MONTHYEARML0212604292002-05-0202 May 2002 G20020271/LTR-02-0324 - Sen. Arlen Specter Ltr Re New Gas-Fired Power Plant Proposed by Florida Power and Light Directly Adjacent to Existing Exelon Nuclear Facility Project stage: Other ML0213404572002-05-22022 May 2002 G20020271/LTR-02-0324 - Response to Thomas Dibello Ltr New Gas-Fired Power Plant Proposed by Florida Power and Light Directly Adjacent to Existing Exelon Nuclear Facility Project stage: Other ML0213601862002-05-24024 May 2002 G20020271/LTR-02-0324 - Response to John Skolds Ltr - RAI Regarding the Impact of the Construction of the Linfield Energy Center Power Plant on the Safe Operation of the Limerick Generating Station. (MB4990 and MB4991) Project stage: RAI ML0216105442002-07-26026 July 2002 Response to 05/02/2002 Ltr. Gas-Fired Power Plant Proposed by Florida Power & Light Directly Adjacent to Existing Exelon Nuclear Facility Project stage: Other 2002-05-22
[Table View] |
|
---|
Category:Letter
MONTHYEARML24151A3842024-10-31031 October 2024 – Issuance of Amendment Nos. 264 and 226 Support to Digital Modernization Project Installation (EPID L-2023-LLA-0025) and Exemption from the Requirements of 10 CFR 50.62 ML24303A0902024-10-29029 October 2024 Operator Licensing Examination Approval ML24303A2782024-10-29029 October 2024 10 CFR 50.46 Annual Report ML24299A2642024-10-25025 October 2024 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications IR 05000352/20240122024-10-17017 October 2024 Commercial Grade Dedication Inspection Report 05000352/2024012 and 05000353/2024012 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24274A2372024-10-0707 October 2024 – Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications ML24278A3022024-10-0404 October 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10 CFR 50.62 ATWS Rule to Support the Digital Modernization Project Installation - Rev Unit 2 Technical Spec ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A0032024-09-27027 September 2024 Generation Station, Units 1 and 2 – Regulatory Audit Plan Supporting Review of the Component Interface Module System of the Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) (Redacted) ML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24215A4042024-09-18018 September 2024 Request for Withholding Information from Public Disclosure IR 05000352/20244202024-09-16016 September 2024 – Security Baseline Inspection Report 05000352/2024420 and 05000353/2024420 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds IR 05000352/20250102024-09-10010 September 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000352/2025010 and 05000353/2025010 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000352/20240052024-08-29029 August 2024 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2024005 and 05000353/2024005) ML24241A1952024-08-28028 August 2024 License Amendment Request for Modification to Technical Specification 3.6.1.2 and Main Steam Isolation Valve Leakage Rate Requirements ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24163A3902024-08-14014 August 2024 Request for Withholding Information from Public Disclosure ML24220A2392024-08-12012 August 2024 Correction to Technical Specification Page 3/4 3-11 in Amendment No. 225 IR 05000352/20240022024-08-12012 August 2024 Integrated Inspection Report 05000352/2024002 and 05000353/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24204A0712024-07-29029 July 2024 Issuance of Amendment Nos. 263 and 225 Technical Specifications for Main Steam Line Tunnel Temperature ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24208A1592024-07-25025 July 2024 Regulatory Audit Plan Supporting Review of the System Development Portion of Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) - Non-Proprietary ML24201A1662024-07-19019 July 2024 Response to Request for Additional Information for License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam L ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24170A7702024-06-20020 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing(Epid L-2024-LLA-0079) LTR 05000352/LER-2024-003, Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK1232024-06-18018 June 2024 Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK123 ML24166A1142024-06-14014 June 2024 Response to Requests for Additional Information (RAIs 15 Through 23) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24165A2642024-06-13013 June 2024 License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam Line Tunnel Temperature TS 3/4.7.9 05000352/LER-2024-002, Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker2024-06-10010 June 2024 Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker ML24151A2882024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24151A2012024-06-10010 June 2024 Request for Withholding Information from Public Disclosure 05000352/LER-2024-001, Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit2024-06-10010 June 2024 Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit ML24150A0242024-05-29029 May 2024 Notification of Commercial Grade Dedication Inspection (05000352/2024012 and 05000353/2024012) and Request for Information ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000352/20243022024-05-20020 May 2024 Revised Initial Operator Licensing Examination Report 05000352/2024302 and 05000353/2024302 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000352/20240012024-05-0707 May 2024 Integrated Inspection Report 05000352/2024001 and 05000353/2024001 ML24124A0432024-05-0303 May 2024 Response to Requests for Additional Information (RAIs 9 Through 14) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24114A3222024-04-23023 April 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) - Pivot to Unit ML24109A0702024-04-18018 April 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFRC50.52 ATWS Rule to Support the Digital Modernization Project Installation . 2024-09-06
[Table view] |
Text
May 24, 2002 Mr. John L. Skolds, President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 200 Exelon Way, KSA 3-E Kennett Square, PA 19348
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REGARDING THE IMPACT OF THE CONSTRUCTION OF THE LINFIELD ENERGY CENTER POWER PLANT ON THE SAFE OPERATION OF THE LIMERICK GENERATING STATION (MB4990 AND MB4991)
Dear Mr. Skolds:
You may be aware that FPL Energy (FPLE) is planning to construct a 550-megawatt, gas-fired power plant, the Linfield Energy Center, at a location adjacent to Exelon Generation Companys (Exelon) Limerick Generating Station (LGS), Units 1 and 2. The staff has been monitoring the potential construction of the Linfield Energy Center for some time. While the Linfield Energy Center is not within the regulatory authority of the Nuclear Regulatory Commission (NRC), the construction and operation of the facility may have potential safety implications for LGS. It appears that the original design of LGS Units 1 and 2 did not consider a facility like the Linfield Energy Center within close proximity to LGS.
In Title 10 of the Code of Federal Regulations, Section 100.10, the Commission specifies factors to be considered when evaluating sites for nuclear facilities. It states that reactors are expected to have an extremely low probability for accidents that could result in the release of significant quantities of radioactive fission products, and that, should an accident occur, the reactor facility should ensure a low risk of public exposure. NRC staff guidance on the identification of potential hazards in the vicinity of the site is described in NUREG-800, Standard Review Plan [SRP] for the Review of Safety Analysis Reports for Nuclear Power Plants, SRP No. 2.2.1 - 2.2.2. NRC staff guidance on the evaluation of potential hazards is described in SRP No. 2.2.3 of NUREG-0800. Section 2.2.3 of the LGS Units 1 and 2 Updated Final Safety Analysis Report (UFSAR) describes Exelons evaluation of potential accidents in nearby transportation and industrial facilities, some of which were used to determine the design of LGS Units 1 and 2. The previous licensee, PECO Energy Company, completed this evaluation during initial plant licensing and did not consider an industrial facility the size or in the location of what is being planned by FPLE.
The construction and operation of a gas-fired power plant within close proximity to LGS has the potential to adversely affect the analyses described in Section 2.2.3 of the LGS Units 1 and 2 UFSAR. As a result, the NRC requests that you assess the impact of construction and operation of the proposed power plant on LGS Units 1 and 2. If your assessment determines that the impact adversely affects the analyses currently described in the UFSAR, please update the LGS Units 1 and 2 UFSAR and other related documents. As part of your assessment and response, the NRC staff specifically requests that you address those issues identified by Mr. Thomas DiBello, Chairman, Board of Supervisors, Limerick Township, that are documented
J. Skolds in the attachment to the enclosed letter to Chairman Meserve from Senator Specter dated May 2, 2002, as they relate to the proposed Linfield Energy Center project and its impact on the safe operation of LGS.
Several issues identified by the Limerick Township regarding the proposed power plant need not be addressed in your response to us. These issues are: violation of Township ordinances; unspecified concerns by the Montgomery County Planning Commission; deficiencies in the Pennsylvania Department of Environmental Protection air quality permit review process; conflicts with certain qualifying criteria, such as noise levels and local growth management policies; and, Township concerns about the construction of the Linfield Energy Center creating a potential threat to homeland security.
As we discussed with your staff by telephone on May 14, 2002, we understand that you will be able to provide your response to this request within 30 days of the receipt of this letter. If you have any questions regarding this matter, please contact me at 301-415-1055.
Sincerely,
/RA/
Christopher Gratton, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
Ltr to Chairman Meserve from Senator Specter dated May 2, 2002, with attached letter to Senator Specter from T. DiBello dated April 30, 2002 cc w/encl: See next page
J. Skolds in the attachment to the enclosed letter to Chairman Meserve from Senator Specter dated May 2, 2002, as they relate to the proposed Linfield Energy Center project and its impact on the safe operation of LGS.
Several issues identified by the Limerick Township regarding the proposed power plant need not be addressed in your response to us. These issues are: violation of Township ordinances; unspecified concerns by the Montgomery County Planning Commission; deficiencies in the Pennsylvania Department of Environmental Protection air quality permit review process; conflicts with certain qualifying criteria, such as noise levels and local growth management policies; and, Township concerns about the construction of the Linfield Energy Center creating a potential threat to homeland security.
As we discussed with your staff by telephone on May 14, 2002, we understand that you will be able to provide your response to this request within 30 days of the receipt of this letter. If you have any questions regarding this matter, please contact me at 301-415-1055.
Sincerely,
/RA/
Christopher Gratton, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
Ltr to Chairman Meserve from Senator Specter dated May 2, 2002, with attached letter to Senator Specter from T. DiBello dated April 30, 2002 cc w/encl: See next page DISTRIBUTION:
PUBLIC OGC PDI-2 R/F OCA OPA W Travers J Craig C Paperiello P Norry J Zwolinski W Borchardt W Kane S Collins/J Johnson B Sheron/K Johnson C. Gratton S. Richards J. Clifford B. Platchek, RI M. OBrien G Imbro M Shanbaky L Cox J Davis, NSIR R Zimmerman, NSIR H Miller, RI Burns/Cyr T. Gorham (EDO #G20020271)
SECY (SECY # LTR-02-0324) *See previous concurrence Accession Number: ML021360186 Package Number: ML021360225 Incoming Number: ML021260429 OFFICE PM:PDI-2 LA:PDI-1 BC:EMEB
- BC: R1 B4 OGC SC:PDI-1 D: PD1 NAME CGratton MOBrien G Imbro M Shanbaky RHoefling J Clifford S Richards DATE 5/21/02 5/21/02 5/21/02 5/21/02 5/23/02 5/23/02 5/24/02 Official Record Copy
Limerick Generating Station, Units 1 & 2 cc:
Vice President, General Counsel and Secretary Library Exelon Generation Company, LLC U.S. Nuclear Regulatory Commission 300 Exelon Way Region I Kennett Square, PA 19348 475 Allendale Road King of Prussia, PA 19406 Manager Licensing-Limerick and Peach Bottom Exelon Generation Company, LLC Dr. Judith Johnsrud Nuclear Group Headquarters National Energy Committee Correspondence Control Sierra Club P.O. Box 160 433 Orlando Avenue Kennett Square, PA 19348 State College, PA 16803 Site Vice President Vice President, Licensing and Regulatory Affairs Limerick Generating Station Exelon Generation Company, LLC Exelon Generation Company, LLC 4300 Winfield Road P.O. Box 2300 Warrenville, IL 60555 Sanatoga, PA 19464 Director-Licensing Plant Manager Mid-Atlantic Regional Operating Group Limerick Generating Station Exelon Generation Company, LLC Exelon Generation Company, LLC Nuclear Group Headquarters P.O. Box 2300 Correspondence Control Sanatoga, PA 19464 P. O. Box 160 Kennett Square, PA 19348 Regional Administrator, Region I U.S. Nuclear Regulatory Commission Correspondence Control Desk 475 Allendale Road Exelon Generation Company, LLC King of Prussia, PA 19406 200 Exelon Way, KSA 1-N-1 Kennett Square, PA 19348 Senior Resident Inspector U.S. Nuclear Regulatory Commission Chief Operating Officer Limerick Generating Station Exelon Generation Company, LLC P.O. Box 596 4300 Winfield Road Pottstown, PA 19464 Warrenville, IL 60555 Chairman Senior Vice President, Nuclear Services Board of Supervisors Exelon Generation Company, LLC of Limerick Township 4300 Winfield Road 646 West Ridge Pike Warrenville, IL 60555 Linfield, PA 19468 Chief-Division of Nuclear Safety PA Dept. of Environmental Resources P.O. Box 8469 Harrisburg, PA 17105-8469
Limerick Generating Station, Units 1 & 2 cc:
Vice President, Mid-Atlantic Operations Support Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Senior Vice President Mid-Atlantic Regional Operating Group Exelon Generation Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Regulatory Assurance Manager Limerick Generating Station Exelon Generation Company, LLC P.O. Box 2300 Sanatoga, PA 19464 The Honorable Arlen Specter ATTN: Mr. Tom Dower United States Senate Washington, DC 20510-3802