September 10, 2002 Mr. C. Lance Terry Senior Vice President &
Principal Nuclear Officer TXU Energy Attn: Regulatory Affairs Department P. O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION, UNITS 1 AND 2 RE: BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE (TAC NOS. MB4537 AND MB4538)
On March 18, 2002, the staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements.Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized water reactor (PWR) plants. All addressees were requested to respond to Items 1.A. through E. within 15 days of the Bulletins issuance, or to provide a written response to the U.S. Nuclear Regulatory Commission (NRC) in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they can not meet the requested completion dates.
You provided your 15-day Bulletin response by letter dated April 2, 2002. The staff finds that you have provided the requested information and has concluded that your plant does not appear to have conditions similar to those which lead to the type of degradation observed at Davis-Besse. However, the staff may issue questions to confirm or verify the information that was provided in your 15-day response to Bulletin 2002-01.
We will complete a full review of your response to Bulletin 2002-01, after we review your response to Items 2 and 3 of the Bulletin.
Sincerely,
/RA/
David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page We will complete a full review of your response to Bulletin 2002-01, after we review your response to Items 2 and 3 of the Bulletin.
Sincerely,
/RA/
David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page DISTRIBUTION:
PUBLIC RidsNrrDlpmLpdiv1 (RGramm)
RidsOgcRp PDIV-1 RF RidsNrrDeEmcb (WBateman)
RidsNrrPMDJaffe EMCB R/F RidsAcrsAcnwMailCenter ALee SBloom RidsRgn4Mail Center (KBrockman) SCoffin ACCESSION NO. ML022560120 OFFICE PDIV-1/PM PDIV-1/LA EMCB PDIV-1/SC NAME DJaffe DJohnson SBloom RGramm DATE 9/9/02 9/5/02 9/9/02 9/10/02 OFFICIAL RECORD COPY
August 2002 Comanche Peak Steam Electric Station cc:
Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 2159 Glen Rose, TX 76403-2159 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Mr. Roger D. Walker Regulatory Affairs Manager TXU Generation Company LP P. O. Box 1002 Glen Rose, TX 76043 George L. Edgar, Esq.
Morgan, Lewis & Bockius 1800 M Street, N.W.
Washington, DC 20036-5869 County Judge P. O. Box 851 Glen Rose, TX 76043 Environmental and Natural Resources Policy Director Office of the Governor P. O. Box 12428 Austin, TX 78711 Mr. Richard A. Ratliff, Chief Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 Mr. Brian Almon Public Utility Commission William B. Travis Building P. O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Mr. Wade Wheatley, Director Waste Permits Division Texas Natural Resource Conservation Commission P. O. Box 13087 (MS 126)
Austin, TX 78711-3087