August 26, 2002 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)
ATTN: Supervisor, Licensing &
Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
CRYSTAL RIVER UNIT 3
Dear Mr. Young:
On August 5, 2002, the NRC staff completed its mid-cycle plant performance assessment of Crystal River Unit 3. In accordance with NRC Inspection Manual Chapter 0305 Operating Reactor Assessment Program, the mid-cycle review involved the participation of all technical divisions in evaluating the performance of your Crystal River facility for the first half of the current assessment cycle, January 1 - December 31, 2002. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections which may conflict with your plant activities.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only baseline inspections at your facility through September 30, 2003.
The enclosed inspection plan details the inspections scheduled through September 30, 2003.
The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The last six months of the inspection plan is tentative and may be revised at the end-of-cycle review.
In addition, the NRC is in the process of finalizing a Temporary Instruction that will be used to review implementation of the Interim Compensatory Measures required by the Agencys Security Order to all commercial nuclear power plants dated February 25, 2002. Schedules have not yet been finalized, but it is anticipated that these inspections will begin within the next calendar quarter. Once finalized, the details will be communicated by separate correspondence.
FPC 2
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4540 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
//RA//
Leonard D. Wert, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 50-302 License No. DPR-72
Enclosure:
Crystal River Inspection/Activity Plan cc w/encl:
Daniel L. Roderick Director Site Operations Crystal River Nuclear Plant (NA2C)
Electronic Mail Distribution Jon A. Franke Plant General Manager Crystal River Nuclear Plant (NA2C)
Electronic Mail Distribution Richard L. Warden Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C)
Electronic Mail Distribution R. Alexander Glenn Associate General Counsel (MAC - BT15A)
Florida Power Corporation Electronic Mail Distribution (cc w/encl cont'd - See page 3)
FPC 3
Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304 William A. Passetti Bureau of Radiation Control Department of Health Electronic Mail Distribution Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs Electronic Mail Distribution Chairman Board of County Commissioners Citrus County 110 N. Apopka Avenue Inverness, FL 36250 Michael A. Schoppman Framatome Technologies Electronic Mail Distribution
FPC 4
Distribution w/encl:
B. Mozafari, NRR RIDSNRRDIPMLIPB PUBLIC OFFICE RII:DRP SIGNATURE SON NAME SNinh DATE 8/26/2002 E-MAIL COPY?
YES PUBLIC DOCUMENT YES OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML022390650.wpd