MONTHYEARML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22109A2122022-04-20020 April 2022 Duke Energy Pre-Submittal Public April 20, 2022, Meeting Presentation ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML21322A3262021-11-29029 November 2021 Duke Energy November 29, 2021 Pre-Submittal Public Meeting Slides for EOF Relocation Licensing Amendment Request ML21090A1162021-03-31031 March 2021 Combined 2020 Aam Presentation ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21033A7022021-02-0303 February 2021 Pre-submitting for Planned LAR for Standby Liquid Control Tank Volume Increase ML21011A0822021-01-12012 January 2021 Pre-Submittal Meeting January 12, 2021, Revision to VRR-01, Full Stroke Testing of Safety/Relief Valves - Presentation Material ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML20099C9992020-04-0808 April 2020 Har 2019 Mtg Slides ML20099D1282020-04-0808 April 2020 Bru 2019 Mtg Slides ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML19123A3532019-05-0202 May 2019 Public Meeting Summary - Brunswick Steam Electric Plant, Docket Nos. 05000325 and 05000324 ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17297B7892017-10-26026 October 2017 Meeting Slide for Partially Closed Pre-submittal Public Meeting with Duke Energy for License Amendment Request to Adopt Areva'S XM-11 Fuel Methodology for Brunswick Steam Electric Plant ML17229B2942017-08-22022 August 2017 Meeting Slide Regarding Partially Closed Pre-submittal Public Meeting with Duke Energy for a License Amendment Request for Brunswick Steam Electric Plant ML16231A1322016-08-18018 August 2016 Materials for 8/18/16 Pre-Application Meeting Brunswick Mellla+ LAR ML16210A5152016-07-28028 July 2016 Bnp Commercial Grade Dedication Issue (Printable) ML16134A1742016-05-12012 May 2016 Summary of Public Meeting - 2015 Annual Assessment Regarding Brunswick, Units 1 and 2 ML14140A1882014-05-19019 May 2014 Summary of Public Meeting - 2013 Annual Assessment Regrading Brunswick Steam Electric Plant ML14135A5112014-04-17017 April 2014 Enclosure 4 to BSEP 14-0048 - Areva Mellla+ Methods Applicability Presentation (Non-Proprietary Version) ML14135A5092014-04-17017 April 2014 Enclosure 1 to BSEP 14-0048, Duke Energy Presentation - Brunswick Mellla+ Methods Applicability, Pre-Application Meeting ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13277A0382013-09-24024 September 2013 GEH Presentation on Methods Applicability to Areva Atrium 10XM Fuel ML13277A0372013-08-20020 August 2013 Duke Energy Presentation - Brunswick Mellla+ Methods Applicability, Pre-Application Meeting, August 20, 2013 ML13130A2552013-05-10010 May 2013 4/24/2013 - Meeting Summary - Category 3 Public Meeting - Annual Assessment of Brunswick Steam Electric Plant ML12181A0362012-06-29029 June 2012 Meeting Summary - Category 1 Public Meeting - Annual Assessment of Brunswick Steam Electric Plant, Docket Nos. 50-325, 50-324 ML12158A3442012-06-0606 June 2012 Meeting Slides for Pre-Application Meeting with Carolina Power and Light Company Regarding Emergency Diesel Generator Completion Time Extension for Brunswick Steam Electric Plant, Units 1 and 2 ML11102A0052011-04-12012 April 2011 Progress Energy - Slides for NFPA 805 Pre-LAR Application Meeting April 12, 2011 ML1020304622010-07-20020 July 2010 Groundwater Protection Status ML1016705232010-06-0808 June 2010 NRC Fire Protection Screening Criteria, Brunswick Nuclear Plant ML1015404182010-05-27027 May 2010 Meeting Summary - Public Meeting - Brunswick Steam Electric Plant Annual Assessment - Reactor Oversight Program 2009 Presentation Slides ML1001507632010-01-15015 January 2010 Meeting Presentation Brunswick Nuclear Plant Human Performance ML1001507042010-01-14014 January 2010 Human Performance Slides ML0930206712009-10-22022 October 2009 Emergency Diesel Generators - Progress Energy ML1019400952009-10-0808 October 2009 Marsh, River, and Creek Tritium Results Updated 10/08/09 ML1019400932009-10-0808 October 2009 Groundwater Well Samples Results, Updated 10/08/09 ML0923210802009-08-20020 August 2009 MELLLA Plus Implementation ML0921609632009-08-0404 August 2009 Meeting Summary - Public Meeting Category 1 - Preliminary White Finding - Brunswick Steam Electric Plant ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML1019404532008-05-21021 May 2008 Email from Grzeck, Lee to Heather Gepford, Austin, Joe, George Kuzo, England, Louise, Kemp, Daniel and Dale.Dusenbury@Ncmail.Net; Subject: Storm Drain Collection Basin and Storm Drain Stabilization.Pdf; Sampling Locations Data Updated 5-19- ML0813006582008-05-0101 May 2008 EOC 2007 NRC Slides ML0813006662008-05-0101 May 2008 EOC 2007 Progress Energy Slides ML1019405012008-04-0101 April 2008 Annual Report Slides BSEP 07-0108, Areva Presentation Slides for Brunswick Fuel Transition License Amendment Request2007-07-31031 July 2007 Areva Presentation Slides for Brunswick Fuel Transition License Amendment Request ML0711503272007-04-23023 April 2007 Brunswick, EOC Slides, Cy 2006 ML0710803842007-04-18018 April 2007 Presentation Slides from Public Management Meeting to Discuss Brunswick Site and Emergency Diesel Generator Improvements 2022-09-14
[Table view] |
Text
i Progress Energy 2/25/2003 1
Agenda EZZ - -.
