G20020655 - Marvin S. Fertel Ltr Re New Reactor Licensing Issues -- Plant Parameters Envelope for Early Site Permits
ML023250052
Person / Time
Site: Nuclear Energy Institute
Issue date: 12/10/2002
From: Lyons J
NRC/NRR/NRLPO
To: Fertel M
Nuclear Energy Institute
Jenkins R, NRR/NRLPO 415-2985
Shared Package
ML023250035 List:
References
G20020655
Download: ML023250052 (5)


Text

December 10, 2002 Mr. Marvin S. Fertel Nuclear Energy Institute (NEI) 1776 I Street, NW, Suite 400 Washington, DC 20006-3708

SUBJECT:

Early Site Permit Issues

Dear Mr. Fertel:

The purpose of this letter is to acknowledge receipt of your letter to Mr. William F. Kane dated November 14, 2002, regarding the Nuclear Energy Institutes (NEIs) views on issues related to the early site permit (ESP) applications to be filed in 2003. The U.S. Nuclear Regulatory Commission (NRC) has always been receptive to the use of alternative approaches to meet regulatory requirements so we look forward to continuing our working-level discussions on the practical implementation of the plant parameter envelope (PPE) approach and other related issues. In order to achieve a set of common understandings and expectations by the February 1, 2003, deadline cited in your letter regarding the PPE approach (ESP-6 and ESP-7) and quality assurance (ESP-3) issues, the staff must receive the applicable White Papers which describe your position by December 20, 2002. You discussed the schedule for these papers in the public meeting on November 5, 2002. In addition, Mr. Ronaldo V. Jenkins, Project Manager for ESPs of my staff notified Mr. Russell Bell of your staff of additional questions on the PPE approach in the environmental area which we transmitted to you on November 26, 2002. We would request that the PPE White Paper address your response to the subject questions.

Please contact Mr. Jenkins at 301-415-2985 if you have any questions on this matter.

Sincerely,

/RA/

James E. Lyons, Director New Reactor Licensing Project Office Office of Nuclear Reactor Regulation Project No. 689

December 10, 2002 Mr. Marvin S. Fertel Nuclear Energy Institute (NEI) 1776 I Street, NW, Suite 400 Washington, DC 20006-3708

SUBJECT:

Early Site Permit Issues

Dear Mr. Fertel:

The purpose of this letter is to acknowledge receipt of your letter to Mr. William F. Kane dated November 14, 2002, regarding the Nuclear Energy Institutes (NEIs) views on issues related to the early site permit (ESP) applications to be filed in 2003. The U.S. Nuclear Regulatory Commission (NRC) has always been receptive to the use of alternative approaches to meet regulatory requirements so we look forward to continuing our working-level discussions on the practical implementation of the plant parameter envelope (PPE) approach and other related issues. In order to achieve a set of common understandings and expectations by the February 1, 2003, deadline cited in your letter regarding the PPE approach (ESP-6 and ESP-7) and quality assurance (ESP-3) issues, the staff must receive the applicable White Papers which describe your position by December 20, 2002. You discussed the schedule for these papers in the public meeting on November 5, 2002. In addition, Mr. Ronaldo V. Jenkins, Project Manager for ESPs of my staff notified Mr. Russell Bell of your staff of additional questions on the PPE approach in the environmental area which we transmitted to you on November 26, 2002. We would request that the PPE White Paper address your response to the subject questions.

Please contact Mr. Jenkins at 301-415-2985 if you have any questions on this matter.

Sincerely,

/RA/

James E. Lyons, Director New Reactor Licensing Project Office Office of Nuclear Reactor Regulation Project No. 689 Accession #ML023250052-Response Accession #ML023250035-Pkg.

OFC PM: NRLPO DD:NRLPO D:NRLPO NAME RJenkins MGamberoni JLyons DATE 12/2/02 12/3/02 12/3/02 OFFICIAL RECORD COPY

Distribution for G20020655 to M. Fertel dated December 10, 2002 Hard Copy JLyons RJenkins MGamberoni NRLPO Rdg.

