Letter Sequence Response to RAI |
---|
|
|
|
|
---|
Category:Letter type:LIC
MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
Fort Calhoun Station PO. Box 550 Fort Calhoun, NE 68023 January 16,2007
, LIC-07-000 1 U. S. Nuclear Regulatory Commission Attn: Document Control Desk 1 Washington, DC 20555-0001 1
References:
- 1. Docket No. 50-285 i 2. NRC Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power" (NRC-06-0013)
I I
- 3. Letter from OPPD (H. J. Faulhaber) to NRC (Document Control Desk), "60 Day Response to Generic Letter 2006-02" dated April 3, 2006 (LIC-06-0025)
- 4. Letter from NRC (C. Haney) to OPPD (R. T. Ridenoure), "Request for Additional 1I Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power," dated December j 5,2006 (NRC-06-0168) 1 5. Letter from NRC (C. Haney) to OPPD (R. T. Ridenoure), "Revised Response Date 1 For Request For Additional Information Regarding Resolution Of Generic Letter I
i 1 2006-02, Grid Reliability And The Impact On Plant Risk And The Operability Of Offsite Power," dated December 13,2006 (NRC-06-0 176)
SUBJECT:
Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power" Attached is the Omaha Public Power District (OPPD) response to Reference 4, which is an NRC request for additional information (RAI) regarding resolution of Generic Letter (GL) 2006-02 (Reference 2). In Reference 5, the NRC extended the due date of the required response to January 3 1,2007. Reference 3 is OPPD's initial response to GL 2006-02.
No commitments to the NRC are made in this letter.
I declare under penalty of perjury that the foregoing is true and correct. (Executed on January 16, 2007.)
U. S. Nuclear Regulatory Commission LIC-07-0001 Page 2 If you have additional questions, or require further information, please contact Mr. Thomas C.
Matthews at (402) 533-6938.
Sincerely, Division Manager Nuclear Engineering
Attachment:
Response to RAI Regarding Resolution of Generic Letter 2006-02
LIC-07-0001 Attachment Page 1 ATTACHMENT Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power"
LIC-07-000 1 Attachment Page 2 REQUESTED INFORMATION (only Question 4 was applicable to Fort Calhoun Station)
NRC Question
- 4. Identification of Applicable Single Contingencies In response to question 3(a) you did not identify the loss of other critical transmission elements that may cause the offsite power system (OSP) to degrade, other than the loss of the nuclear unit.
If it is possible for specific critical transmission elements (such as other generators, critical transmission line, transformers, capacitor banks, voltage regulators, etc.) to degrade the OSP such that inadequate post-trip voltage could result, have these elements been included in your N-1 contingency analysis? When these elements are included in your GO'S contingency analysis model and failure of one of these transmission elements could result in actuation of your degraded voltage grid relay, is the offsite power declared inoperable? If not, what is your basis for not declaring the offsite power inoperable?
OPPD Answer As stated in OPPD's response (Reference 3) to Item 2(e) of Generic Letter (GL) 2006-02, alarms are generated on the OPPD energy management system (EMS) to notify both Fort Calhoun Station (FCS) and the control area operator (CAO) when the predicted post-plant-trip voltages at Substation 1251 drop below 16l.OkV, 160.8kV, and 158.8kV. These post-plant-trip voltages are specified in Quality Procedure NOD-QP-36, "Grid Operations and Control of Switchyard at FCS" to maintain FCS stability.
The calculation of post-plant-trip voltage is done only for the real-time system configuration.
The grid steady-state analysis considered the following six worst-case contingencies to determine the grid's capability to supply plant loads following a plant trip:
- 1. Outage of the 345kV line from OPPD Substation 3451 to MidAmerican (MEC) Raun Substation.
- 2. Outage of MEC Council Bluffs Unit 3.
- 3. Simultaneous outage of MEC Council Bluffs Unit 3, the 345kV line fiom OPPD Substation 3451 to OPPD Substation 3459 and the 345kV line from OPPD Substation 3451 to OPPD Substation 3454.
- 4. Outage of the 345kV line from MEC Council Bluffs Substation to OPPD Substation 3456.
- 5. Simultaneous outage of both 161kV lines from OPPD Substation 1211 to OPPD Substation 1250.
- 6. Simultaneous outage of the 345kV line fiom OPPD Substation 3451 to OPPD Substation 3459 and the 345kV line from OPPD Substation 3451 to OPPD Substation 3454.
As stated in OPPD's response (Reference 3) to Item 3(a) of GL 2006-02, at an actual or post-trip calculated value of 160.8kV, FCS will enter Technical Specification 2.7(2)c due to inoperability of house transformers T1A-3 and TlA-4. The NRC Operations Center will be notified within four hours.
If at the same time either emergency diesel generator is inoperable, the reactor will be placed in hot shutdown within six hours. At an actual or post-trip calculated value of 158.8kV for more than eight hours, the reactor will be placed in hot shutdown within twelve hours. The house transformers are
LIC-07-000 1 Attachment Page 3 considered inoperable due to the increased likelihood of activating the degraded voltage circuitry in the event of a design basis accident coincident with loss of the offsite power supply.
