|
---|
Category:Environmental Assessment
MONTHYEARML20150A3002020-11-23023 November 2020 Enclosure - Environmental Assessment Memo to File: Environmental Assessment and Finding of No Significant Impact for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf I ML20149K4522020-11-23023 November 2020 Encl: Environmental Assessment and Finding of No Significant Impact for Entergy Operations, Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One ISFSI) 0CAN101901, Request for Exemption from Requirements of 10 CFR 72.212(b)(3)2019-10-11011 October 2019 Request for Exemption from Requirements of 10 CFR 72.212(b)(3) ML1002215262010-03-12012 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Physical Security Requirements ML1002214942010-03-12012 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Physical Security Requirements ML0801706622008-03-0303 March 2008 Environmental Assessment and Finding of No Significant Impact, Related to Request for Exemption from 10 CFR 50.46 and 10 CFR Part 50, Appendix K, for Use of Optimized ZIRLO-TM Fuel Rod Cladding ML0517302682005-06-22022 June 2005 Environmental Assessment and Finding of No Significant Impact Related to Exemption from 10 CFR 50.46 and 10 CFR Part 50, Appendix K (Tac No. MC4612) ML0429503942005-04-0606 April 2005 Environmental Assessment and Finding of No Significant Impact Related to Exemption from Certain Requirements of 10 CFR Part 50, Appendix a (TAC No. Mc1228) ML0224900332002-09-0606 September 2002 Environmental Assessment, Makeup Pump Rooms ML0224102312002-08-28028 August 2002 Environmental Assessment, Definition of Total Effective Dose Equivalent ML0210906972002-04-19019 April 2002 Letter to C G Anderson ANO2-TAC. MB0789-EA and Finding of No Significant Impact Related to a Proposed License Samd to Increase the Licensed Power Level ML0207406592002-04-0202 April 2002 Environmental Assessment, Exemption from Requirements of 10 CFR Part 50, Appendix G ML0207203662002-03-13013 March 2002 Draft EA and Findings of No Significant Impact Related to a Proposed License Amendment to Increase the Licensed Power Level TAC MB0789 ML0203101512002-02-0404 February 2002 Draft Environmental Assessment, Proposed License Amendment to Increase the Max. Rated Thermal Power Level 2020-11-23
[Table view] Category:Finding of No Significant Impact
MONTHYEARML20149K4522020-11-23023 November 2020 Encl: Environmental Assessment and Finding of No Significant Impact for Entergy Operations, Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One ISFSI) ML1002215262010-03-12012 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Physical Security Requirements ML0517302682005-06-22022 June 2005 Environmental Assessment and Finding of No Significant Impact Related to Exemption from 10 CFR 50.46 and 10 CFR Part 50, Appendix K (Tac No. MC4612) ML0429503942005-04-0606 April 2005 Environmental Assessment and Finding of No Significant Impact Related to Exemption from Certain Requirements of 10 CFR Part 50, Appendix a (TAC No. Mc1228) ML0224900332002-09-0606 September 2002 Environmental Assessment, Makeup Pump Rooms ML0224102312002-08-28028 August 2002 Environmental Assessment, Definition of Total Effective Dose Equivalent ML0210906972002-04-19019 April 2002 Letter to C G Anderson ANO2-TAC. MB0789-EA and Finding of No Significant Impact Related to a Proposed License Samd to Increase the Licensed Power Level 2020-11-23
[Table view] Category:Letter
MONTHYEARIR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation 2024-09-09
[Table view] |
Text
September 6, 2002 Mr. Craig G. Anderson Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 - ENVIRONMENTAL ASSESSMENT FOR EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 50, SECTION III.G.2 OF APPENDIX R (TAC NO. MB2258)
Dear Mr. Anderson:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application dated June 8, 2001, for an exemption from 10 CFR Part 50, Appendix R for the makeup pump rooms. The proposed exemption would address the lack of one-hour rated fire barriers for auxiliary lube oil pumps and their associated conduits in the makeup pump rooms.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
William Reckley, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-313
Enclosure:
Environmental Assessment cc w/encl: See next page
September 6, 2002 Mr. Craig G. Anderson Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 - ENVIRONMENTAL ASSESSMENT FOR EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 50, SECTION III.G.2 OF APPENDIX R (TAC NO. MB2258)
Dear Mr. Anderson:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application dated June 8, 2001, for an exemption from 10 CFR Part 50, Appendix R for the makeup pump rooms. The proposed exemption would address the lack of one-hour rated fire barriers for auxiliary lube oil pumps and their associated conduits in the makeup pump rooms.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
William Reckley, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-313
Enclosure:
Environmental Assessment cc w/encl: See next page DISTRIBUTION:
PUBLIC DRIP/RLEP/ESSC (JTappert)
PDIV-1 Reading RidsOgcRp RidsNrrDlpmLpdiv (WRuland) RidsAcrsAcnwMail Center RidsNrrDlpmLpdiv1 (RGramm) K. Brockman, RIV RidsNrrPMWReckley RidsNrrLADJohnson Accession No.: ML022490033 *See previous concurrence OFFICE PDIV-1/PM DRIP/RLEP PDIV-1/LA OGC PDIV-1/SC NAME WReckley JTappert* DJohnson SHom* RGramm nlo w/changes DATE 9/5/02 08/30/02 9/5/02 09/03/02 9/6/02 OFFICIAL RECORD COPY
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION ENTERGY OPERATIONS, INC.
