Summary Reports for In-Service Inspection & Repairs or Replacements
ML030130011
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 01/09/2003
From: Sen G
Entergy Nuclear Operations, Entergy Nuclear Vermont Yankee
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BVY 03-02
Download: ML030130011 (33)


Text

Entergy Nuclear Vermont Yankee, LLC Entergy Entergy Nuclear Operations, Inc.

185 Old Ferry Road Brattleboro, VT 05302-0500 January 9, 2003 BVY 03-02 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

Subject:

Vermont Yankee Nuclear Power Station License No. DPR-28 (Docket No. 50-271)

Vermont Yankee 2002 Summary Reports for In-service Inspection and Repairs or Replacements Pressure Vessel In accordance with Article IWA-6000 of Section XI of the ASME Boiler and Summary Report for Code, Vermont Yankee (VY) hereby submits the 2002 Form NIS-I Owner's for Repairs and In-service Inspections and the 2002 Form NIS-2 Owner's Summary Report replacements Replacements. These reports describe the in-service inspections, repairs and 2001 through October 25, 2002. VY's third ten-year performed during the period May 21, interval began September 1, 1993.

have questions or We trust that the information provided is adequate; however, should you require additional information, please contact Mr. Jim DeVincentis at (802) 258-4236.

Sincerely, Gaau d*m / 4en Manager, Licensing Attachments cc: USNRC Region I Administrator USNRC Resident Inspector - VYNPS USNRC Project Manager - VYNPS Vermont Department of Public Service Inspection Agency - Factory Mutual Insurance Company

/\

SUMMARY

OF VERMONT YANKEE COMMITMENTS 1BVY NO.: 03-02 Vermont Yankee 2002 Summary Reports for In-service Inspection and Repairs or Replacements The following table identifies commitments made in this document by Vermont Yankee.

Any other actions discussed in the submittal represent intended or planned actions by Vermont Yankee. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Licensing Manager of any questions regarding this document or any associated commitments.

COMMITMENT COMMITTED DATE OR "OUTAGE" None N/A VYAPF 0058.04 AP 0058 Original Page 1 of I

SEntergy Entergy Northeast Vermont Yankee 2002 Form NIS-1 Owner's Summary Report For Inservice Inspections May 21, 2001 through October 25, 2002 Reviewed by: Date: ( 0-c, nserv e Insp tion Coordinator Approved by: _ Date: 12-i"o-02 Systm/ ngineering Manager

FORM NIS-1 OWNER'S REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules

1. Owner Entergy Northeast Vermont Yankee, 185 Old Ferry Road, Brattleboro VT 05352 (Name and Address of Owner)
2. Plant Entergy Northeast Vermont Yankee, P.O. Box 157, Governor Hunt Road, Vernon, VT 05354-0157 (Name and Address of Plant)
3. Plant Unit 1 4. Owner Certificate of Authorization (if required) DPR-28
5. Commercial Service Date 11/30/72 6. National Board Number for Unit NONE
7. Components Inspected - SEE ATTACHED PAGES 2 THROUGH 16.
8. Examination Dates 5/21/01 to 10/25/02 9. Inspection Interval from 911/93 to 8/31/2003
10. Applicable Editions of Section XI 1986 Addenda None
11. Abstract of Examinations Including a list of examinations and a statement concerning status of work required for current interval - SEE ATTACHED PAGES 2 THROUGH 18.
12. Abstract of Conditions Noted - SEE ATTACHED PAGES 19 and 20.
13. Abstract of Corrective Measures Recommended and Taken - SEE ATTACHED PAGES 19 and 20.

We certify that the statements made in this report are correct and the examinations and corrective measures taken conform to the rules of the ASME Code,Section XI.

Certificate of Authorization No. (If applicable) DPR-28 Expiration Date 3/21/2012 Date b f, ý/J/ t1F 200Z- Signed f77&4-" "- Ach By /ýVa.0.,/-

4 Zfner,/ 7( AI - ;2, )ALiL I CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and/or the State or Province of Vermont and employed by Factory Mutual Insurance Company of Johnston, Rhode Island, have inspected the components described in this Owner's Report during the period May 21, 2001 to October 25, 2002 and state to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owner's Report in accordance with the requirements of the ASME Code,Section XI By signing this certificate neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owner's Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

Commissions VT-350 Inspe r's gnature National Board, State, Province, and Endorsements Date 6*2-J9-, 200P.-

Page 1 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 System ID Drawing No. Examination ASME Category Component ID Exam Type B-A BCFlange Weld RPV Head to UT, MT Nuclear Boiler ISI-RPV-103 Acceptable N4C-IR Acceptable B-D Feedwater Nozzle Inner UT Inner Radius Nuclear Boiler ISI-RPV-103 Examined area that was Radius limited during RFO-22.

