ML021970063
| ML021970063 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 04/29/2002 |
| From: | Nuclear Management Co |
| To: | Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML021970045 | List: |
| References | |
| Download: ML021970063 (55) | |
Text
Point Beach Nuclear Plant Potential Common Mode Failure Auxiliary Feedwater April 29, 2002
2 AGENDA
Introduction (Mark Warner)
System Design (Lori Armstrong)
Risk Assessment (Jim Masterlark)
Root Cause & Corrective Actions (Fred Cayia)
Inspection Report Opportunities (Lori Armstrong)
Operations Perspective (Jerry Strharsky)
Reactor Oversight Process (Tom Webb)
Conclusion (Mark Warner)
3 AFW SYSTEM DESIGN Lori Armstrong
4 AFW DESIGN BASIS
Supply water to SG to remove decay heat and replenish SG inventory
Safety-Related Functions:
Supply FW during accidents with main steam safety valve opening
Supply FW during accidents which require rapid RCS cooldown
Isolation capability
6 RISK ASSESSMENT Jim Masterlark
7 ORIGINAL IPE ANALYSIS
Used System Functional Method
- Failure modes based on design basis information
- Focused on need to feed steam generators
- Modeled open failure mode of recirc valve
- Accepted industry method
Operator actions were evaluated where they could be credited to mitigate a failure
8 ORIGINAL IPE ANALYSIS
Original IPE identified failure mode of recirc valve in the closed position
- Pump overheating potential outcome
- Discharge valve would only be throttled for decay heat removal - occurs late in event
- Recirc valve failure mode not modeled
- The PRA did not model that the flow could be stopped early in the event o Overfilling steam generators o Overcooling RCS
9 PRA UPDATE PROJECT
Self initiated voluntary project
Ongoing formal evaluation of PRA model
Most risk significant systems evaluated first
Revalidates model assumptions
Four primary reasons for update
Validates changes in plant since original PRA model
Adds sophistication for better use of on line Safety Monitor
Update reliability and availability data
Expand Human Reliability Analysis
10 PRA UPDATE PROJECT
Use of Failure Modes and Effects Analysis
Determines possible failure modes
Rigorous evaluation for each component
- Capture failure mode in fault tree, or
- Document reason that it is not included
Analyze to determine effect of failure modes on system operation
Determination of how component could get to each position analyzed
- Equipment failure
- Operator action
- Support system failure
11 FMEA
FMEA for AFW System
Failure effects of Recirculation Valve
- Open position - flow diversion
- Closed position - potential for maloperation of pump
Human Error Analysis and Timeline Analysis
- Identified that discharge valve could be closed prior to gagging open recirculation valve
12 FMEA
Summary
The identification of this issue required the combination of a failure modes and effects analysis with time line studies from a Human Error Analysis
This combination of analyses is unique to the PRA
13 ROOT CAUSE, CORRECTIVE ACTION, and EXTENT of CONDITION Fred Cayia
14 PROBLEM STATEMENT
EOP-0.1, Reactor Trip Response, did not contain the specific operator actions needed to :
Assure in all instances operators consistently control or stop AFW flow to prevent AFW pump damage under certain conditions
- Those conditions are loss of instrument air coincident with steam generator overfill or RCS overcooling
15 IMMEDIATE CORRECTIVE ACTIONS
Immediate Actions
Information tags placed
Shifts briefed and trained on issue
Simulator training for each crew
Procedure changes
Notification made to NRC
Root Cause Evaluation initiated
- Multidiscipline RCE Team
16 ROOT CAUSE
EOP validation process did not evaluate the interaction between:
Design
Procedure
Human Error Timeline Analysis
Typical industry approaches have not included Human Error Timeline Analysis
17 COMPLETED ACTIONS
Procedure Changes
Design Modifications to Recirculation Valve
Pneumatic backup
EOP validation process has changed to incorporate PRA into the validation
Simulator changed to model AFW pumps during response to low flow conditions
18 EXTENT OF CONDITION
Previously evaluated four top risk significant systems
EOP steps evaluated to ensure successful implementation on a loss of instrument air
Reviewed PRA assumptions for operator actions on the next two risk-significant systems
Systems reviewed comprise 80% of CDF risk
19 OTHER ISSUES IDENTIFIED
Design Basis fire causes failure of AFW pumps
Compensatory fire rounds initiated
Nitrogen back-up to charging pumps undersized for Appendix R event
Compensatory fire rounds initiated
Potential to identify additional improvements
20 CONTINUING ACTIONS
Continue the PRA project
Factor PRA insights into
Operating Procedures
Operator training
21 INSPECTION REPORTS OPPORTUNITIES Lori Armstrong
22 INSPECTION REPORT OPPORTUNITIES
Examples Listed by NRC
1989 station blackout (SBO) submittal
GL 88-20 (IPE submittal - 1993)
1997 AFW N2 backup modification
23 ISSUE IDENTIFICATION
Three elements need to be evaluated concurrently to identify this issue
Design
Procedural Guidance
FMEA Timeline Study
24 GL 81-14 (1981)
GL 81-14 Requirement
Determine extent of AFWS seismic qualification
PBNP Action
Performed reviews and walk-downs
Completed NRC Bulletin 79-14 AFW modifications
Installed AFW recirc valve supports
25 GL 81-14 KEY ELEMENTS
SUMMARY
Design Review
Reviewed seismic adequacy of foundations, supports, and structures.
