Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company January 14, 2003

Davis-Besse Oversight Panel - Public Meeting January 2003 Purposes of This Meeting

  • Inform the Public of the NRCs Oversight Panel Activities
  • Discuss Licensees Progress on Implementing the Return to Service Plan 2

Davis-Besse Oversight Panel - Public Meeting January 2003 AGENDA

  • Introduction and Opening Remarks
  • Summary of Dec. 10th & Dec. 23rd Public Meetings
  • Discussion of NRCs Restart Checklist and Status of NRC Inspections
  • Licensee Presentation on the Status of Their Return to Service Plan
  • Adjourn NRC meeting with FENOC

<break>

  • Public Comments and Questions of NRC
  • Adjourn Meeting 3

Davis-Besse Oversight Panel - Public Meeting January 2003

SUMMARY

OF DEC. 10, 2002 PUBLIC MEETING

  • Topics Discussed

- Management & Human Performance Excellence Plan

- Operations Root Cause

- Restart Preparations

- Containment Health Plan

- System Health Assurance

- Plant Program Reviews

- 0350 Action Progress

- FENOC Alignment for Sustained Operations

- QA Oversight of FENOC Alignment

  • Transcripts of the Dec. 10, 2002, meetings will be available on our web site. http://www.nrc.gov/

4

Davis-Besse Oversight Panel - Public Meeting January 2003

SUMMARY

OF DEC. 23, 2002 PUBLIC MEETING

  • Topics Discussed

- System Health Assurance

- Open Design Questions

  • Transcripts of the Dec. 23, 2002, meeting will be available on our web site. http://www.nrc.gov/

5

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Adequacy of Root Cause Determination

- Penetration cracking and reactor pressure vessel corrosion

- Organizational, programmatic and human performance issues 6

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Adequacy of Safety Significant Structures Systems and Components

- Reactor pressure vessel head replacement

- Containment vessel restoration

- Structures, systems and components inside containment

- Emergency core cooling system and containment spray system sump

- Systems outside containment 7

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Adequacy of Safety Significant Programs

- Corrective action program

- Operating experience program

- Quality audits and self-assessments of programs

- Boric acid corrosion management program

- Reactor coolant system unidentified leakage monitoring program

- In-service inspection program

- Modification control program

- Radiation protection program 8

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Adequacy of Organizational Effectiveness and Human Performance

- Adequacy of root causes

- Adequacy of corrective actions

- Effectiveness of corrective actions 9

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Readiness for Restart

- Systems readiness for restart

- Operations readiness for restart

- Test program development and implementation 10

Davis-Besse Oversight Panel - Public Meeting January 2003 Restart Checklist

  • Licensing Issue and Confirmatory Action Letter Resolution

- Resolve three limited ASME code relief requests

- Meet with the NRC to obtain restart approval 11

Davis-Besse Oversight Panel - Public Meeting January 2003 CONTINUING NRC INSPECTIONS

  • Organizational Effectiveness and Human Performance
  • System Health Reviews
  • Safety Significant Program Effectiveness
  • Resident Inspection 12

Davis-Besse Oversight Panel - Public Meeting January 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO January 14, 2003, 7:00 pm EST Purpose of Meeting:

Inform the Public of the NRCs Oversight Panel Activities 13

Davis-Besse Oversight Panel - Public Meeting January 2003 GOALS

  • One of the goals of this meeting is to receive comments / questions from all interested members of the public. To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.

14

Davis-Besse Oversight Panel - Public Meeting January 2003 AGENDA

  • Introduction and Opening Remarks
  • Summary of Vessel Head Degradation Issue
  • Summary of Todays Public meeting
  • Comments/Questions from local members of the public 15