B-D N5B UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Nozzle to Shell Weld B-D N5B-IR UT Inner Radius Nuclear Boiler ISI-RPV-103 Acceptable RPV Nozzle Inner Radius N6A B-D RPV Head Nozzle to Shell UT Nuclear Boiler ISI-RPV-103 Acceptable Weld N6A-IR B-D RPV Head Nozzle Inner UT Inner Radius Nuclear Boiler ISI-RPV-103 Acceptable Radius N6B B-D RPV Head Nozzle to Shell UT Nuclear Boiler ISI-RPV-103 Acceptable Weld N6B-IR B-D RPV Head Nozzle Inner UT Inner Radius Nuclear Boiler ISI-RPV-103 Acceptable Radius N7 B-D RPV Head Nozzle to Shell UT Nuclear Boiler ISI-RPV-103 Acceptable Weld N7-IR B-D RPV Head Nozzle Inner UT Inner Radius Nuclear Boiler ISI-RPV-103 Acceptable Radius Page 2 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Exam Type System ID Drawing No. Examination ASME Category Component ID I I I I Results B-D N9 UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Nozzle to Shell Weld B-D N9-IR RPV Nozzle Inner Radius UT Inner Radius Nuclear Boiler ISI-RPV-103 Acceptable Acceptable B-F No1-oSE PT Nuclear Boiler ISI-RPV-103 Examined in accordance with BWRVIP-27-A.

RPV Nozzle to Safe End Weld B-F N12B-SE PT Nuclear Boiler ISI-RPV-103 Acceptable RPV Nozzle to Safe End Weld N6A-SE B-F RPV Head Nozzle to Safe End UT, PT Nuclear Boiler ISI-RPV-103 Acceptable Weld N6B-SE B-F RPV Head Nozzle to Safe End UT, PT Nuclear Boiler ISI-RPV-103 Acceptable Weld N7-SE B-F RPV Head Nozzle to Safe End UT, PT Nuclear Boiler ISI-RPV-103 Acceptable Weld B-F N9-SE UT, PT Nuclear Boiler ISI-RPV-103 Acceptable RPV Nozzle to Safe End Weld B-G-1 45-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G- 1 45-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 45-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing Page 3 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 System ID 1

DrawingNo.

1 j Examination xait ASME Category Component ID Exam Type I I Results B-G-1 46-N VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 46-S UT Nuclear Boiler ISI-RPV- 103 Acceptable RPV Stud B-G-1 46-W/B VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 47-N VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-I 47-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 47-W/B VT-I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 48-N VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-I 48-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 48-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 49-N VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 49-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud Page 4 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 System ID DrawingNo. Examination ASME Category Component ID Exam Type B-G-1 49-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 50-N VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 50-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 50-W/B VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 51-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G- 1 51-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 51-W/B VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 52-N VT-I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1RPV 52-S Stud UT Nuclear Boiler ISI-RPV-103 Acceptable B-G-1 52-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 53-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut Page 5 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 11 Exam Type 1 System ID 1 DrawingNo. Examination Results ASME Category Component ID B-G-1 53-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 53-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 54-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B--54-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 54-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-C-i 55-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B--55-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 55-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 56-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-C-i 56-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 56-W/B VT-1 Nuclear Boiler ISI-RPV- 103 Acceptable I RPV Washer/Bushing IIIII Page 6 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Exam Type System ID DrawingNo. Examination ASME Category Component ID I I I I Results B-G-1 57-N VT-i Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-57-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 57-W/B VT- I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 58-N VT-i Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 58-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 58-W/B VT-I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 59-N VT-I Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 59-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 59-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing VT-1 Nuclear Boiler ISI-RPV-103 Acceptable B-G-I 60-N RPV Nut B-G-1 60-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud Page 7 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Exam Type System ID DrawingNo. Examination ASME Category Component ID B-G-1 60-W/B VT-I Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 61-N RPV Nut VT-1 Nuclear Boiler ISI-RPV-103 Acceptable B-G- 1 61-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 61-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 62-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G-1 62-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 62-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-I 63-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut B-G- 1RPV 63-S Stud LT Nuclear Boiler ISI-RPV-103 Acceptable B-G-1 63-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-1 64-N VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Nut Page 8 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 11 System ID 1 DrawingNo.