Text
Fort Calhoun Station PO. Box 550 Fort Calhoun, NE 68023 January 16,2007
, LIC-07-000 1 U. S. Nuclear Regulatory Commission Attn: Document Control Desk 1 Washington, DC 20555-0001 1
References:
- 1. Docket No. 50-285 i 2. NRC Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power" (NRC-06-0013)
I I
- 3. Letter from OPPD (H. J. Faulhaber) to NRC (Document Control Desk), "60 Day Response to Generic Letter 2006-02" dated April 3, 2006 (LIC-06-0025)
- 4. Letter from NRC (C. Haney) to OPPD (R. T. Ridenoure), "Request for Additional 1I Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power," dated December j 5,2006 (NRC-06-0168) 1 5. Letter from NRC (C. Haney) to OPPD (R. T. Ridenoure), "Revised Response Date 1 For Request For Additional Information Regarding Resolution Of Generic Letter I
i 1 2006-02, Grid Reliability And The Impact On Plant Risk And The Operability Of Offsite Power," dated December 13,2006 (NRC-06-0 176)
SUBJECT:
Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power" Attached is the Omaha Public Power District (OPPD) response to Reference 4, which is an NRC request for additional information (RAI) regarding resolution of Generic Letter (GL) 2006-02 (Reference 2). In Reference 5, the NRC extended the due date of the required response to January 3 1,2007. Reference 3 is OPPD's initial response to GL 2006-02.
No commitments to the NRC are made in this letter.
I declare under penalty of perjury that the foregoing is true and correct. (Executed on January 16, 2007.)
U. S. Nuclear Regulatory Commission LIC-07-0001 Page 2 If you have additional questions, or require further information, please contact Mr. Thomas C.
Matthews at (402) 533-6938.
Sincerely, Division Manager Nuclear Engineering
Attachment:
Response to RAI Regarding Resolution of Generic Letter 2006-02
LIC-07-0001 Attachment Page 1 ATTACHMENT Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, "Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power"
LIC-07-000 1 Attachment Page 2 REQUESTED INFORMATION (only Question 4 was applicable to Fort Calhoun Station)
NRC Question
- 4. Identification of Applicable Single Contingencies In response to question 3(a) you did not identify the loss of other critical transmission elements that may cause the offsite power system (OSP) to degrade, other than the loss of the nuclear unit.
If it is possible for specific critical transmission elements (such as other generators, critical transmission line, transformers, capacitor banks, voltage regulators, etc.) to degrade the OSP such that inadequate post-trip voltage could result, have these elements been included in your N-1 contingency analysis? When these elements are included in your GO'S contingency analysis model and failure of one of these transmission elements could result in actuation of your degraded voltage grid relay, is the offsite power declared inoperable? If not, what is your basis for not declaring the offsite power inoperable?
OPPD Answer As stated in OPPD's response (Reference 3) to Item 2(e) of Generic Letter (GL) 2006-02, alarms are generated on the OPPD energy management system (EMS) to notify both Fort Calhoun Station (FCS) and the control area operator (CAO) when the predicted post-plant-trip voltages at Substation 1251 drop below 16l.OkV, 160.8kV, and 158.8kV. These post-plant-trip voltages are specified in Quality Procedure NOD-QP-36, "Grid Operations and Control of Switchyard at FCS" to maintain FCS stability.
The calculation of post-plant-trip voltage is done only for the real-time system configuration.
The grid steady-state analysis considered the following six worst-case contingencies to determine the grid's capability to supply plant loads following a plant trip:
- 1. Outage of the 345kV line from OPPD Substation 3451 to MidAmerican (MEC) Raun Substation.
- 2. Outage of MEC Council Bluffs Unit 3.
- 3. Simultaneous outage of MEC Council Bluffs Unit 3, the 345kV line fiom OPPD Substation 3451 to OPPD Substation 3459 and the 345kV line from OPPD Substation 3451 to OPPD Substation 3454.
- 4. Outage of the 345kV line from MEC Council Bluffs Substation to OPPD Substation 3456.
- 5. Simultaneous outage of both 161kV lines from OPPD Substation 1211 to OPPD Substation 1250.
- 6. Simultaneous outage of the 345kV line fiom OPPD Substation 3451 to OPPD Substation 3459 and the 345kV line from OPPD Substation 3451 to OPPD Substation 3454.
As stated in OPPD's response (Reference 3) to Item 3(a) of GL 2006-02, at an actual or post-trip calculated value of 160.8kV, FCS will enter Technical Specification 2.7(2)c due to inoperability of house transformers T1A-3 and TlA-4. The NRC Operations Center will be notified within four hours.
If at the same time either emergency diesel generator is inoperable, the reactor will be placed in hot shutdown within six hours. At an actual or post-trip calculated value of 158.8kV for more than eight hours, the reactor will be placed in hot shutdown within twelve hours. The house transformers are
LIC-07-000 1 Attachment Page 3 considered inoperable due to the increased likelihood of activating the degraded voltage circuitry in the event of a design basis accident coincident with loss of the offsite power supply.