DOCKET NO. 50-313 ARKANSAS NUCLEAR ONE, UNIT 1 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (NRC) is considering issuance, to Entergy Operations, Inc. (the licensee), of an exemption from Title 10 of the Code of Federal Regulations (10 CFR) Part 50,Section III.G of Appendix R. The licensee is the holder of Renewed Facility Operating License No. DPR-51, for operation of Arkansas Nuclear One, Unit 1 (ANO-1), located in Pope County, Arkansas. Therefore, as required by 10 CFR 51.21, the NRC is issuing this environmental assessment and finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action would exempt the licensee from certain requirements of Section III.G of Appendix R, Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979. Specifically, this exemption applies to requirements for fire barriers for the auxiliary lube oil pump and associated conduits in the ANO-1 makeup pump rooms.
The proposed action is in accordance with the licensees application dated June 8, 2001.
The Need for the Proposed Action:
The proposed action is needed to resolve an issue involving the auxiliary lube oil pumps and associated conduits which are used during the starting of a reactor coolant makeup pump.
The licensee was granted an exemption on March 22, 1983, which exempted the makeup pump
rooms from the requirement to have an automatic fire suppression system. The equipment identified in the exemption as being needed for safe shutdown included the makeup pumps, the service water to lube oil cooler isolation valves, and associated cabling. The licensee subsequently classified the auxiliary lube oil pump (and associated conduits) as required for safe shutdown. Because the auxiliary lube oil pump was not addressed in the previous exemption, the licensee needed to either request a specific exemption or provide specific fire protection features for the auxiliary lube oil pump.
Environmental Impacts of the Proposed Action:
The NRC has completed its evaluation of the proposed action and concludes that the proposed exemption does not involve radioactive wastes, release of radioactive material into the atmosphere, solid radioactive waste, or liquid effluents released to the environment.
The proposed action will not significantly increase the probability or consequences of accidents, no changes are being made in the types or amounts of effluents that may be released off site, and there is no significant increase in occupational or public radiation exposure. Therefore, there are no significant radiological environmental impacts associated with the proposed action.
With regard to potential nonradiological impacts, the proposed action does not have a potential to affect any historic sites. It does not affect nonradiological plant effluents and has no other environmental impact. Therefore, there are no significant nonradiological environmental impacts associated with the proposed action.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the no-action alternative). Denial of the application would result in no change in
current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resource than those previously considered in the Final Environmental Statement related to the operation of ANO-1 (NUREG-0254) dated February 1973, and the Final Supplemental Environmental Impact Statement regarding ANO-1 (NUREG-1437, Supplement 3) dated April 2001.
Agencies and Persons Consulted:
On August 26, 2002, the staff consulted with the Arkansas State official, Jared Thompson, of the Arkansas Department of Health, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensees letter dated June 8, 2001. Documents may be examined, and/or copied for a fee, at the NRCs Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor),
Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 6th day of September 2002.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Robert A. Gramm, Chief, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation