MONTHYEARML0833602642008-09-17017 September 2008 E-mail Request for Additional Information Re Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 31 Project stage: RAI LIC-08-0109, Response to Request for Additional Information Concerning Exemption from Requirements of 10 CFR 50, Appendix R, Section Iii.G.B. for Fire Area 312008-10-13013 October 2008 Response to Request for Additional Information Concerning Exemption from Requirements of 10 CFR 50, Appendix R, Section Iii.G.B. for Fire Area 31 Project stage: Response to RAI ML0833300362008-12-23023 December 2008 Environmental Assessment and Finding of No Significant Impact, Re Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 31 Project stage: Approval ML0833300262008-12-23023 December 2008 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML0900504382009-02-0606 February 2009 Transmittal Letter, Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 31 Project stage: Approval ML0900504422009-02-0606 February 2009 Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 31 Project stage: Approval NRC-2008-0670, Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 312009-02-0606 February 2009 Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.1.b for Fire Area 31 Project stage: Approval 2008-12-23
[Table View] |
|
---|
Category:Letter type:LIC
MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
Omaha Public Power District 444 South 16th Street Mall Omaha NE 68102-2247 October 13, 2008 LIC-08-0109 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
References:
- 1. Docket No. 50-285
- 2. Letter from OPPD (R. P. Clemens) to NRC (Document Control Desk),
"Request for Exemption from Requirements of 10 CFR 50, Appendix R, Section IIl.G.1.b for Fire Area 31 at the Fort Calhoun Station," dated February 4, 2008 (LIC-08-0006)
- 3. Email from NRC (A. B. Wang) to OPPD (B. R. Hansher), "FP (Fire Protection) RAI (Request for Additional Information)," dated September 17, 2008
SUBJECT:
,Response to Request for Additional Information Concerning
,.,Exemption from Requirements of 10 CFR 50, Appendix R, Section I*ll.G.l.b. for Fire Area 31 at the Fort Calhoun Station In Reference 2, the Omaha Public Power District (OPPD) requested an exemption, pursuant to 10 CFR 50.12 and 10 CFR 50.48, from the requirements of Appendix R, Section IIl.G.l.b.', which requires that fire protection features be provided for the structures, systems and components important to safe shutdown (raw water pump and valve cables) at Fort Calhoun Station (FCS). In Reference 3, the NRC Project Manager sent OPPD a request for additional information regarding the Reference 2 submittal. In a teleconference on September 25, 2008, the NRC provided additional clarification to the information being sought. OPPD's response to the NRC RAI is attached.
No regulatory commitments are made in this letter. If you should have any further questions, please contact Mr. Bill R. Hansher at (402) 533-6894.
Sinrerel,..
7-
' R. 'P. Clemens Division ManagePr.:,
Nuclear Engineering RPC/MLE/mle
Attachment:
Response to NRC RAI 1l6(,
Employment with Equal Opportunity 4171
LIC-08-0109 Attachment Page 1 Response to NRC Request for Additional Information Concerninq Exemption from Requirements of 10 CFR 50, Appendix R, Section IIl.G.l.b. for Fire Area 31 at the Fort Calhoun Station By letter dated February 4, 2008, the Omaha Public Power District requested an exemption for the Fort Calhoun Station, Unit 1 from requirements of Section IIl.G.1.b of Appendix R to Part 50 of Title 10 "Energy" of the Code of FederalRegulations (10 CFR 50), and the 72-hour requirement to provide repair procedure(s) and material for-cold shutdown capability for redundant cold shutdown components.
The proposed exemption request addresses the power and control cables for the four raw water pumps that are routed from the auxiliary building through outside cable pull boxes 128T and 129T into the underground duct bank and manhole vaults number 5 and 31 into the intake structure building.
The Nuclear Regulatory Commission staff has reviewed the information the licensee provided that supports the proposed changes to their approved fire protection program.
In order for the staff to complete its evaluation, the following additional information is requested:
NRC RAI Section II of Appendix R to 10 CFR Part 50, "General Requirements," states that thefire.
protection program shall extend the concept of defense-in-depth to fire protection in fires areas that are important to safety, with the following objectives:
- Prevent fires from starting.
- Rapidly detect, control, and extinguish those fires that do occur.
- Protect structures, systems, and components that are important to safety so that a fire that is not promptly extinguished -by the fire suppression activities will not prevent the safe shutdown of the plant.
The staff requests that the licensee provide a description of the defense-in-depth features in the underground duct bank and manhole vaults number 5 and 31.
OPPD Response The following is a description of the defense-in-depth features of the Fort Calhoun Station (FCS) fire protection program as it applies to the underground duct bank and manhole vaults No. 5 and 31.
Prevent Fires from Starting There are no ignition sources in the duct bank and manhole vaults, other than the remote possibility of a self-ignited cable fault. The duct bank and manholes are not occupied locations and are generally inaccessible, which minimizes the potential for
LIC-08-0109 Attachment Page.2 introducing transient ignition sources or combustible materials. The area is classified as a confined space and therefore, entry is not allowed without appropriate permits and controls. Maintenance personnel inspect the manholes annually; however, these activities do not involve ignition sources or transient combustible materials, so there is no added risk of fire initiation. Hot work performed in the duct bank and/or manhole vaults is conducted in accordance with SO-M-9, and FCSG-15-35, which requires the protection of electrical cables located within 35 feet of the welding or cutting location.
