Letter Sequence Other |
---|
|
|
MONTHYEARML0232505062002-11-22022 November 2002 RAI, Amendment Request to Allow Plant Operation with Associated Containment at Atmospheric Pressure (TAC Nos. MB5303 & MB5304) Project stage: RAI ML0233304922002-11-29029 November 2002 Draft Request for Additional Information (Rai), Regarding Amendment Request to Allow Plant Operation with Associated Containment at Atmospheric Pressure Project stage: Draft RAI L-02-115, Response to a Request for Additional Information in Support of License Amendment Requests Nos. 300 & 1722002-12-0202 December 2002 Response to a Request for Additional Information in Support of License Amendment Requests Nos. 300 & 172 Project stage: Response to RAI ML0301000742002-12-11011 December 2002 Responses to (Request for Additional Information) RAI Questions on MAAP5 Topical Report Project stage: Request ML0300906222003-01-0909 January 2003 Firstenergy Nuclear Operating Company an Application for a License Amendment to Allow FENOC to Convert the Beaver Valley Power Station Containments to Operate at Atmospheric Pressure Project stage: Other ML0312201452003-05-0202 May 2003 Request for Additional Information - Conversion from Subatmospheric to Atmospheric Containment Project stage: RAI ML0315601402003-06-0505 June 2003 (BVPS-1 and 2) - Request for Additional Information (RAI) - Conversion from Subatmospheric Containment Project stage: RAI ML0325302042003-09-10010 September 2003 Issuance of Amendment Nos. 257 & 139, Respectively, Approving Selective Implementation of Alternate Source Term and Control Room Habitability Techinical Specification Changes Project stage: Approval ML0325501732003-09-10010 September 2003 Technical Specification Pages for Amendment Nos. 257 & 139 to License Nos. DPR-66 & NPF-73, Respectively, Selective Implementation of Alternate Source Term & Control Room Habitability Project stage: Acceptance Review ML0323300032003-09-22022 September 2003 Summary of Meeting with Firstenergy Nuclear Operating Co Licensee'S MAAP5 Computer Code Modifications to Support Its Application for a License Amendment for Containment Conversion Project stage: Meeting 2003-01-09
[Table View] |
|
---|
Category:Meeting Minutes
MONTHYEARML0300906222003-01-0909 January 2003 Firstenergy Nuclear Operating Company an Application for a License Amendment to Allow FENOC to Convert the Beaver Valley Power Station Containments to Operate at Atmospheric Pressure ML0308000302002-11-17017 November 2002 Extract from the Minutes of the Meeting of the Board of Directors of Firsenergy Corp. Held November 17, 2002 2003-01-09
[Table view] Category:Meeting Summary
MONTHYEARML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections ML23026A3552023-01-31031 January 2023 Summary of Public Meeting with Energy Harbor Nuclear Corp. Regarding Beaver Valley Power Station License Amendment Request to Consolidate Fuel Decay Time TS Into New Limiting Condition for Operation ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML22105A3932022-04-20020 April 2022 Summ. of March 17, 2022, Public Meeting with Ehnc Regarding Planned License Amendment Request to Consolidate Fuel Decay Time Requirements in a New Limiting Condition for Operation for Beaver Valley Power Station, Units 1 and 2 ML22053A2982022-02-25025 February 2022 Summary of the February 15, 2022, Meeting with Energy Harbor Nuclear Corp. Regarding the License Amendment Request Related to Revising TS 5.6.3 Core Operating Limits Report (COLR) ML21308A0712021-11-0909 November 2021 Summary of Teleconference with Energy Harbor Nuclear Corp. Regarding Fall 2021 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20197A2722020-07-15015 July 2020 2020 Beaver Valley, Calvert Cliffs, Limerick Peach Bottom, Susquehanna Annual Assessment Webinar Summary ML20148M3852020-06-0101 June 2020 Summary of May 26, 2020, Public Meeting with Energy Harbor Nuclear Corp. Potential License Amendment Request Related to Steam Generator Tube Sleeve Inspections and Maintenance ML20122A0032020-05-19019 May 2020 Summary of April 22, 2020, Teleconference with Energy Harbor Nuclear Corp. Regarding Spring 2020 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20111A0142020-04-27027 April 2020 Summary of March 31, 2020, Public Meeting with Energy Harbor Nuclear Corp. to Discuss COVID-19 Potential Submittals of Regulatory Actions ML19280A0382019-10-22022 October 2019 Ti 2515-191 Summary of Findings ML16125A5072019-10-22022 October 2019 Ti 191 Issue Matrix ML19191A1882019-07-0909 July 