1 Examination E mResults ASME Category Component ID Exam Type B-G-1 64-S UT Nuclear Boiler ISI-RPV-103 Acceptable RPV Stud B-G-1 64-W/B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable RPV Washer/Bushing B-G-2 10-15B VT-1 CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 10-35B VT-1 CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 14-39B VT- I CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 30-15B VT- I CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 30-31B VT-i CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 30-39B VT-1 CRD ISI-RPV-104 Acceptable CRD Bolting B-G-2 N7-B VT-1 Nuclear Boiler ISI-RPV-103 Acceptable Flange Bolting B-G-2 VIO-27A VT-I Residual Heat Removal ISI-RHR-PART ii SHI Acceptable Valve Bolting B-G-2 V10-88 VT-I Residual Heat Removal ISI-5920-6622 SHI Acceptable Valve Bolting Page 9 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/2 Components Inspected/Abstract of examinations Sections 7 and 11 Examination ASME Category Component ID Exam Type System ID Drawing No. Results B-G-2 V14-12A Valve Bolting VT-i Core Spray ISI-5920-9211 Acceptable B-G-2 V14-14A Valve Bolting VT-I Core Spray ISI-5920-9211 Acceptable B-G-2 V2-29A Valve Bolting VT- I Feedwater ISI-FDW-PART 5 Acceptable B-G-2 V2-53A Valve Bolting VT-I Nuclear Boiler ISI-5920-6622 SH1 Acceptable B-J MS7A-A7A UT, MT Main steam ISI-RPV-105 Acceptable Code Case N-560 Selection Piping Weld B-J MS7B-B6 UT, MT Main steam ISI-RPV-105 Acceptable Code Case N-560 Selection Piping Weld B-J MS7C-N3C-SW UT, MT Main steam ISI-RPV-105 Acceptable Code Case N-560 Selection Piping Weld B-J MS7D-D8 UT, MT Main steam ISI-RPV-105 Acceptable Code Case N-560 Selection Piping Weld B-J RH33-15 UT, MT Residual Heat Removal ISI-5920-9283 Acceptable Code Case N-560 Selection Piping Weld B-J RH33-16 UT, MT Residual Heat Removal ISI-5920-9283 Acceptable Code Case N-560 Selection Piping Weld B-J SL11-F10 PT Standby Liquid control ISI-SLC-PART 4 Acceptable Piping Socket Weld Page 10 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Component ID Exam Type System ID DrawingNo. Examination ASME Category B-J SL11-Fl I PT Standby Liquid control ISI-SLC-PART 4 Acceptable Piping Socket Weld B-J SLI 1-F4 PT Standby Liquid control ISI-SLC-PART 4 Acceptable Piping Socket Weld B-J B-J Piping Socket Weld SL1e W-5 PT Standby Liquid control ISI-SLC-PART 4 Acceptable B-J SLI1I-F6 PT Standby Liquid control ISI-SLC-PART 4 Acceptable Piping Socket Weld B-J SLI l-F7 PT Standby Liquid control ISI-SLC-PART 4 Acceptable Piping Socket Weld B-K CS-2 PT Core Spray ISI-5920-9211 Acceptable Integral Attachment B-K RPV SUPPORT SKIRT PT Nuclear Boiler ISI-RPV-103 Acceptable Support A-HTEX10-1 C-A RHR Heat Exchanger Shell UT Residual Heat Removal ISI-RPV-104 Acceptable Weld A-N4 Acceptable C-B RHR Heat Exchanger Nozzle MT, VT-2 Residual Heat Removal ISI-RPV- 104 See page 19 for conditions to Shell Weld noted/correctie measures taken C-C CS-HD61A MT Core Spray ISI-5920-9211 Acceptable Integral Attachment IIIII Page 11 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 ASME Category Component ID Exam Type System ID DrawingNo. Examination I. I I I Results C-C H-A-RHR-CC-3 Integral Attachment MT Residual Heat Removal ISI-RPV-104 Acceptable C-C RHR-H187 Integral Attachment PT Residual Heat removal ISI-RHR-PART I1 SH3 Acceptable C-F-2 RH5A-S209 UT, MT Residual Heat Removal ISI-RHR-PART 11 SH3 Acceptable Piping Weld C-P-2 RH5B-S220 Piping Weld UT, MT Residual Heat Removal ISI-5920-9288 Acceptable C-F-2 RH6-P231 Piping Weld UT, MT Residual Heat Removal ISI-RHR-PART 11 SH3 Acceptable C-F-2 RH6-S233 UT, MT Residual Heat Removal ISI-RHR-PART 11 SH3 Acceptable Piping Weld C-F-2 RH7-S261 UT, MT Residual Heat Removal ISI-5920-9288 Acceptable Piping Weld H-E-8-1AReactor Bldg. Closed D-A H-E-8-A VT-i ISI-RCW-PART 4 SH I Acceptable Integral Attachment Cooling Water D-A H-P-8-1A Integral Attachment VT-1 Service Water ISI-SW-PART 2 SH4 Acceptable H-TK-- 1 AReactor Bldg. Closed D-A H-TK-7-1A VT- 1 Reco lg lsd ISI-RCW-PART 3 SH I Acceptable Integral Attachment Cooling Water F-A ACSP-HD203B Support VT-3 Standby Gas Treatment ISI-5920-9201 Acceptable Page 12 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 1 1 Drawing No.

