April 4, 2002 Mr. John T. Conway Site Vice President Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED AMENDMENT OF TECHNICAL SPECIFICATION, SECTION 6.0 (TAC NO. MB2441)
Dear Mr. Conway:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing the subject proposed amendment, requested by your letter dated October 26, 2001. On March 28, 2002, we discussed by telephone with Mr. D. Vandeputte of your staff our need for additional information.
The enclosed request for additional information (RAI) formalizes the NRC staffs information request.
Please respond within 60 days. If more time is needed, or you need clarification of this RAI, feel free to call me at 301-415-1451.
Sincerely,
/RA/
Peter S. Tam, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-220
Enclosure:
RAI cc w/encl: See next page
April 4, 2002 Mr. John T. Conway Site Vice President Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED AMENDMENT OF TECHNICAL SPECIFICATION, SECTION 6.0 (TAC NO. MB2441)
Dear Mr. Conway:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing the subject proposed amendment, requested by your letter dated October 26, 2001. On March 28, 2002, we discussed by telephone with Mr. D. Vandeputte of your staff our need for additional information.
The enclosed request for additional information (RAI) formalizes the NRC staffs information request.
Please respond within 60 days. If more time is needed, or you need clarification of this RAI, feel free to call me at 301-415-1451.
Sincerely,
/RA/
Peter S. Tam, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-220
Enclosure:
RAI cc w/encl: See next page DISTRIBUTION:
PDI-1 R/F PUBLIC JMunday PTam OGC AChu ACRS RDennig BPlatchek, RGI SLittle Accession Number: ML020940164 OFFICE PDI-1/PM PDI-1/LA RORP RORP/SC PDI-1/SC(A)
NAME PTam SLittle AChu CHarbuck for RDennig JMunday DATE 03/29/02 03/29/02 03/29/02 04/02/02 04/02/02 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 AMENDMENT APPLICATION DATED OCTOBER 26, 2001 SECTION 6.0 OF TECHNICAL SPECIFICATIONS The licensees application proposed to revise Section 6.0, Administrative Controls, of the Nine Mile Point Nuclear Station, Unit No. 1, Technical Specifications (TSs). In the NRC staffs judgment, the proposed amendment is in fact a conversion of Section 6.0 of the TSs to the Improved Standard Technical Specifications (ISTS) format.
In accordance with Nuclear Energy Institute (NEI)-9606, NEI Improved Technical Specifications Conversion Guidance, dated August 1996, the attachments to an ISTS conversion application for each chapter should include the following:
- 1. A reprinted copy of the proposed TS in the ISTS format;
- 2. Marked-up pages of the current Technical Specifications to show the proposed changes;
- 3. Discussion of the proposed changes of the current TS;
- 4. Marked-up pages of the ISTS and Bases to show the proposed changes;
- 5. Justification for differences between the proposed changes and the ISTS
- 6. Proposed no significant hazards consideration determination for the changes.
The October 26, 2001, application is lacking Items 4 (excluding Bases) and 5. These items need to be provided before the review can be completed.
In addition, NEI-9606 specifies that electronic files be provided in WordPerfect 5.1 on diskettes which contain discussions of the changes and justification for differences between the ISTS and the proposed new improved TS.
Enclosure
Nine Mile Point Nuclear Station Unit No. 1 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 126 Lycoming, NY 13093 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mr. Paul D. Eddy Electric Division NYS Department of Public Service Agency Building 3 Empire State Plaza Albany, NY 12223 Mr. William M. Flynn, President New York State Energy, Research, and Development Authority Corporate Plaza West 286 Washington Avenue Extension Albany, NY 12203-6399 Mark J. Wetterhahn, Esquire Winston & Strawn 1400 L Street, NW Washington, DC 20005-3502 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Mr. Robert E. Denton President Nine Mile Point Nuclear Station, LLC 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Mr. Raymond L. Wenderlich Senior Constellation Nuclear Officer Responsible for Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093 Mr. James M. Petro, Jr., Esquire Counsel Constellation Power Source, Inc.