Procedural Guidance Hot work operations are controlled by Standing Order (SO)-M-9, "Hot Work Operations,"
and FCS Guideline (FCSG)-15-35, "Guideline Welding, Cutting and Burning." Prior to beginning hot work, form FC-18, "Hot Work Permit" is completed and a copy given to the Operations Control Center (OCC). Form FC-18 contains numerous steps to prevent, detect, and respond to a fire. The steps include protecting areas such as electrical cabling located within 35 feet of the welding or cutting location. A trained individual is designated fire watch both during and for 30 minutes after the hot work is completed. The fire watch monitors the work area, adjacent areas, and above and below the work area. The fire watch is trained to immediately report fires to the control room and is equipped with a fire extinguisher to extinguish small fires if possible.
If hot work were to be performed in a confined space like the duct bank and/or manhole vaults, FCSG-15-35 has additional controls that apply when welding is suspended for a substantial period of time such as for lunch or overnight. In these circumstances, electrodes are removed from holders, the holders carefully located so that accidental contact cannot occur, and the welding machine disconnected from its power source.
When gas welding or cutting is performed, the torch valves are closed to eliminate the possibility of gas escaping through leaks or improperly closed valves, the gas supply is shutoff at the source, the regulator pressure is bled off and the torch and hose are removed from the confined space.
Rapidly Detect, Control And Extinguish Those Fires That Do Occur There are no means of automatic fire detection or suppression in the duct bank or manhole vaults. However, if a fire did occur, operators in the control room would have indications of equipment faults (e.g., tripping of operating pumps, off-normal valve indication lights, etc.) and rapidly begin to investigate the cause and location of the fault.
The duct bank and manhole vaults are located inside the protected area in close proximity to the power block, which would facilitate rapid detection and extinguishment of the fire. A fire in the duct bank and/or manhole vaults involving cable insulation would produce significant amounts of smoke through the manhole covers, providing another indication of the location of the fire to operators and/or fire brigade personnel.
The fire brigade using manual fire suppression equipment including portable fire extinguishers and/or fire hoses would extinguish the fire. Should a fire occur as a result of hot work in the duct bank and/or manhole vaults, the craft or fire watch would
LIC-08-0109 Attachment Page 3 immediately contact the control room, and the fire brigade would be dispatched to extinguish the fire.
Protect Structures, Systems, and Components that are Important to Safety As stated in Reference 2, there is no credible threat from a fire involving the duct bank and manhole vaults that would disable all trains of raw water and prevent safe shutdown of the plant. Therefore, FCS has adequately protected the structures, systems, and components (SSCs) important to safety necessary to meet this level of defense-in-depth for fire protection.
NRC RAI Your letter dated February 4, 2008 Attachment 1, Page 6, states that,
"...In the unlikely event that all raw water pumps are lost for any reason, OPPD maintains an abnormal operating procedure (AOP) for loss of the raw water system. If all raw water pumps are lost, due to any condition, the procedure directs the operators to trip the reactor and enter emergency operating procedures (EOPs) based on observed plant conditions..." AOPs often do not assume damage to collateral equipment in a fire area or cable tunnel.
Please confirm that the post-fire safe-shutdown analysis assumes that the FCS Unit I AOPs have all equipment available during a postulated fire. Without a heat sink (loss of raw water), for a pressurized water reactor, EOPs often result in going to a "feed and bleed" means of protecting the core. Confirm that the post-fire safe shutdown analysis EOPs do not rely solely on feed and bleed as the means of protecting the core.
OPPD Response The FCS Post-Fire Safe Shutdown Analysis (Engineering Analysis (EA)-FC-89-055) assumes all equipment credited for a given fire area is available during a postulated fire.
FCS does not rely solely on once through cooling (or "feed and bleed") as a means of heat removal to protect the reactor core in a post-fire safe shutdown scenario. Options for reactor coolant system (RCS) heat removal in FCS Emergency Operating Procedure (EOP)-20 "Functional Recovery Procedure" include:
- 1. RCS and core heat removal via steam generators with no safety injection,
- 2. RCS and Core Heat Removal via steam generators with safety injection operating,
- 3. Shutdown cooling operation, and
- 4. Feed and bleed (or once through cooling).
LIC-08-0109 -
Attachment Page 4 Although feed and bleed is one of the EOP-20 options, it is the least desirable and would only be utilized if other means are unavailable or have failed for the given plant conditions.
Please note that FCS does not have a specific EOP for post-fire safe shutdown. For a fire within the protected area, FCS implements Abnormal Operating Procedure (AOP)-
06, "Fire Emergency." Based on the extent of fire damage, location of the fire and plant response to the fire, control room operators have the option to implement EOPs to achieve safe shutdown conditions.
NRC RAI Clarify and confirm that the types of combustibles have not changed and total combustible loading in the intake structure building has not increased, and that there is no change in active and passive fire protection features as last described in your letter dated August 30, 1983. If there is a change in the types of combustibles or there is an increase in combustible load or change in fire protection features in the intake structure building, the staff requests that the OPPD provide details and a basis for why the change remains acceptable. Also confirm that the pyrocrete enclosure is in place to protect the cables for raw water pumps AC-10A and AC-1OB from fire in the intake structure building.
OPPD Response The type of combustible material in the duct bank and manhole vaults is limited to cable insulation. This has not changed since original plant construction. Any change in the total combustible loading since August 30, 1983 for the duct bank, manhole vaults, and/or intake structure would have been evaluated for impact on the combustible loading calculation (FC05814), which is the controlled design calculation that maintains an accounting of combustible load for fire areas at FCS. A review of previous revisions of this calculation confirms that total combustible loading has remained classified as low and no significant changes in total loading has occurred. Therefore, the basis for this reference remains valid.
The pyrocrete enclosure remains in place to protect cables associated with AC-1 A and AC-10B from a fire in the intake structure. This enclosure is inspected by a fire barrier surveillance test on an 18-month interval.