1 Examination E mResults ASME Category Component ID Exam Type System ID F-A CS-2 VT-3 Core Spray ISI-5920-9211 Acceptable Support F-A CU-2 VT-3 Reactor Water Clean up ISI-5920-6622 SH1 Acceptable Support F-A H-A-RHR-CC-1 VT-3 Residual Heat Removal ISI-RPV-104 Acceptable Support F-A H-A-RHR-CC-2 VT-3 Residual Heat Removal ISI-RPV-104 Acceptable Support F-A H-A-RHR-CC-3 VT-3 Residual Heat Removal ISI-RPV-104 Acceptable Support F-A H-A-RHR-CC-4 VT-3 Residual Heat Removal ISI-RPV-104 Acceptable Support F-A H-P-7-1A VT-3 Service Water ISI-SW-PART 3 SH2 Acceptable Support Acceptable F-A H-P-8-1A VT-3 Service Water ISI-SW-PART 2 SH4 See page 19 for conditions Support noted/corrective measures taken Acceptable F-A H-S-31A VT-3 Service Water ISI-SW-PART 3 SHI See page 20 for conditions Support noted/corrective measures taken F-A RHR-H187 Support VT-3 Residual Heat removal ISI-RHR-PART 11 SH3 Acceptable Page 13 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Examination System ID DrawingNo. Results ASME Category Component ID Exam Type F-A RHR-HD200B VT-3 Residual Heat Removal ISI-RHR-PART 11 SH2 Acceptable Support VT-3 Nuclear Boiler ISI-RPV-103 Acceptable F-A Support SKIRT RPV SUPPORT F-A RSW-H165 VT-3 RHR Service Water ISI-SW-PART I SH2 Acceptable Support F-A RSW-H166 VT-3 RHR Service Water ISI-SW-PART I SH2 Acceptable Support F-A RSW-H169 VT-3 RHR Service Water ISI-SW-PART 6 SH2 Acceptable Support F-A RSW-H 170 VT-3 RHR Service Water ISI-SW-PART 9 Acceptable Support F-A RSW-H177 VT-3 RHR Service Water ISI-SW-PART 6 SH2 Acceptable Support F-A RSW-H179 VT-3 RHR Service Water ISI-SW-PART 9 Acceptable Support F-A RSW-H 180 VT-3 RHR Service Water ISI-SW-PART 6 Acceptable Support F-A RSW-H216 VT-3 RHR Service Water ISI-SW-PART 2 SH3 Acceptable Support F-A RSW-H220 VT-3 RHR Service Water ISI-SW-PART 2 SH4 Acceptable Support Page 14 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Exam Type System ID DrawingNo. Examination ASME Category Component ID I I Results F-A RSW-H220 VT-3 RHR Service Water ISI-SW-PART 2 SH4 Acceptable F-A RSW-H221 VT-3 RHR Service Water ISI-SW-PART 2 SH4 Acceptable Acceptable RSW-H226A VT-3 RHR Service Water ISI-SW-PART 3 SH4 See page 19 for conditions F-A Support noted/corrective measures taken F-A RSW-H226B VT-3 RHR Service Water ISI-SW-PART 3 SH4 Acceptable F-A RSW-H232 VT-3 RHR Service Water ISI-SW-PART 10 SH5 Acceptable Acceptable RSW-H233 VT-3 RHR Service Water ISI-SW-PART 10 SH5 See page 19 for conditions F-A noted/corrective measures Support taken F-A RSW-HD216B VT-3 RHR Service Water ISI-SW-PART 2 SH3 Acceptable F-A RSW-HD225A VT-3 RHR Service Water ISuI-SW-PART 4 H3 Acceptable F-A RSW-HD88C VT-3 RHR Service Water ISI-SW-PART 2 SHI Acceptable F-A SLC-H47 VT-3 Standby Liquid Control ISI-SLC-PART 4 Acceptable ISupportII Page 15 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code Rules Entergy Northeast Vermont Yankee Owner Certification: DPR.28 Commercial Service date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Exam Type System ID DrawingNo. Examination ASME Category Component ID F-AUG CS-HD61A VT-3 Core Spray ISI-5920-9211 Acceptable Support Acceptable VT-3 Core Spray ISI-5920-9211 See page 20 for conditions F-AUG CS-HD61B noted/corrective measures Support taken F-AUG CS-HD61C VT-3 Core Spray ISI-5920-9211 Acceptable Support Augmented Seismic ASCSP-H201A VT-3 Standby Gas Treatment ISI-AC-PART 5 Acceptable Support Program Support Augmented Seismic MSD-HD7 VT-3 Main Steam VYI-MSD-PART 2B Acceptable Support Program Support Page 16 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service Date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Quantity Previously Quantity Scheduled, Third Percent of Third Interval Code Category Quantity Inspected 2002 odCerOutage Inspected, Third Interval Interval Complete B-A 1 15 16 100%

