Letter Sequence Approval |
---|
|
|
MONTHYEARML0205104142002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0212200812002-05-28028 May 2002 Ltr, Reply to Licensee'S Response to Security Order Project stage: Other ML0225402152002-09-18018 September 2002 Gen. Station, Unit 1 Tac. MB4197- Reply to Response Order for Interim Safeguards and Security Compensatory Measures Project stage: Other 2002-05-28
[Table View] |
|
---|
Category:Letter
MONTHYEARML24025A0992024-01-25025 January 2024 Withdrawal of Request for Exemption from Specific 10 CFR Part 73 Requirements ML24018A0792024-01-22022 January 2024 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed Nshcd and Opportunity for a Hearing (EPID L-2024-LLA-0007) (Letter) ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information ML24018A2482024-01-18018 January 2024 License Amendment Request to Modify the Implementation Date of License Amendment No. 238 IR 05000482/20230042024-01-11011 January 2024 Integrated Inspection Report 05000482/2023004 ML23356A0722024-01-0404 January 2024 Supplemental Information Needed for Acceptance of Requested Licensing Actions Exemption from Specific 10 CFR Part 73N Requirements (EPID L-2023-LLE-0048) (Redacted Version) WO 23-0002, Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-0082023-12-26026 December 2023 Operating Corp., Summary of Actions Implemented for EA-18-165, Confirmatory Order, NRC Inspection Report 05000482/2019010 and NRC Investigation Report 4-2018-008 ML23348A3662023-12-18018 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000482 2024012) and Request for Information ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23299A2662023-11-29029 November 2023 Issuance of Amendment No. 238 Modified Implementation Date of License Amendment No. 237 ML23331A4972023-11-27027 November 2023 Supplement to License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23325A2112023-11-20020 November 2023 Submittal of Request for Exemption from Specific Provisions in 10 CFR 73.55 ML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML23292A3592023-10-19019 October 2023 License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23292A3572023-10-19019 October 2023 Operating Corporation, Request for Correction in Response to Issuance of Amendment No. 237 and Corresponding Safety Evaluation ML23277A2772023-10-11011 October 2023 Regulatory Audit Summary Concerning Review of Request Number CI3R-01 for Proposed Alternative Inspection Frequency for Containment Unbonded Post Tensioning System Components ML23284A2392023-10-11011 October 2023 NRC Initial Operator Licensing Examination Approval 05000482/2023301 ML23276B4552023-10-0303 October 2023 Technical Specification 5.6.8 Post Accident Monitoring (PAM) Report ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L ML23256A2062023-09-14014 September 2023 Withdrawal of Requested Licensing Action Exemption from Specific 10 CFR Part 73 Requirements ML23165A2502023-08-31031 August 2023 Issuance of Amendment No. 237 Request for Deviation from Fire Protection Requirements ML23243A0002023-08-31031 August 2023 Wolf Generating Station - Withdrawal of Request for Exemption from Specific 10 CFR Part 73 Requirements IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 ML23221A3932023-08-0909 August 2023 Submittal of Request for Exemption from Specific 10 CFR Part 73 Requirements ML23220A4222023-08-0808 August 2023 Supplement to License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ML23201A1212023-08-0707 August 2023 Issuance of Amendment No. 236 Revision to Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML23130A2902023-07-26026 July 2023 Issuance of Amendment No. 235 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections IR 05000482/20230022023-07-11011 July 2023 Integrated Inspection Report 05000482/2023002 ML23167A0042023-06-26026 June 2023 Audit Plan to Support Review of Request for Alternative Containment Inservice Inspection Frequency IR 05000482/20234012023-06-21021 June 2023 Security Baseline Inspection Report 05000482/2023401 ML23171B1312023-06-20020 June 2023 Additional Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ET 23-0006, CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components2023-05-17017 May 2023 CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components WO 23-0014, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) ML23135A1172023-05-0808 May 2023 Redacted Version of Revision 36 to Updated Safety Analysis Report ML23117A2112023-04-27027 April 2023 Annual Exposure Report (2022) ML23117A1342023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report Report 46 2024-01-04
[Table view] |
Text
SAFEGUARDS INFORMATION February 25, 2002 Otto L. Maynard President and Chief Executive Officer Wolf Creek Generating Station, Unit 1 Wolf Creek Nuclear Operating Corporation 1550 Oxon Lane N.E.
Burlington, KS 66839
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - WOLF CREEK GENERATING STATION, UNIT 1
Dear Mr. Maynard:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
O. Maynard The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
Wolf Creek Generating Station cc:
Jay Silberg, Esq. Vice President Operations Shaw, Pittman, Potts & Trowbridge Wolf Creek Nuclear Operating Corporation 2300 N Street, NW P. O. Box 411 Washington, D.C. 20037 Burlington, KS 66839 Regional Administrator, Region IV Superintendent Licensing U.S. Nuclear Regulatory Commission Wolf Creek Nuclear Operating Corporation 611 Ryan Plaza Drive, Suite 1000 P.O. Box 411 Arlington, TX 76011 Burlington, KS 66839 Senior Resident Inspector U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspectors Office P. O. Box 311 8201 NRC Road Burlington, KS 66839 Steedman, MO 65077-1032 Chief Engineer Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS 66604-4027 Office of the Governor State of Kansas Topeka, KS 66612 Attorney General Judicial Center 301 S.W. 10th 2nd Floor Topeka, KS 66612 County Clerk Coffey County Courthouse Burlington, KS 66839 Vick L. Cooper, Chief Radiation Control Program, RCP Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366
O. Maynard February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD4-2 JDonohew EPeyton SRichards SDembek RidsRgn4MailCenter Accession No. ML020490028 (Package)
Accession No. ML020 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY