ML030510344
| ML030510344 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 02/20/2003 |
| From: | Mahesh Chawla NRC/NRR/DLPM/LPD3 |
| To: | Skolds J Exelon Generation Co, Exelon Nuclear |
| References | |
| TAC MB4851, TAC MB4852 | |
| Download: ML030510344 (1) | |
Text
Containment Spray and Cooling Systems 3.6.6 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3.6.6.4 Verify each containment spray pump's In accordance developed head at the flow test point is with the greater than or equal to the required Inservice developed head.
Testing Program SR 3.6.6.5 Verify each automatic containment spray 18 months valve in the flow path that is not locked, sealed, or otherwise secured in position, actuates to the correct position on an actual or simulated actuation signal.
SR 3.6.6.6 Verify each containment spray pump starts 18 months automatically on an actual or simulated actuation signal.
SR 3.6.6.7 Verify each containment cooling train 18 months starts automatically on an actual or simulated actuation signal.
SR 3.6.6.8 Verify each spray nozzle is unobstructed.
Following maintenance that could result in nozzle blockage OR Following fluid flow through the nozzles BRAIDWOOD - UNITS 1 & 2 3.6.6-3 Amendment 126