B-D 10 48 58 100%

B-F 6 29 35 100%

B-G-1 60 168 228 100%

B-G-2 13 77 90 100%

9 B-J 6 Code Case N-560 was first 15 100%

Code Case N-560 selection. used for selection during RFO-22.

B-J These are ASME Category B-J, Item B9.40 socket welds 6 16 22 100%

which are not included in the Code Case N-560 selection.

B-K 2 8 10 100%

Per approved Relief Request N/A B-L-2 0 0 No. B-1 Page 17 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service Date: 11/30/72 Components Inspected/Abstract of examinations Sections 7 and 11 Code Category Quantity Inspected 2002 Quantity Previously Quantity Scheduled, Third Percentof Third Interval oOutage Inspected, Third Interval Interval Complete B-M-2 0 26 Per approved Relief Request N/A BM2 0 26No. B-2 B-N-1 0 2 Each Period 100%

B-N-2 0 Partial 1 100%

B-O 0 7 7 100%

C-A 1 3 4 100%

C-B 1 3 4 100%

C-C 3 17 20 100%

C-F-2 5 67 72 100%

D-A 3 8 11 100%

F-A 31 88 119 100%

Page 18 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service Date: 11/30/72 ABSTRACT OF CONDITIONS NOTED/CORRECTIVE MEASURES TAKEN Sections 12 and 13 Code Category Item Identification ConditionsNoted and Corrective Measures Taken Surface examination of RHR Heat Exchanger E-14-1A nozzle to shell weld A-N4 revealed two rejectable indications. Inservice Discrepancy report # 02-06 was generated to request engineering evaluation. Mechanical Design Engineering dispositioned the IDR as follows: The weld in the as found 3A-N4 condition can perform its design function. The indications were welding/construction related. Remove C-B Athe indications per memo VYM 182/88. Work Order 01-004584-097 was generated to mechanically remove the indications. Ultrasonic thickness readings were taken prior to, during and after removal. The indications were removed with minimal material loss and an acceptable surface examination was documented.

VT-3 visual examination of restraint RSW-H-233 revealed a loose bolt (the nut was tight) on the hanger clamp. Inservice Discrepancy report # 02-01 was generated to request engineering evaluation.

Mechanical Design Engineering dispositioned the IDR as follows: The identified loose bolt does not F-A RSW-H-233 compromise the structural integrity of the clamp/support configuration. The fact that the nut is tight ensures that the bolt will not fall out. The second bolt is actually the load carrying component with no identified anomalies. No further action is required/use-as-is.

VT-3 visual examination of restraint RSW-226A revealed a cotter pin not sufficiently bent. Inservice Discrepancy report # 02-02 was generated to request engineering evaluation. Mechanical Design F-A RSW-226A Engineering dispositioned the IDR as follows: Support function is not degraded by identified condition.

Initiate work order to bend pin to desired configuration." The work was performed as part of the Fix It Now team effort and an acceptable VT-3 was performed to document the work having been performed.

VT-1 visual examination of RHR Service Water Pump H-P-8-1A integral attachment weld revealed numerous areas of under fill and undercut. Inservice Discrepancy report # 02-01 was generated to request engineering evaluation. Mechanical Design Engineering dispositioned the condition via F-A H-P-8-1A Technical Evaluation 2002-042 as follows: A conservative minimum size for the pump barrel weld is a 3/16" fillet weld. Actual field inspection demonstrates that the as found weld configuration/size exceeds the minimum required. The existing weld is therefore demonstrated as capable of transferring/resisting the applied design loading and no further action is required - use-as-is Page 19 of 20

FORM NIS-1 OWNER'S DATA REPORT FOR INSERVICE INSPECTIONS As Required by the Provisions of the ASME Code rules Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service Date: 11/30/72 ABSTRACT OF CONDITIONS NOTED/CORRECTIVE MEASURES TAKEN Sections 12 and 13 Code Category Item Identification Conditions Noted and CorrectiveMeasures Taken VT-3 visual examination of Service Water Strainer support H-S-3-1A revealed lack of proper thread engagement on 3 of the 4 base plate anchors. Inservice Discrepancy report # 02-04 was generated to F-A H-S-3-1A request engineering evaluation. Mechanical Design Engineering dispositioned the IDR as follows: This issue was identified and addressed as "Accept As Is" previously under work orders 99-001981-000 &

99-002650-000. No action required.