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - Meeting Summary ML18325A0232018-11-28028 November 2018 Summary of Teleconference with Firstenergy Nuclear Operating Company Regarding Fall 2018 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML18099A0812018-04-0606 April 2018 Bv Annual Assessment Meeting Summary and Attendance List 2018 ML17347A8082017-12-20020 December 2017 December 5, 2017, Summary of Public Meeting with Firstenergy Nuclear Operating Company to Discuss a Proposed License Amendment Request Extending Sleeve Life on the Steam Generator at Beaver Valley Power Station, Unit 2 ML17158B1662017-06-0909 June 2017 Summary of Meeting with Firstenergy Nuclear Operating Company Regarding the Spring 2017 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML17082A1842017-03-28028 March 2017 March 20, 2017, Summary of Annual Assessment Meeting with Beaver Valley, Units 1 and 2 ML16250A5012016-10-0303 October 2016 Summary of August 30, 2016, Meeting with Firstenergy Nuclear Operating Company Regarding Planned Submittal of Emergency Action Level Scheme Change ML16105A0082016-04-25025 April 2016 March 30, 2016, Summary of Meeting with Firstenergy Nuclear Operating Company on Its Draft Probabilistic Risk Assessment RAI Related to Its License Amendment Request to Adopt NFPA Standard 805 ML16091A0702016-03-31031 March 2016 2016 Beaver Valley Annual Assessment Meeting Summary 2016 ML15320A3912015-11-24024 November 2015 Summary of Conference Call Regarding the Fall 2015 Steam Generator Inspections ML15225A4812015-08-14014 August 2015 July 23, 2015, Summary of Meeting with Representatives of the U.S. Army Corps, U.S. Nuclear Regulatory Commission and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station ML15135A2982015-05-21021 May 2015 Summary of April 28, 2015, Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station, ML15104A6652015-04-14014 April 2015 April 9, 2015 Summary of Annual Assessment Meeting with Beaver Valley Power Station, Units 1 and 2 ML14325A7782014-12-16016 December 2014 October 6, 2014, Summary of Pre-Application Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Combination of Site Emergency Plans ML14184B1962014-08-14014 August 2014 Summary of June 18, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and Firstenergy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Stat ML14160B1032014-07-10010 July 2014 June 6, 2014 Summary of Meeting with FENOC Flooding Hazard Reevaluation Extension Request for Beaver Valley Power Station, Units 1 and 2 and Flooding Hazard Reevaluation Report for Davis-Besse Nuclear Power Station, Unit 1 ML14142A0872014-06-0909 June 2014 Summary of Conference Call Regarding the Spring 2014 Steam Generator Inspections ML14099A1732014-04-0909 April 2014 Annual Assessment Meeting Summary, ROP14 ML13295A2182013-10-22022 October 2013 Summary of Public Meeting with Beaver Valley, ML13114A2072013-04-22022 April 2013 Summary of Annual Assessment Meeting at Beaver Valley ML13057A6782013-03-11011 March 2013 2/20/2013 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Request for Additional Information Response Regarding Beaver Valley Power Station End-of-Life Moderator Temperature Coefficient Testing ML12321A3012012-11-29029 November 2012 Summary of November 15, 2012, Meeting with Firstenergy Nuclear Operating Company to Discuss Upcoming License Amendment Request Relating to the Implementation of the Alternate Pressurized Thermal Shock Rule ML12310A0662012-11-13013 November 2012 Summary of Conference Call with Firstenergy Nuclear Operating Company to Discuss 2012 Steam Generator Tube Inspections ML12293A0402012-11-0101 November 2012 October 18, 2012 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Request for Additional Information Regarding Fenoc'S Extension Request for Upcoming Beaver Valley Power Station National Fire Protection Association ML12277A4082012-10-0303 October 2012 September 26, 2012, Summary of Public Meeting to Discuss FENOC Fleet Performance ML12223A4672012-08-22022 August 2012 August 1, 2012 - Summary of Meeting with FENOC to Discuss Upcoming National Fire Protection Association Standard 805 License Amendment Request Status ML12195A1132012-07-16016 July 2012 Summary of Public Meeting with FENOC Regarding Licensing Practices and Processes ML12104A1052012-04-13013 April 2012 Meeting Summary of Annual Assessment Meeting on March 22, 2012 ML1115805152011-06-15015 June 2011 (BVPS-2) - Summary of Conference Call Regarding the Spring 2011 Steam Generator Tube Inspection Results ML1112504622011-05-0505 May 2011 Summary of Annual Assessment Open House Public Meeting, Beaver Valley ML1035606612010-12-29029 December 2010 Summary of Beaver Valley Power Station, Unit 2 Public Conference Call Regarding Spent Fuel Pool Rerack LAR Draft RAI Responses Discussion ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 ML1014105172010-05-21021 May 2010 Summary of the May 2010 Annual Assessment Open-House Public Meeting ML1013206652010-05-18018 May 2010 Summary of Category 1 Teleconference with Firstenergy Nuclear Operating Company to Discuss NRC Request for Additional Information Regarding Generic Letter 2004-02 ML1009502432010-04-0505 April 2010 Meeting Summary of 3-31-10 Public Meeting with FENOC ML0931407282009-11-18018 November 2009 Steam Generator Tube Inspections ML0909203872009-04-0202 April 2009 Summary of Annual Assessment Open-House Meeting Regarding the Safety Performance of the Beaver Valley Units 1 and 2 2023-06-28
[Table view] |
Text
January 9, 2003 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2
SUBJECT:
SUMMARY
OF DECEMBER 11, 2002, MEETING REGARDING AN APPLICATION FOR A LICENSE AMENDMENT TO ALLOW FENOC TO CONVERT THE BEAVER VALLEY POWER STATION CONTAINMENTS TO OPERATE AT ATMOSPHERIC PRESSURE (TAC NOS. MB5303 AND MB5304)
On December 11, 2002, the U.S. Nuclear Regulatory Commission (NRC) staff, with support from a contractor, held a meeting at NRC headquarters in Rockville, Maryland, with representatives from FirstEnergy Nuclear Operating Company (FENOC), the licensee for the Beaver Valley Power Station, Units 1 and 2 (BVPS-1 and 2); Westinghouse Electric Company (W), Fauske & Associates, Inc. (FAI); and Stone & Webster. The list of meeting attendees is included as Enclosure 1. Enclosures 2 and 3 are copies of the slides presented at the meeting by the licensees consultant, FAI, and the NRCs contractor, Mr. Jack Tills, respectively. The presentations closely followed information presented in the slides.
By letter dated June 5, 2002, FENOC submitted an amendment request to allow plant operation of BVPS-1 and 2 with containments at atmospheric pressure. The application relies on WCAP-15844, Topical Report on Modular Accident Analysis Program Version 5 (MAAP5) Pressurized Water Reactor (PWR) Large Dry Containment Model, which was submitted separately by W and is being reviewed in parallel with the NRC staffs review of FENOCs application. By letters dated November 22, 2002 (ADAMS Accession Nos. ML023250506 and ML023250519), the NRC staff issued requests for additional information (RAIs) to FENOC and W regarding the application and the topical report respectively. FENOC responded to the RAI by letter dated December 2, 2002, (ADAMS Accession No. ML023430155) and W responded to the RAI by letter dated December 4, 2002 (ADAMS Accession No. ML023520323).
FAI, the licensees consultant, presented responses to the NRC staffs RAIs as docketed in the December 2, and December 4, 2002, letters. The NRC staff asked several questions during the presentation to seek clarification on various aspects of the responses.
The NRCs contractor presented an overview of preliminary findings from review of FENOCs application and the WCAP on which the application relies. The NRC staff stated that they have concerns with some of the proposed models included in the MAAP5 code that yield non-conservative results when applied to BVPS-1 and 2. The staffs concerns regarding the WCAP-15844 methodology must be adequately addressed before the NRC staff can approve the topical report for use in containment analyses and before the NRC staff can approve FENOCs amendment request.
FENOC The attendees from FENOC, W, FAI, and Stone & Webster stated that they understood the NRC staffs concerns regarding the WCAP and that they will conduct further internal discussions to develop supplemental submittals that address the NRC staffs concerns.
FENOC also stated that they may evaluate other methods, such as a containment structural analysis, of demonstrating the containments abilities to safely operate at higher pressures without having to rely on the WCAP-15844 methodology.
/RA/
Daniel S. Collins, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
- 1. List of Meeting Attendees
- 2. FAI Meeting Slides
- 3. NRC Contractors Meeting Slides cc w/encls: See next page
FENOC The attendees from FENOC, W, FAI, and Stone & Webster stated that they understood the NRC staffs concerns regarding the WCAP and that they will conduct further internal discussions to develop supplemental submittals that address the NRC staffs concerns.
