Corrected TS Page for Amendment 123 Re Redundant Train Requirements with an Inoperable Emergency Diesel Generator
ML020070275
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 01/04/2002
From: Moroney B
NRC/NRR/DLPM/LPD2
To: Stall J
Florida Power & Light Co
References
TAC MB3182
Download: ML020070275 (4)


Text

NSREG~j

' RUNITED STATES 0 -NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 4, 2002 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

ST. LUCIE UNIT 2 - ISSUANCE OF CORRECTED PAGE FOR AMENDMENT NO. 123 REGARDING REDUNDANT TRAIN REQUIREMENTS WITH AN INOPERABLE EMERGENCY DIESEL GENERATOR (TAC NO. MB3182)

Dear Mr. Stall:

Following the issuance of Amendment No. 123 to Facility Operating License No. NPF-1 6 for the St. Lucie Plant, Unit No. 2, your staff noted an error on the clean (corrected) Technical Specification (TS) page 3/4 8-1 that they had submitted. TS 3.8.1.1, under ACTION b, should have read ". . . restore the diesel generator to OPERABLE status within 14 days.... ." (instead of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />). The error was in a section of the TSs that was not included in Amendment 123.

This letter forwards the corrected page to be inserted into the amendment in place of the incorrect one.

Sincerely, Brendan T. Moroney, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-389

Enclosure:

Corrected TS Page cc w/enclosure: See next page

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a. Two physically independent circuits between the offsite transmission network and the onsite Class 1E distribution system, and
b. Two separate and independent diesel generators, each with:
1. Two separate engine-mounted fuel tanks containing a minimum volume of 200 gallons of fuel each,
2. A separate fuel storage system containing a minimum volume of 40,000 gallons of fuel, and
3. A separate fuel transfer pump.

APPLICABILITY: MODES 1, 2, 3, and 4.

ACTION:

a. With one offsite circuit of 3.8.1.1.a inoperable, except as provided in Action f.

below, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1 .a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter. Restore the offsite circuit to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

b. With one diesel generator of 3.8.1.1 .b inoperable, demonstrate the OPERABILITY of the A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; and ifthe EDG became inoperable due to any cause other than an inoperable support system, an independently testable component, or preplanned preventative maintenance or testing, demonstrate the OPERABILITY of the remaining OPERABLE EDG by performing Surveillance Requirement 4.8.1.1.2a.4 within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, unless it can be confirmed that the cause of the inoperable EDG does not exist on the remaining EDG*; restore the diesel generator to OPERABLE status within 14 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Additionally, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from the discovery of concurrent inoperability of required redundant feature(s) (including the steam driven auxiliary feed pump in MODE 1, 2, and 3),

declare required feature(s) supported by the inoperable EDG inoperable if its redundant required feature(s) is inoperable.

If the absence of any common-cause failure cannot be confirmed, this test shall be completed regardless of when the inoperable EDG is restored to OPERABILITY.

ST. LUCIE - UNIT 2 3/4 8-1 Amendment No. 2-5, 49, 7-8, 4-15, 123

Mr. J. A. Stall ST. LUCIE PLANT Florida Power and Light Company cc:

Senior Resident Inspector Mr. R. G. West St. Lucie Plant Plant General Manager U.S. Nuclear Regulatory Commission St. Lucie Nuclear Plant P.O. Box 6090 6351 South Ocean Drive Jensen Beach, Florida 34957 Jensen Beach, Florida 34957 Joe Myers, Director Mr. T. L. Patterson Division of Emergency Preparedness Licensing Manager Department of Community Affairs St. Lucie Nuclear Plant 2740 Centerview Drive 6351 South Ocean Drive Tallahassee, Florida 32399-2100 Jensen Beach, Florida 34957 M. S. Ross, Attorney Mr. Don Mothena Florida Power & Light Company Manager, Nuclear Plant Support Services P.O. Box 14000 Florida Power & Light Company Juno Beach, FL 33408-0420 P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Douglas Anderson County Administrator Mr. Rajiv S. Kundalkar St. Lucie County Vice President - Nuclear Engineering 2300 Virginia Avenue Florida Power & Light Company Fort Pierce, Florida 34982 P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. William A. Passetti, Chief Department of Health Mr. J. Kammel Bureau of Radiation Control Radiological Emergency 2020 Capital Circle, SE, Bin #C21 Planning Administrator Tallahassee, Florida 32399-1741 Department of Public Safety 6000 SE. Tower Drive Mr. Donald E. Jernigan, Site Vice President Stuart, Florida 34997 St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957

OFFICE PPlI-2/PM PDII-2/LA PDII-2/SC NAME BW1orn4y' RCot-'ia"- /

DATE 01/04/02 01/04/02 01/04/02