VT-3 visual examination of spring hanger CS-HD6IB revealed spring can settings outside the acceptable range (+/- 5%). Inservice Discrepancy report # 02-05 was generated to request engineering evaluation of this condition. Mechanical Design Engineering dispositioned the IDR as follows: All values are within the working range of the spring, therefore the support can perform its design function.

F-AUG CS-HD61B The springs are to be reset to the values shown on drawing 5920-6401 sheet 1. The adjacent gravity hangers CS-HD6IC & CS-HD6IA shall be inspected when resetting the springs to ensure that no abnormal pipe movement is observed and that they still function as designed. Work Order 0 1-004584 096 was generated to reset the spring cans to the required setting. An acceptable VT-3 examination was performed after the resetting of the springs.

Page 20 of 20

SEntergy Entergy Northeast Vermont Yankee 2002 Form NIS-2 Owner's Summary Report For Repairs or Replacements May 21, 2001 through October 25, 2002 Reviewed by: A ," Date: IZ--4, - -

Approved by: Date: /2.16-oZ

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As required by the Provisions of the ASME Code Section XI

/

1. Owner Entergy Northeast Vermont Yankee Date / /b6;,-

Name 185 Old Ferry Road, Brattleboro VT 05352 Sheet 1 of 9 Address 1)

L.° DI

.[ amHl Entergy Northeast Vermont Yankee Unit 1 Name P.O Box 157, Governor Hunt Road, Vernon, VT 05354 N/A Address Repair Organization P.O. No, Job No, etc.

3. Work Performed by Entergy Northeast Vermont Yankee Type Code Symbol Stamp N/A Name Authorization No. N/A 185 Old Ferry Road, Brattleboro VT 05352 Expiration Date N/A Address
4. Identification of System See attached table, pages 3 through 9
5. (a) Applicable Construction Code B 31.1 1967 Edition, No Addenda, No Code Case (b) Applicable Edition of Section XI Utilized for Repairs or Replacements 1986 Edition No Addenda
6. Identification of Components Repaired or Replaced and Replacement Components See attached table, pages 3 through 9
7. Description of Work See attached table, pages 3 through 9
8. Tests Conducted See attached table, pages 3 through 9
9. Remarks See attac L eA ta 1- 1 e, paRCS 12 Lt. roug L n Page 1 of 9

Form NIS-2 (cont.)

CERTIFICATE OF COMPLIANCE We certify that the statements made in the report are correct and these repairs/replacements conform to the rules of ASME Code,Section XI.

Type Code Symbol Stamp N/A Certificate of Authorization Number N/A Expiration Date N/A Signed = *__. 6Su-fuss, .-Date System Engineering endent, 17" _ _ , 20 __"

CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Vermont and employed by Factory Mutual Insurance Company of Johnston, Rhode Island have inspected the components described in this Owner's Report during the period May 21,2001 to October 25, 2002 and state to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owner's Report in accordance with the requirements of the ASME Code,Section XI.

By signing this certificate neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owner's Report. Furthermore, neither the inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