FENOC also stated that they may evaluate other methods, such as a containment structural analysis, of demonstrating the containments abilities to safely operate at higher pressures without having to rely on the WCAP-15844 methodology.
/RA/
Daniel S. Collins, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosures:
- 1. List of Meeting Attendees
- 2. FAI Meeting Slides
- 3. NRC Contractors Meeting Slides cc w/encls: See next page DISTRIBUTION:
PUBLIC S. Richards OGC T. Bergman, EDO, RI Plants PDI-1 Reading R. Laufer ACRS J. Rogge, RGN-I J. Zwolinski/T. Marsh R. Lobel D. Collins B. Platchek, RGN-I M. Kotzalas S. LaVie E. Throm S. Weerakkody M. OBrien J. Hannon A. Notafrancesco C:\ORPCheckout\FileNET\ML030090622.wpd Accession No.: ML030090622 OFFICE PM:PDI-1 LA:PDI-2 SC:SPLB SC:PDI-1 NAME DCollins MOBrien SWeerakkody R. Laufer DATE 01/02/03 01/02/03 01/03/03 01/08/03 Official Record Copy
Beaver Valley Power Station, Units 1 and 2 Mary OReilly, Attorney FirstEnergy Nuclear Operating Company Rich Janati, Chief FirstEnergy Corporation Division of Nuclear Safety 76 South Main Street Bureau of Radiation Protection Akron, OH 44308 Deparment of Environmental Protection Rachel Carson State Office Building FirstEnergy Nuclear Operating Company P.O. Box 8469 Regulatory Affairs/Performance Harrisburg, PA 17105-8469 Improvement Larry R. Freeland, Manager Mayor of the Borough of Beaver Valley Power Station Shippingport Post Office Box 4, BV-A P O Box 3 Shippingport, PA 15077 Shippingport, PA 15077 Commissioner James R. Lewis Regional Administrator, Region I West Virginia Division of Labor U.S. Nuclear Regulatory Commission 749-B, Building No. 6 475 Allendale Road Capitol Complex King of Prussia, PA 19406 Charleston, WV 25305 Resident Inspector Director, Utilities Department U.S. Nuclear Regulatory Commission Public Utilities Commission Post Office Box 298 180 East Broad Street Shippingport, PA 15077 Columbus, OH 43266-0573 FirstEnergy Nuclear Operating Company Director, Pennsylvania Emergency Beaver Valley Power Station Management Agency ATTN: M. P. Pearson, Director 2605 Interstate Dr. Services and Projects (BV-IPAB)
Harrisburg, PA 17110-9364 Post Office Box 4 Shippingport, PA 15077 Ohio EPA-DERR ATTN: Zack A. Clayton FirstEnergy Nuclear Operating Company Post Office Box 1049 Beaver Valley Power Station Columbus, OH 43266-0149 Mr. B. F. Sepelak Post Office Box 4, BV-A Dr. Judith Johnsrud Shippingport, PA 15077 National Energy Committee Sierra Club Mr. Mark B. Bezilla 433 Orlando Avenue Vice President State College, PA 16803 FirstEnergy Nuclear Operating Company Beaver Valley Power Station J. H. Lash, Plant Manager (BV-IPAB) Post Office Box 4 FirstEnergy Nuclear Operating Company Shippingport, PA 15077 Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077
MEETING ATTENDEES FIRSTENERGY NUCLEAR OPERATING COMPANY BEAVER VALLEY POWER STATION, UNITS 1 AND 2 DECEMBER 11, 2002
Participants:
Name Organization D. Collins NRC/NRR/Division of Licensing Project Management R. Lobel NRC/NRR/Division of Systems Safety and Analysis E. Throm NRC/NRR/Division of Systems Safety and Analysis S. LaVie NRC/NRR/Division of Systems Safety and Analysis A. Notafrancesco NRC/RES/Division of Systems Analysis and Regulatory Effectiveness J. Tills NRC Contractor B. Sepelak FirstEnergy Nuclear Operating Company S. Sarver FirstEnergy Nuclear Operating Company M. Testa FirstEnergy Nuclear Operating Company K. Frederick FirstEnergy Nuclear Operating Company F. Twogood FirstEnergy Nuclear Operating Company J. DeBlasio Westinghouse Electric Company L. Smith Westinghouse Electric Company B. Henry Fauske & Associates, Inc.
B. Hammersley Fauske & Associates, Inc.
C. Paik Fauske & Associates, Inc.
D. Graves Stone & Webster Enclosure 1