WKane TBergman E-mail PUBLIC WTravers CPaperiello PNorry JCraig SBurns KCyr RidsNrrOD (SCollins/JJohnson)

RidsNrrAdip (RBorchardt)

RidsNrrAdpt (BSheron)

JLyons ACRS/ACNW OPA OCA NRR Mailroom (RidsNrrWpcMail - TJ Gorham #G20020655)

NRR/ADPT Secretary (K. Johnson)

RidsOgcRp

ESP-Generic cc:

Mr. David Lochbaum Union of Concerned Scientists 1707 H Street, NW Suite 600 Washington, DC 20006-3919 Mr. Paul Gunter Director of the Reactor Watchdog Project Nuclear Information & Resource Service 1424 16th Street, NW, Suite 404 Washington, DC 20036 Mr. Ron Simard Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Russell Bell Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Thomas P. Miller U.S. Department of Energy Headquarters - Germantown 19901 Germantown Road Germantown, MD 20874-1290 Mr. James Riccio Greenpeace 702 H Street, NW, Suite 300 Washington, DC 20001 Rod Krich Vice President, Licensing Projects Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Patricia Campbell Winston & Strawn 1400 L Street, NW Washington, DC 20005 Mr. Eddie Grant Exelon Generation 200 Exelon Way, KSA3-E Kennett Square, PA 19348 Mr. James F. Mallay, Director Regulatory Affairs FRAMATOME, ANP 3315 Old Forest Road Lynchburg, VA 24501 Mr. Ernie H. Kennedy Vice President New Plants Nuclear Plant Projects Westinghouse Electric Company 2000 Day Hill Road Windsor, CT 06095-0500 Dr. Regis A. Matzie Senior Vice President and Chief Technology Officer Westinghouse Electric Company 2000 Day Hill Road Windsor, CT 06095-0500 Mr. Gary Wright, Manager Office of Nuclear Facility Safety Illinois Department of Nuclear Safety 1035 Outer Park Drive Springfield, IL 62704 Mr. Vince Langman Licensing Manager Atomic Energy of Canada Limited 2251 Speakman Drive Mississauga, Ontario Canada L5K 1B2 Mr. David Ritter Research Associate on Nuclear Energy Public Citizens Critical Mass Energy and Environmental Program 215 Pennsylvania Avenue, SE Washington, DC 20003 Mr. Tom Clements 6703 Guide Avenue Takoma Park, MD 20912 Mr. Edwin Lyman Nuclear Control Institute 1000 Connecticut Avenue, NW Suite 410 Washington, DC 20036 Mr. Jack W. Roe SCIENTECH, INC.

910 Clopper Road Gaithersburg, MD 20878

Dr. Gail H. Marcus U.S. Department of Energy Room 5A-143 1000 Independence Ave., SW Washington, DC 20585 Ms. Marilyn Kray Vice President, Special Projects Exelon Generation 200 Exelon Way, KSA3-E Kennett Square, PA 19348 Mr. Joseph D. Hegner Lead Engineer - Licensing Dominion Generation Early Site Permitting Project 5000 Dominion Boulevard Glen Allen, VA 23060 Mr. George Alan Zinke Project Manager Nuclear Business Development Entergy Nuclear M-ECH-683 1340 Echelon Parkway Jackson, MS 39213 Mr. Charles Brinkman Westinghouse Electric Co.

Washington Operations 12300 Twinbrook Pkwy., Suite 330 Rockville, MD 20852 Mr. Ralph Beedle Senior Vice President and Chief Nuclear Officer Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Dr. Glenn R. George PA Consulting Group 130 Potter Street Haddonfield, NJ 08033 Arthur R. Woods Enercon Services, Inc.

500 TownPark Lane Kennesaw, GA 30144