APPLICABILITY SURVEILLANCE REQUIREMENTS 4.0.1 Surveillance Requirements shall be applicable during the OPERATIONAL MODES or other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement.
4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a maximum allowable extension not to exceed 25 percent of the specified surveillance interval.
4.0.3 Failure to perform a Surveillance Requirement within the allowed surveillance interval, defined by Specification 4.0.2, shall constitute noncompliance with the OPERABILITY requirements for a Limiting Condition for Operation.
The time limits of the ACTION requirements are applicable at the time it is identified that a Surveillance Requirement has not been performed.
The ACTION requirements may be delayed for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to permit the completion of the surveillance when the allowable (equipment inoperability) outage time limits of the ACTION requirements are less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Surveillance requirements do not have to be performed on inoperable equipment.
4.0.4 Entry into an OPERATIONAL MODE or other specified applicability condition shall not be made unless the Surveillance Requirement(s) associated with the Limiting Condition for Operation have been performed within the stated surveillance interval or as otherwise specified.
4.0.5 Surveillance Requirements for inservice inspection and testing of ASME Code Class 1, 2 and 3 components shall be applicable as follows:
- a. Inservice inspection of ASME Code Class 1, 2 and 3 components shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a.
Inservice Testing of ASME Code Class 1, 2 and 3 pumps and valves shall be performed in accordance with the ASME Code for Operation and Maintenance of Nuclear Power Plants (ASME OM Code) and applicable Addenda as required by 10 CFR 50, Section 50.55a.
Amendment No. 71,140,145,197, 250 3/4 0-2 DAVIS-BESSE, UNIT I
APPLICABILITY SURVEILLANCE REQUIREMENTS (Continued)
- b. Surveillance intervals specified in Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda and the ASME OM Code and applicable Addenda shall be applicable as follows in these Technical Specifications:
ASME Boiler and Pressure Vessel Code and the ASME OM Code and applicable Addenda terminology for inservice inspection and testing criteria Weekly Monthly Semi-quarterly Quarterly or every 3 months Semiannually or every 6 months Every 9 months Yearly or annually Biennially or every 2 years Required frequencies for performing inservice inspection and testing activities At least once per 7 days At least once per 31 days At least once per 46 days At least once per 92 days At least once per 184 days At least once per 276 days At least once per 366 days At least once per 731 days
- c. The provisions of Specification 4.0.2 are applicable to the above required frequencies for performing inservice inspection and testing activities.
- d. Performance of the above inservice inspection and testing activities shall be in addition to other specified Surveillance Requirements.
- e. Nothing in the ASME Boiler and Pressure Vessel Code or the ASME OM Code shall be construed to supersede the requirements of any Technical Specification.
DAVIS-BESSE, UNIT I I
I I I I
3/4 0-3 Amendment No. 250
APPLICABILITY BASES 4.0.5 This specification ensures that: 1) inservice inspection of ASME Code Class 1, 2 and 3 components will be performed in accordance with a periodically updated version of Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50.55a, and 2) inservice testing of ASME Code Class 1, 2 and 3 pumps and valves will be performed in accordance with a periodically updated version of the ASME Code for Operation and Maintenance of Nuclear Power Plants (OM Code) and applicable Addenda as required by 10 CFR 50.55a.
This specification includes a clarification of the frequencies for performing the inservice inspection and testing activities required by Section XI of the ASME Boiler and Pressure Vessel Code and the ASME OM Code and their applicable Addenda. This clarification is provided to ensure consistency in surveillance intervals throughout these Technical Specifications and to remove any ambiguities relative to the frequencies for performing the required inservice inspection and testing activities.
Under the terms of this specification, the more restrictive requirements of the Technical Specifications take precedence over the ASME Boiler and Pressure Vessel Code and the ASME OM Code and their applicable Addenda. For example, the requirements of Specification 4.0.4 to perform surveillance activities prior to entry into an OPERATIONAL MODE or other specified applicability condition takes precedence over the ASME OM Code provision which allows pumps to be tested up to one week after return to normal operation.
Amendment No. 145, 197, 213,250 DAVIS-BESSE, UNIT 1 B 3/4 0-4
3/4.4 REACTOR COOLANT SYSTEM BASES inject water into the reactor coolant system is disabled to ensure operation within reactor coolant system pressure-temperature limits.
Demonstration of the safety valves' lift settings will occur only during shutdown and will be performed in accordance with the provisions of the ASME Code for Operation and Maintenance of Nuclear Power Plants and applicable Addenda.
The pressurizer code safety valves must be set such that the peak Reactor Coolant System pressure does not exceed 110% of design system pressure (2500 psig) or, 2750 psig. The control rod group withdrawal accident will result in the most limiting high pressure in the RCS. The analysis assumes RPS high pressure trip at 2355 psig and the code safety valves open at 2500 psig. The tolerance on the RPS instrument accuracy is 30 psi and, it is +1% for the code safety valve settings. The pressurizer pilot operated relief valve was assumed not to open for this transient. The resulting system peak pressure was calculated to be 2700 psig. Therefore, the code safety valve setpoint is conservatively set at
- 2525 psig which is the maximum pressure of 2500 psig + 1% for tolerance.
The pressurizer pilot operated relief valve should be set such that it will open before the code safety valves are opened. However, it should not open on any anticipated transients. BAW-1890, September 1985 identified that the turbine trip from full power would cause the largest overpressure transient. This report demonstrated that with a RPS high pressure trip setpoint of 2355 psig the resulting overshoot in RCS pressure would be limited to 50 psi. Consequently, the minimum PORV setpoint needs to accommodate both the RCS pressure overshoot and the RPS instrument string error of 30 psi.
Amendment No. 33,60,128,135,250 DAVIS-BESSE, UNIT I B 3/4 4-1a