Commissions V'T nspector's Signature National Board, State, Province, and Endorsements Date /,2 - /7f-20 0 P-Page 2 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11130/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case Manufacturer National OtherIdentification Repair, ASME Component System Manufacturer Serial Board Replaced, Code ofsWorkt Conduct Equipment Number S mu rer bor Minor Modification, Built Replacementof Work Conducted Number Number Design Change etc. Replacement Stamped General N/A N/A WO 01-005194-006 1972 Replaced N/A Replaced System CRD-10-15 CRD Electric CRD Leakage General N/A N/A WO 01-005194-008 1972 Replaced N/A Replaced System CRD-10-23 CRD Electric CRD Leakage General N/A N/A WO 01-005194-002 1972 Replaced N/A Replaced System CRD-10-35 CRD Electric CRD Leakage General N/A N/A WO 01-005194-005 1972 Replaced N/A Replaced System CRD-14-39 CRD Electric CRD Leakage General N/A N/A WO 01-005194-007 1972 Replaced N/A Replaced System CRD-18-19 CRD Electric CRD Leakage General NIA N/A WO 01-005194-003 1972 Replaced N/A Replaced System CRD-30-15 CRD Electric CRD Leakage CRD-30-31 CRD General N/A NIA WO 01-005194-001 1972 Replaced N/A Replaced System Electric CRD Leakage CRD-30-39 CRD General N/A N/A WO 01-005194-004 1972 Replaced N/A Replaced System Electric CRD Leakage Replaced System N/A WO 01-002335-000 1972 Replaced N/A Valve Leakage TCV-24-3A DG Amot N/A Inservice Refurbished Leak TCV-24-3B DG Amot N/A N/A WO 01-005807-000 1972 Repaired N/A valve Leak Page 3 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case Manufacturer National Other Identification Repair, ASME Component System Manufacturer Serial Board Work OrderNo., Year Replaced, Code Description Test Equipment Number MinorModification, Built of Work Conducted Number Number Design Change etc. Replacement Stamped Replaced System TK-3-125-26-19 HCU Liquidonics N/A N/A WO 02-002285-000 1972 Repaired N/A Accum. Functiona tank N/A- repaired Bergen ADH-301-1598 N/A WO 01-005321-000 1972 Replaced N/A Replaced structural IPCI-HD103GN HPCI Patterson Snubber members only N86476 Replaced System SR-23-34 HPCI Crosby 0001 N/A WO 01-004330-000 1972 Replaced N/A Safety Leakage Valve N81993 Replaced System SR-23-66 HPCI Crosby 0001 N/A WO 01-004338-000 1972 Replaced N/A Safety Leakage Valve N/A WO 01-006272-001 1972 Repair N/A Replaced System V23-14 HPCI Walworth N/A Stem Leakage V23-3 HPCI Enertech NIA N/A MM 2001-051 1972 Replaced N/A Replaced System valve Leakage Replaced System N/A MM 2001-051 1972 Replaced N/A valve Leakage V23-4 HPCI Enertech N/A System Replaced Leakage in RRU-8 HVAC H. K. Porter M-24442 N/A MM 2002-001 Si 1972 Repaired N/A ~~~cooling coolcoi coil accordance wihod with Code Case N-416-1 Page 4 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case Manufacturer National Other Identification Repair, ASME Description Test Component Work OrderNo., Year Repair, ASMe Equipment Number System Manufacturer I Serial Number Board Number MinorModification, Design Change etc.

Built Replaced, Replacement Coded Stamped N/A- repaired WO 01-005241-000 1972 Replaced N/A Replaced structural MS-3 MS ITT Grinell 32194 N/A Snubber members only N/A- repaired Repacd /A N/A Replaced Snubber structural members Lynair 32197 N/A WO 01-005181-000 1972 Replaced RR-2 NB only Replaced System RV-2-71A NB Target Rock 205 N/A WO 01-005199-000 1972 Replaced N/A Relief Valve Leakage Replaced System Leakage N/A WO 01-005202-000 1972 Replaced N/A Valve RV-2-71B NB Target Rock 67-HH- 11 Replaced System WO 01-005204-000 1972 Replaced N/A Valve Leakage RV-2-71C NB Target Rock 67-HH- 12 N/A Replaced System RV-2-71D NB Target Rock 204 N/A WO 01-005206-000 1972 Replaced N/A Relief Leakage Valve Replaced System SV-2-70B NB Dresser BL 1137 N/A WO 01-005472-000 1972 Replaced N/A Relief Leakage Valve Repaired System Leakage N/A WO 02-004406-003 1972 Repaired N/A Linear ed.

V2-80B NB Rockwell 119 Repaired System V2-86B NB Rockwell N/A N/A WO 02-004468-000 1972 Repair N/A (3) Linear Leakage Ind. Leakage Page 5 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case CnpnetWork Manufacturer National Order No.,

OtherIdentification Year Rear Repair, SE ASME Description Test Component System Manufacturer Serial Board Mor OdercNon, Buil Replaced, Code ofsWorktiondTet Equipment Number Number Number Replacement Stamped Design Change etc.

DRYWELL- PCAC CBI N/A N/A WO-02-002156-000 1972 Replaced N/A Replaced 4 PCLRT HEAD Bolt Assy.

V16-19-12A PCAC Walworth N/A N/A WO 01-003067-000 1972 Repaired N/A Replaced PCLRT Valve Seat V16-19-12B PCAC Walworth N/A N/A WO 01-003068-000 1972 Repaired N/A Replaced PCLRT VaplvedSeate V70-71D RB Velan N/A N/A WO 99-011105-000 1972 Replaced N/A Replaced System Valve Leakage Replaced System P-18-lB RBCCW Byron Jackson 671-S-1109 N/A MM 2002-023 1972 Replaced N/A RBCCW Leakage piping Leakage VYDC 200 1-003 Replaced System N/A 0004-000 WO 01-004558-000 1972 Replaced N/A vale Lea V 13-6 RCIC Enertech Model DRV-2 WO valve Leakage VYDC 2001-003 1972 Replaced N/A Replaced System V13-7 RCIC Enertech Model DRV-2 N/A valve Leakage RV-20-94A RDW Consolidated N/A N/A WO 01-004328-000 1972 Replaced N/A Replaced System Dresser Valve Leakage Replaced System N/A WO 01-005038-000 1972 Replaced N/A Snubber Leakage CS-HD54A RHR Miller Electric 26352 691-N-0364 N/A WO 02-001883-000 1972 Replaced N/A RePump Leakage System P-8-1B RHR Byron Jackson

