumption of LOCA steam clean CACs 278 E

Lic didn't complete all RC2 CAs 290 E

No doc'd eval of CAC clogging 293 E

All PI's green prior to event 294 E

Inadequate temp mod safety eval on code safety seat leakage f

NRC staff resources & experience 2

F NRC staffing level not filled for all positions 6of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NAEPreDecisional 3

F One year period (1999), only one Resident on site.

4 F

Project Engineer - two 8-month gaps.

5 F

Resident inspectors not certified.

6 F

SRI position delayed in filling.

7 F

High Project Manager turnover rate (9 PMs in 10-years) 9 F

Limited commercial nuclear experience RI 10 F

Resident inspector had a materials background 11 F

SRI experience with only DB containment 40 F

Low number of inspection hours compared to other RIII sites (1/2 in 1999) 53 F

1998 events diverted inspection efforts re:BA issues 57 F

Resident not aware of OOS logs 63 F

PE little time at DB (1997&1999) 92 F

Between PE coverage gaps, 8 months/3months coverage/8 months 93 F

BC had Clinton 0350 plant coincident w/DB 110 F

RIII resources decreasing 111 F

RIII insp contractor support poor 112 F

Rill too many competing priorities which detract from insp.

131 F

No 1245 cert requirements for BA corrossion 158 F

Contract support after '98 report dried up (staff decreased/# reports decreased) 167 F

AEOD had 80+ FTE; now 2.5 FTE for OE (RES) 215 F

No guidance for background training for PM g

~

NRC failed to communicate critical information 17 G

Other than DD-DRP; others didn't recollect CAC/RM issues 94 G

NRR inspection branch has no feedback form on Plant status time as addressed by RI interview 7of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRCPriD ezsioratlU 101 G

Procedure for RIII morning meeting isn't followed 102 G

RIII not conducive to info exchange 103 G

Senior RIII Managers not the audience for the morning meeting 117 G

RI not aware of FeO on CAC 126 G

RA didn't know about BA on head 136 G

IRO didn't participate to follow MD8.3 for AIT determination 137 G

NRR/RIII didn't follow MD8.3 203 G

Deferral of DB shutdown not well documented 216 G

Interviews indicate that NRR and RIII communications poor/nonexistent 291 G

Late arrival of calcs for crack propagation h

NRC failed to adequately assess relevant operating experience 157 H

OE review in NRC not performed by independent or long review 163 H

NRR is reactive for short-term/current event 166 H

NRC generic issue program takes too long/too hard...use bulletins instead 170 H

Foreign OE was reviewed by NRC 171 H

70 LERs about Boric Acid leaks 172 H

Axial cracks known from early 1970s, Circumferential from 1980s 173 H

LIC-503 references some wrong procedures in RES 183 H

No clear process for using foreign experience 184 H

French corrective actions were documented but never used 185 H

Mind set that French CA was an over reaction from NRC perspective; aggressive inspection was reponse 186 H

NRC never asked the French why they were replacing their RPV heads 188 H

Swedish, Spanish, Japanese, French have replaced heads 193 H

NRR staff not aware BA leakage OE 8of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

XlC-PreDeeisionab 209 H

RES procedure 2i not used/not known by staff 210 H

Cracking/BA corrosion not considered by either NRR or RES to be a GI (MD 6.4) 230 H

GI program relies on user needs before taking action 231 H

Preferred process flow for OE: nothing; IN; BU; GL; GI (all else fails) 297 H

No NRC review of submittals/reports (ISI) i Licensee failed to implement Fo p guidance.

202a I

DB was the only B&W licensee that didn't do inspections (ref GL97-01) LIC 236 I

No BWOG verification for implementation of GL97-01 237 I

No BWOG verification for implementation of GL88-05 247 I

No tracking system to ensure that industry guidance was included in site guidance/

processes.

261 I

93 B&W report flange leaks need to be eval first 289 I

BA corr handbook shows CAC/RM as evidence of RCS leak i

Licensee failed to understand implications of BA corrosion.

