MONTHYEARLR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, And Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 And Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains LR-N23-0024, Submittal of Hope Creek Generating Station Technical Specification Bases Changes2023-03-29029 March 2023 Submittal of Hope Creek Generating Station Technical Specification Bases Changes LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N23-0016, And Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 And Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0018, Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges2023-02-27027 February 2023 Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 LR-N23-0011, In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage2023-01-19019 January 2023 In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage LR-N22-0096, And Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 And Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments LR-N22-0075, 2022 Annual 10 CFR 50.46 Report2022-09-30030 September 2022 2022 Annual 10 CFR 50.46 Report LR-N22-0074, Emergency Plan Evacuation Time Estimate2022-09-15015 September 2022 Emergency Plan Evacuation Time Estimate LR-N22-0051, License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report2022-06-22022 June 2022 License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report LR-N22-0044, Emergency Plan Document Revisions Implemented November, 20212022-05-19019 May 2022 Emergency Plan Document Revisions Implemented November, 2021 LR-N22-0040, 2021 Annual Radiological Environmental Operating Report2022-04-28028 April 2022 2021 Annual Radiological Environmental Operating Report LR-N22-0041, 2021 Annual Radioactive Effluent Release Report (Rerr)2022-04-28028 April 2022 2021 Annual Radioactive Effluent Release Report (Rerr) LR-N22-0039, Emergency Plan Document Revisions Implemented March 24, 20222022-04-21021 April 2022 Emergency Plan Document Revisions Implemented March 24, 2022 LR-N22-0023, Guarantees of Payment of Deferred Premiums2022-03-21021 March 2022 Guarantees of Payment of Deferred Premiums LR-N22-0017, Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data2022-02-25025 February 2022 Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data LR-N22-0019, Technical Specification 6.9.1.5.b 2021 Annual Report of SRV Challenges2022-02-24024 February 2022 Technical Specification 6.9.1.5.b 2021 Annual Report of SRV Challenges LR-N22-0016, Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility2022-02-24024 February 2022 Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility LR-N22-0011, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink2022-02-0101 February 2022 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink LR-N22-0005, Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs2022-01-0707 January 2022 Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs 2024-09-30
[Table view] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 0 7 2004 PSEG LR-N04-0161 Nuclear LLC United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NPF-57 DOCKET NO. 50-354 UPDATE ASME Xi CODE OF RECORD Federal Register (Notice 66 FR 40626) amended 10CFR50.55a(g) and revised the requirements for inservice inspection (ISI) of nuclear power plant components by permitting the use of ASME Boiler and Pressure Vessel Code, Section Xl 1998 Edition up through and including 2000 Addenda. The first 10-year inspection interval for Hope Creek Generating Station ended on December 13, 1997. In accordance with 10CFR50.55a, the second 10-year inspection interval was prepared to meet the requirements of the NRC approved ASME Section Xi Code in effect on December 13, 1996. This Code is the 1989 Edition no Addenda.
The current ISI Program for Hope Creek Generating Station is based on ASME Section Xl 1989 Edition no Addenda. This letter is to inform you that the Code of record for Hope Creek Generating Station for the remainder of the second 10-year interval has been upgraded to the latest approved ASME Section Xl Code incorporated into 10CFR50.55a for ISI on all affected ASME Xl (Class 1, 2 and 3)
Subsections IWB, IWC, IWD and IWF systems, structures and components contained within Tables IWX-2500-1. This will make it easier for involved personnel to be familiar with ASME XI code requirements, ensure a greater degree of implementation consistency, decrease costs associated with surveillance procedure revisions, reduce opportunities for inadvertent human errors due to differences between code requirements and lessen administrative burdens and complexities associated with maintaining multiple ISI Program Long Term Plans.
1 4-DN7 95-2168 REV. 7/99
Document Control Desk 2 MAY 0 7 2004 LR-N04-0161 PSEG will comply with 1998 Edition up through and including 2000 Addenda unless relief is requested in accordance with 10CFR50.55a (a)(3). PSEG will comply with the following 10CFR50.55a imposed additional requirements for:
o Exam Category B-D, items B3.40, B3.60, B3.120 and B3.140 for the use of ASME 1998 Edition for the inspection of Nozzle Inner Radii.
o Exam Category B-G-2, item B7.80 for the use of ASME 1995 Edition to perform VT-1 of CRD housing bolts, studs and nuts when disassembled.
o Exam Category B-K, item B10.10 for the use of ASME 1995 Edition to examine welded attachments on at least one vessel in each group.
On March 11, 2004, (LR-N04-0115) PSEG submitted a Risk Informed Inservice Inspection (RI-ISI) program for ASME Xl Exam Categories B-F, B-J, C-F-1 and C-F-2 class 1 and 2 piping. This program will be substituted beginning with the Fall 2004 refueling outage.
ASME Xi Subsections IWE and IWL will continue to be performed in accordance with PSEG Nuclear's previously submitted and approved relief requests for IWE and IWL and the NRC's Safety Evaluation Report (SER) (TAC) for Hope Creek Generating Station containment inspection.
ASME Xi Appendix Vil requirements will continue to be performed in accordance with ASME Xl 1998 Edition up to and including the 2000 Addenda, as modified by 10CFR.50.55a final rulemaking.
There are no new commitments contained in this letter. If you have any questions, please contact Michael Mosier at (856) 339-5434.
Sincerely, Steven R. Mannon Manager Nuclear Safety and Licensing
Document Control Desk 3 LR-N04-0161 MAY 0 7 2004 C Mr. H. Miller Regional Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. D. Collins, Project Manager - Hope Creek U.S. Nuclear Regulatory Commission Mail Stop 08C2 Washington, DC 20555-0001 USNRC Senior Resident Inspector - Hope Creek (X24)
Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering P.O. Box 415 Trenton, NJ 08625