Ensured system would remain functional following a seismic event
Procedures
Review of system operating procedures was not an expected response to the GL
Therefore, this very specific design review would not identify the time dependent procedural vulnerability
26 GL 88-14 (1988)
GL 88-14 Requirement
Review of instrument air system
- Emergency procedures and training
- Air operated safety-related components
PBNP Action
Verified loss of IA procedure acceptable
Periodic training provided
Concluded IA not required for component/
system safety-related functions
27 GL 88-14 KEY ELEMENTS
SUMMARY
Design
Verified performance of safety-related functions with loss of IA
Verified AFW recirc valves must fail close to assure AFW safety-related function
Procedures
Verified that adequate procedures existed to address a loss of instrument air (gagging open recirc valve)
FMEA Timeline
PRA techniques not available
Lacking the Human Error Timeline Analysis tool, it was not expected to identify this issue
28 SBO RULE (1989)
10 CFR 50.63 requirement
Withstand a station blackout of a specified duration
PBNP Action
No AOVs are required to operate for one hour to cope with a SBO
AFWS operation is independent of AC and IA for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
Only turbine driven AFW pumps available
SBO Emergency Response Procedures
29 SBO RULE KEY ELEMENTS
SUMMARY
Design
Verified units could withstand SBO
Prescriptive assumptions defined course of the event to demonstrate compliance with the rule
- High initial decay heat (100% power for 100 days)
- No additional independent failures
- All equipment operating or available and IA restored within one hour
Based upon high decay heat load, not credible to stop flow in first hour
30 IPE SUBMITTAL (1993)
GL 88-20 Requirement
Directed licensees to submit a program/schedule for completing an IPE
PBNP Action
Performed an IPE using accepted industry method
31 IPE SUBMITTAL KEY ELEMENTS
SUMMARY
Design
IPE uses system functional method
Pump overheating potential outcome
Procedures
Verified recirc valves gagged open on loss of instrument air
FMEA Timeline Analysis
Operator actions only modeled for mitigation of failure
Accepted industry method did not use FMEA Timeline Analysis
Based on the method used this was not a missed opportunity
NRC Inspection Report stated
DBD-01 stated recirc valve had safety-related open function
Open function not reconciled with fail closed safety function on loss of instrument air
The DBD is an engineering tool and does not provide an operational perspective.
SUMMARY
Design
DBD is an Engineering tool that contains the limits of designs and the reasons for these limits
Confirmed that the design basis requirements were adequately contained in the procedures
Performed a single failure evaluation to disposition conflict
- Result was a closed safety function for the recirc valve
Not expected to assume the design basis approach would find the time dependent procedure vulnerability
34 AFW N2 MODIFICATION (1997)
Inspection Report
Concern was not evaluating other air operated valves in the AFW system on a loss of IA, as part of this modification
Modification Purpose
35 AFW N2 MODIFICATION KEY ELEMENTS
SUMMARY
Design
Modification identified that recirc valve failed closed on loss of IA
Credited forward flow for pump protection
Subsequent PRA update incorporated modification to discharge valves
Procedures
Reviewed for impact of design changes
Therefore this design review was not a missed opportunity
36 IST-DBD ISSUE (1997)
IST-DBD discrepancy identified via a condition report:
No open function testing of the AFW recirc line check valves
AFW recirc AOVs were open function tested in the IST program
DBD listed an open safety function for AFW recirc valves to prevent pump damage
37 IST-DBD ISSUE KEY ELEMENTS
SUMMARY
IST Program periodically confirms the safety related functions of components
Discrepancy resolution based on 1994 DBD evaluation
Result was a closed safety function for recirc valves and no open safety function
Revised DBD
This design review would not find the time dependent procedure vulnerability
EVALUATION OF PRIOR OPPORTUNITIES N/A N/A Yes IST-DBD Issue (1997)
N/A N/A Yes AFW N2 Backup Mod (1997)
N/A Yes Yes GL 88-20 (1993) IPE Submittal N/A Yes Yes SBO Rule (1989)
N/A Yes Yes GL 88-14 (1988) Loss of IA N/A N/A Yes GL 81-14 (1981) AFW Seismic FMEA Timeline Procedures Design Potential Missed Opportunities
39 CONCLUSIONS
AFW system design was acceptable