-W I I PupLekg Page 6 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case Manufacturer National OtherIdentification Repair, ASME Work Order No., Year Description Test Equipment Number System Manufacturer Serial Board Minor Modification, Built Replaced, Code of Work Conducted Number Number Design Change etc. Replacement Stamped N/A- repaired Replaced structural 1972 Replaced N/A Snubber members RHR Miller Electric 32195 N/A WO 01-005177-000 RHR-H197B only N/A- repaired Replaced structural 1972 Replaced N/A Snubber members RHR Miller Electric 32196 N/A WO 01-005178-000 RHR-HDI27M only 1972 Replaced N/A Replaced System RHR Dresser TL33016 N/A WO 01-001904-000 SR-10-86B 1972 Repaired N/A Replaced System V1-8BSW HR CCI N/A N/A WO 00-001858-000 Valve Trim Leakage VRO-89B System Replaced motor Leakage accordancein RHRSW Byron Jackson 691-N-0364 N/A MM2002-022 1972 Replaced N/A bearing with Code P-8-1B cooling line Case N-416-1 Repaired System P-8-1D RHRSW Byron Jackson 691-N-0366 N/A MM 2002-043 1972 Repaired N/A Pump Leakage Casing Replaced System 1972 Replaced N/A Relief SyLea SLC Crosby L-2761 N/A WO 01-005382-000 SR- I 1-39A Leakage Valve Replaced System SR-11-39B SLC Crosby L-2939 N/A WO 01-005383-000 1972 Replaced N/A Relief Leakage I IValve Page 7 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case SyteaMnuacurrrerialtionard Manufacturer Comonnt National Other Order No.,

WorkIdentification Year Replaced, Repair, Code ASME Description Description nducte Test Equipm entNubr System Manufacturer Serial Board Minor Modification, Built Replacedn Codmed Equipment Number Number Number Replacement Stamped of Work Conducted

_ _ _ __ Design Change etc.

3"SW-37A SW N/A N/A N/A WO 02-002006-000 1972 Replaced N/A Replaced System

_______ Piping Leakage N/A WO 01-002894-000 1972 Replaced N/A Replaced System 3"SW-37B SW N/A N/A Piping Leakage System Modified Leakage in 8"SW- 18A SW N/A N/A N/A MM 2002-027 1972 Replaced N/A water accordance supply line with Code Case N-416-1 Replaced System WO-01-003123-000 1972 Replaced N/A Pump Leakage P-7-1C SW Byron Jackson 691-N-0359 N/A Anchor 949070A-1 NIA WO 02-003461-000 1972 Replaced N/A Replaced System SP-70-3B SW Darling Pipe Nipple Leakage Replaced WO 01-002984-000 1972 Repaired N/A valve disc System V13-131 SW Walworth 530IBSB-WE N/A and stem; Leakage lapped seat System Leakage in V70-101 SW Velan N/A N/A WO 95-005089-000 1972 Replaced N/A Valve accordance with Code SCase N-416-1 WO 01-006408-000 1972 Replaced N/A Replaced System V70-315A SW Jenkins N/A N/A

_fLI l II IValve Leakage Page 8 of 9

FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required by the Provisions of the ASME,Section XI, 1986 Edition, No Addenda Entergy Northeast Vermont Yankee Owner Certification: DPR-28 Commercial Service date: 11/30/72 Construction code: B31.1, 1967 Edition, No Addenda, No code Case ComonntSyteaMnuacurrrerialtionard Manufacturer Order No.,

or Identification Year Replaced, Repair, Code ASME ofeWoripti Description on dTeste Test National Other Equipment Number SManufacturer Seral SystemmWorkOrdereNoNmearr_______ Board Minor Modification, Built Replacement Stamped N Design Change etc.

SW Jenkins N/A N/A WO 01-006410-000 1972 Replaced NIA Repalved Sysemg V70-317A Replaced System V70-319A SW Jenkins N/A N/A WO 01-006410-000 1972 Replaced N/A Valve Leakage SW Jenkins N/A N/A WO 01-006475-000 1972 Replaced N/A Replaced Valve System Leakage V70-319A V70-7A SW Crane N/A N/A WO 00-003806-000 1972 Replaced N/A Replaced System Valve Leakage SW Crane N/A N/A WO 01-003834-000 1972 Replaced NA Replaced System V70-713 Page 9 of 9