- Presentation o Licensing Basis Lenny Belier o Present Concern Roger Sims o Resolution Roger Sims
- Conclusion David Hinds SlProgress Energy 2
2/25/2003
Licensing Bases i March 1981: Exemption Requested for Automatic Suppression in Control Room (CR) and CSRs
- November 1981: Exemption G ranted for CR o CSR Addressed Separately
- July 1982: NRC-CP&L Meeting 9 November 1982: NRC Denied Exemption Request SsProgress Energy 2/25/2003 3
Licensing Bases e May 1983 Exemption Request o "We propose the installation of a manually operated, fixed sprinkler system located below the cable trays for these zones. The suppression systems will be designed to extinguish a transient combustible fire. We believe the proposed manually operated, fixed, sprinkler system will provide protection equivalent to Section IiI.G.3, 10CFR50, Appendix R."
C Progress Energy 2/25/2003 4
Licensing Bases
- July 1983 SER o "However, you have proposed to install a manually operated sprinkler system in the cable spreading room of each Brunswick unit. This type of fixed fire suppression meets the requirements of Section III.G.3 and therefore, an exemption is not needed.... Based on this discussion, we understand that you will begin modification of the Diesel Generator Building equipment hatches and the installation of fixed floor-mounted suppression systems in the Cable Spreading Rooms within six months."
SvProgress Energy 2/25/2003 5
Licensing Bases
. Resident Inspector Considered Configuration a Risk Concern
- Task Interface Agreement Sent to NRC Headquarters
- Violation Proposed Against GDC 3 Progress Energy 2/25/2003 6
Present Concern - Initial Response I-
. Technical Study Performed i Correlated Sprinkler Response Vs. Cable Damage Time
- Due to Lack of Validated Analysis Method Study Assumed Sprinkler System Would Not Actuate for Fire between Heads.
D Resident Inspector Provided a [Draft Copy of Study SJProgress Energy 2/25/2003 7
Plan View ISO=Islam Sprinkler Heads SJProgress Energy 2/25/2003 8
Section View N a-m,, - -.
Trays Plume y _-------Sprinkler Head Fire Progress Energy 2/25/2003 9
Present Concern - Study Results 47, o 146 kW Fire P No Cable Damage in 30 Minutes o639 kW Fire SCi8tble Damage in 30 Minutes o783 kW Fire I Cable Damage in 20 Minutes 9 In No Cases Were both Trains Damaged Due to a Si ngle Fire Progress Energy 2/25/2003 10
Present Concern
- 10/2/02 NRC Inspection Report 02-03 o The licensee failed to install fixed fire suppression systems that were capable of minimizing damage to safe shutdown cabling caused by floor level transient combustible fires in the Unit 1 and Unit 2 Cable Spreading Rooms (CSRs). The systems were determined to be unable to fulfill their intended function of limiting fire damage to the preferred trains of safe shutdown cables and safety-related cables in the CSRs.
Energy S 2/25/2003 11
Alternatives for Resolution EZZ.
- Install C,ode Compliant Sprinkler System above and within Cable Trays SSprinkler Contractor Stated Code Compliance May Not Be Pc )ssible o May Not Satisfy FSAR Commitment 8 Progress Energy 2/25/2003 12
Alternatives for Resolution rzzz
- Remove Sprinkler Links o System Will Not Support All Heads Flowing Hydraulically I Drainage Is a Problem Progress Energy 2/25/2003 13
Alternatives for Resolution
. Strengthen Other Areas of Defense-In-Depth P Requires NRC Approval o No Physical Changes to Sprinkler System Progress Energy 2/25/2003 14
Resolution LITI - 1,. - 4.....
"* Restrict Transient Combustibles below that Analyzed as Capable of Causing Cable Damage
"* Install Incipient Fire Detection System
"* Convert System from Manual to Automatic
. Submit Change to Licensing Basis to Remove Term "and Extinguish" Progress Energy 2/25/2003 15
Conclusions 77-E
. Questions?