32 J

BA on head was a "routine" CR 36 J

1996 CR on BA stayed open for -2 years 130 J

BA buildup not a safety issue by DB 155a J

NUREG 6245 (CRDM crack) Industry not aware of B&W content 178 J

BACC person also had many other duties as a system engineer 194 J

BWOG rep didn't know the significance of Brown/red tinted BA buildup 197 J

Risk significance of BA on RPV head is low LIC 217 J

BA procedure not "QA" until 5/02 234 J

Mod on service structure delays 239 J

Ombudsman & cleaning statements 274 J

PRG staff didn't viewed head tapes 9of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRCPre-Decisional\\

275 J

Former VP viewed as-found, not after tape until Fall2001 282 J

Only staff involved in head cleaning 296 J

PCAQ 96-0551 was one of ten oldest CRs before it was resolved 298 J

Multiple people involved in head cleaning w/o raising issues 299 J

Same job done by Framatome at other plants?

k Licensee failed to resolve chronic RCS leakage.

24 K

Routine CAC cleaning 108 K

CAC/RM fouling may have been the impetus for TS change in #107 109 K

HEPA filter for RM may defeat the purpose of the RM workarounds -vs-fix the problem 119 K

Licensee not rigorous in finding RCS leaks 120 K

Licensee deleted Mode 3 walkdown for BA 235 K

CAC fouling and ALARA 244 K

DB entered a 6-hour shutdown TS situation because of RM Problems with BA 248 K

Ability to differentiate between flange leakage/ head penetration leakage 255 K

Until RFO13 lic had flange leaks 262 K

Heavy boron buildup on CACs 268 K

No systematic leak search for 12RFO 269 K

Deleted mode 3 walkdown 273 K

Long history of thermowell leaks 280 K

Triage plan for flange leak / didn't fix all flange leaks 287 K

100% NDE 5.7Rem estimate <past head cleaning 300 K

Relief valve mod masking other leaks in 1998-99 time frame i

Licensee failed to properlv implement an adequate BACC program.

34 L

1996 CR explicit on the BA concern 10of 14

I Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRC PreDedisiwal,

35 L

-50% of RPV head cleaned in 1996 70 L

BAC checklists not kept/tracked/trended 123 L

None of the RPV head cleanings were 100%

124 L

Lost control of video tapes 144 L

BAC procedure wasn't followed 251 L

Appropriate cleaning methods for RPV head (water-vs-vacuum) 254 L

  1. 4, 5 nozzles still had boron on them following cleaning 260 L

Couldn't complete head cleaning due to schedule pressure 263 L

Potential CRDM G9 leak was crack, not dispositioned 266 L

RCS sys engr: scaffold was removed without permission 267 L

RP considered head cleaning as decon, so no procedure 279 L

No deviations from RF012 WO to clean RPV head 281 L

RCS sys engineer upset that they head wouldn't be totally cleaned 283 L

Index of head tapes incomplete 284 L

4/17/00 head mislabeled as as-left 285 L

Head inspection tape not documented as to what was actually inspected - QA zip m

Licensee failed to learned from internaVexternal OE.

68 M

DB's BACC didn't include Rx head/instr until 5/02 151 M

Oconee OE not evaluated at DB until 5/2002 152 M

OE in US...Boric acid leaks. #1 area was CRDM, DB considered not significant 153 M

100% B&W units had RCS PB leakage 162 M

DB OE procedure doesn't require NRC LER review 168 M

100% CE had RCS pressure boundary leakage 174 M

45% of Oconee cracking (CRDM) appears in the same quadrant as DB leakage problems 11 of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRCT'feDeeisional1 175 M

CE plants dominated RCS instrumentation nozzle leakage (10 of 13 leaks) 176 M

Average # of operating years prior to CRDM leakage -22 years 179 M

Foreign experience would indicate that the "crack" model is flawed 191 M

NUREG/CR 6245 recommended enhanced online leakage detection systems (NRC?)

192 M

Calvert Cliffs LER indicated wet boron vs dry 198 M

Annealing nozzle temps were different than required 200 M

3 LERS involved pzr material wastage 218 M

B&W recommended the service structure mod 276 M

Two precursor BA events... RC2, SG line n

Licensee staff resources & experience 159 N

40-50% DB staff decrease over 10 years 246 N

Multiple job assignments depending on cycle (outage, ops, EP) 277 N

Lack of system engineer continuity o

Licensee failed to communicate critical information 150 0

Lic Response to BU2001-01 contained many inaccurate info /response 177 0

Many licensee (DB) staff thought that a whole head inspection/cleaning was done 264 0

Lic Managers I staff knew of head cleaning %, lower staff thought that head was 100% cleaned 265 0

Lic managers said they showed NRC the as-found video tapes of the head w

Awaiting additional review 31 W

We rely on lic to give NRC correct info 37 W

Long time to close out CRs 54 W

CCW event (10/98) resulted in Spec Insp 64 W

Limited entries into containment by NRC 78 W

1997 NOPINOT walkdown by NRC found no leaks 12of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRC PreDecisional 81 W

1992 uptake event insp closeout, then 1998 uptake occurred 84 W

RIII factored BU2001-01 commitments as part of Baseline prog.

89 W

RIII invoked MC0350 w/o DB having met criteria 90 W

DB event risk not completed yet 91 W

SDP has taken 5 months 113 W

Only 1 SES manager inside containment since 1996 114 W

Limited senior manager visits to DB 134 W

No NRC review of Ombudsman files 138 W

Range of opinions on whether an AIT/IIT/SI 180 W

Story differences between what DB told NRC -vs-what NRC thought they were told about BA by DB 181 W

NRR not told about red/brown BA buildup until after the DB event 182 W

After the RPV head videos were shown to the NRC, a vote was taken: 3 for shutdown; remaining (10-13) voted to allow continued operation 196 W

Conclusion in the EPRI guidebook not supported 199 W

"Boric acid on the head is good."

214 W

INPO ratings declined from 1 to 2 within the last few years 220 W

DB experienced no insulation deflections caused by BA buildup on the head 221 W

License Renewal report (GALL) addresses acceptability of GL88-05 for aging management to be updated to reflect lessons learned 223 W

Extending the inspection for DB was largely based on the belief that a "strong" VT-2 inspection was done at DB 238 W

O&M/capital budget and actuals have decreased over last 10-years 240 W

BU2001-01 documentation responses by DB not accurate 241 W

12-16 people at DB reviewed DB response to BU2001-01 242a W

MNSA - repair of joints, boric acid issues NRC 13 of 14

Davis-Besse Lessons Learned Task Force Meeting (7/24-25/2002)

NRCPreDecisiohrcah 242 W

MNSA - repair of joints, boric acid issues LIC 249 W

Bonus correlation with operations 256 W

VP - No NDE tools by 12/31 257 W

VP -Ops last know 259 W

Lic did not eval use of power washer 292 W

QA group didn't have a problem with BAC RFO12 report shows positive finding 295 W

NRC questioned how the licensee was able to do a visual insp. given that boron was left on the head x

Deleted 30 X

CRs reviewed for PI&R -7000 48 X

SSDI insp in 2000 indicated performance was worse than expected 69 X

40500 insp in '98 indicated that commitment tracking NG 79 X

SRI 97-98 no recollection of flange leaks 80 X

Former SRI works for FENOC 99 X

PI&R doesn't allow independent look by inspectors 104 X

PI&R team leader thought that the short form description of CR was adequate 135 X

RIII inspector was told that DB was SALP 1 didn't take findings seriously (arrogant) 148 X

Nothing in allegation area was relevant to BA/cracking issues 195 X

BACC person indicated that the next major nuclear accident will be caused by BAC 250 X

Basis for dose estimates for RPV head inspections 258 X

Eng received closed door talking to for CR initiation 286 X

Lic is doing an assessment of BU2001-01 submittal 288 X

No VT-2 insp during RFO12 per RCS sys eng 14of 14