Forwards Response to IE Bulletin 79-14.Requests Defferal of Portion of Insp Re Inaccessible Areas Because of Low Defect Rate in Hanger & Restraints
ML17207A444
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 09/20/1979
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
L-79-264, NUDOCS 7910050280
Download: ML17207A444 (3)


Text

~ )

pp'gift J i.-r~;<t<IA,"--~" '

~N

~ 3~

P.O. BOX 529100 MIAM(,FL 33162 I

Jlr i

~

FLORIOA POWER IL LIGHT COJAPANY September 20, 1979 L-79-264 Mr. James P. O'Reilly, Director, Region II Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission

'l01 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Rei,

lly:

Re:

RII:JPO 50-335 IE Bulletin 79-14 The attached information addresses Items 2 and 3 of the subject Bulletin.

Based on a low defect rate, we have requested deferral of a portion of the "inaccessible" inspection.

To facilitate planning for an upcoming outage, we would appreciate your responding to our request by September 24, 1979.

Very truly yours, Robert E. Uhrig Vice President Advanced Systems 8 Technology REU/MAS/ms Attachment cc:

Director, Office of Inspection and Enforcement Director, Division of Operating Reactors Harold Reis, Esquire

- dy gp 7 9,'3.0050 1e:;I qeguai~ aOI V PEOPLE.

~. SERVING PEOPLE

lO

ATTACHMENT Re:

RII:JPO 50-335 IE BULLETIN 79-14 As of September 14, 1979, more than 1200 hangers/restraints have been inspected out of approximately 2200 hangers/restraints comprising the scope of the program.

During a September 4 - 5 outage, approxi-mately 150 "inaccessible" hangers in containment were inspected.

Of those hangers/restraints which have been inspected, fewer than 10 deviations have been identified that may result in physical modifications (non-conforming items).

These items are presently being analyzed to resolve the deviation, or develop the required modifica-tion.

During the scheduled plant outage for the week of September 23 (for feedwater pipe inspection per Bulletin 79-13) plans have been firmed to inspect approximately 350 normally inaccessible hangers inside containment representing the containment spray system.

The results of the inspections performed to date indicate less than a lX defect rate.

Based on the results of these inspections, Florida Power 8 Light Company requests deferral of the remaining normally inaccessible hangers/restraints until the scheduled Spring-1980 refueling outage.

Please respond to our deferral request by September 24, 1979, so that we will be able to facilitate our planning for the outage, which will have begun on September 23.