Loss of Instrument Air procedure correctly identified recirc valve failure mode and manual actions for gagging open valve
FMEA Timeline Analysis was required to identify the vulnerability in the EOP
40 OPERATIONS PERSPECTIVE Jerry Strharsky
41 OPERATOR TRAINING
PRA based
Recognized industry strength
AFW system and loss of IA transients previously identified as training significant
Frequent training on AFW and loss of IA transients
Minimum flow requirements well known
42 DEMONSTRATED OPERATOR PERFORMANCE
1989 Loss of IA
Occurred during Unit 2 trip
Operators responded properly
Operating unit transient avoided
1998 AFW Pump Recirc Valve Found Failed Shut
Operator starting an AFW pump observed that recirculation valve did not open
Immediately secured the pump
43 OPERATIONS
SUMMARY
Operator risk based training combined with the technical elements of component and system, operation and design, ensured our operators had the knowledge to properly diagnosis and respond to this condition
Previous operator performance has demonstrated that appropriate actions are taken in response to events with similar concerns
Confident in our operating crews ability to diagnose and respond to events of this complexity and significance
44 REACTOR OVERSIGHT PROCESS Tom Webb
45 REACTOR OVERSIGHT PROCESS
The probabilistic risk assessment:
used realistic assumptions for equipment failure
used accepted assumptions for human performance
vulnerability had high safety significance
Conclusion:
Further regulatory action is not warranted
46 REACTOR OVERSIGHT PROCESS
Old Design Issue Treatment (IMC 0305)
Licensee identified as a result of a voluntary initiative
Was or will be corrected
Not likely to be identified by routine licensee efforts
Does not reflect a current performance deficiency
47 IMC 0305
Old Design Issue: A finding involving a past problem in the engineering calculations or analysis, associated operating procedure, or installation of plant equipment that does not reflect a performance deficiency associated with existing licensee programs, policy, or procedure.
As discussed in section 06.06.a, some old design issues may not be considered in the assessment program. (emphasis added)
48 IMC 0305
Criterion 1: Licensee identified as a result of a voluntary initiative.
PRA model update initiative
Planned, formal process
Systematic and broad-scope
Documented
Continued integration of PRA
Conclusion:
This Criterion has been met
49 IMC 0305
Criterion 2: Was or will be Corrected
Procedure changes
Additional Reviews of EOPs and PRA
System design modifications
PRA Upgrade
Conclusion:
This Criterion has been met
50 IMC 0305
Criterion 3: Not Likely to be Identified by Routine Licensee efforts
Normal surveillance and QA could not identify
Not readily discernable by traditional engineering approaches
Conclusion:
This Criterion has been met
51 IMC 0305
Criterion 4: Does not Reflect a Current Performance Deficiency
PRA has and continues to validate the EOPs
Corrective action process has been restructured
New operating company and management personnel
NMC is embedding a culture which aggressively identifies and resolves issues
Potential Prior Opportunities 5 to 21 years old
- Activities beyond 2 years ago do not reflect accurately on current PBNP processes and performance
Conclusion:
This Criterion has been met
52 IMC 0305
Summary
Point Beach meets the four IMC criteria
NRC has already performed the appropriate supplemental inspection
IMC 0305 states that, the regional offices may take credit for previous inspection efforts in completing the requirements of the procedure.
Conclusion
The NRC has completed all the required inspection of IMC 0305
The finding should not be aggregated into the action matrix
53 PROPOSED VIOLATIONS
10CFR Part 50 Appendix B, Criterion V:
Because the procedures did not include instructions to ensure the recirculation valves were open, the AFW pumps could be damaged under low flow conditions such as when the flow is throttled back to control steam generator level or to mitigate RCS over cooling. This issue is considered an apparent violation.
NMC does not contest this proposed violation
54 PROPOSED VIOLATIONS
10 CFR Part 50; Appendix B Criterion XVI
On seven occasions between 1981 and 1997, the licensee was made aware of the susceptibility of the AFW system to this type of vulnerability, but the licensee failed to identify this significant condition adverse to quality.
This issue is considered an apparent violation
NMC believes that this proposed violation should be withdrawn
55 CONCLUSION Mark Warner
56 Notes: