Letter Sequence Response to RAI |
---|
TAC:MF5298, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B (Approved, Closed) |
|
MONTHYEARL-14-106, License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b2014-03-25025 March 2014 License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b Project stage: Request L-14-271, Request for Licensing Action to Amend Technical Specification 3.8.4, DC Sources - Operating2014-11-24024 November 2014 Request for Licensing Action to Amend Technical Specification 3.8.4, DC Sources - Operating Project stage: Request ML15002A3262015-01-0909 January 2015 Acceptance Review Concerning Revision to Battery Surveillance Test Frequencies (TAC No. MF5298)(L-14-271) Project stage: Acceptance Review ML15103A0062015-04-0909 April 2015 NRR E-mail Capture - NRC Staff'S LIC-109 Acceptance Review Results for Turkey Point Unit 3 Relief Request No. 1, Revision 1 - 5th 10-Year ISI Interval Project stage: Acceptance Review ML15096A0512015-04-13013 April 2015 Unit, No. 1 - Request for Additional Information Concerning Battery Surveillance Test Frequencies Project stage: RAI L-15-146, Response to Request for Additional Information Re Request to Amend Technical Specification 3.8.4, DC Sources - Operating.2015-05-12012 May 2015 Response to Request for Additional Information Re Request to Amend Technical Specification 3.8.4, DC Sources - Operating. Project stage: Response to RAI ML15103A4022015-05-26026 May 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15222A5332015-08-10010 August 2015 Regulatory Audit in Support of Relief Request 1, Revised, for Fifth Ten-Year Inservice Inspection Interval Project stage: Other ML15231A3912015-08-17017 August 2015 NRR E-mail Capture - Request for Additional Information Re. Turkey Point Unit 3 Relief Request No. 1, Revision 1 for 5th ISI Interval Project stage: RAI ML15201A5292015-08-17017 August 2015 Issuance of Amendment Concerning Technical Specification 3.8.4 DC Sources - Operating (TAC No. MF5298) (L-14-271) Project stage: Approval L-2015-225, Inservice Inspection Plan - Fifth Inspection Interval Relief Request No. 1, Response to Request for Additional Information2015-09-15015 September 2015 Inservice Inspection Plan - Fifth Inspection Interval Relief Request No. 1, Response to Request for Additional Information Project stage: Response to RAI ML15271A3252015-10-14014 October 2015 Safety Evaluation for Relief Request No. 1, Revision 1 for Fifth 10-Year Inservice Inspection Interval - Repair of Pressurizer Stainless Steel Heater Sleeve Without Flaw Removal Project stage: Approval 2015-04-09
[Table View] |
Similar Documents at Perry |
---|
Category:Letter type:L
MONTHYEARL-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-049, Core Operating Limits Report for Operating Cycle 202023-03-30030 March 2023 Core Operating Limits Report for Operating Cycle 20 L-23-037, and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage L-23-085, 1 to Emergency Plan2023-03-10010 March 2023 1 to Emergency Plan L-23-057, Energy Harbor Nuclear Corp Retrospective Premium Guarantee2023-02-20020 February 2023 Energy Harbor Nuclear Corp Retrospective Premium Guarantee L-23-017, Mid-Cycle Revisions to the Core Operating Limits Report for Operating Cycle 192023-01-31031 January 2023 Mid-Cycle Revisions to the Core Operating Limits Report for Operating Cycle 19 L-22-271, Emergency Plan2022-12-20020 December 2022 Emergency Plan L-22-272, Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023)2022-12-16016 December 2022 Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023) L-22-263, Spent Fuel Storage Cask Registration2022-12-12012 December 2022 Spent Fuel Storage Cask Registration L-22-254, Emergency Plan for Perry Nuclear Power Plant, Including EAL Matrix Revision 222022-11-18018 November 2022 Emergency Plan for Perry Nuclear Power Plant, Including EAL Matrix Revision 22 L-22-250, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 192022-11-0808 November 2022 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 19 L-22-221, Supplement to Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-10-18018 October 2022 Supplement to Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position L-22-201, Submittal of Evacuation Time Estimates2022-09-12012 September 2022 Submittal of Evacuation Time Estimates L-22-050, Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual2022-08-0909 August 2022 Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual L-20-239, Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-08-0505 August 2022 Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position L-22-171, Response to Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-0632022-07-14014 July 2022 Response to Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 L-22-099, Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis2022-06-0101 June 2022 Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis L-22-104, Annual Radiological Environmental Operating Report2022-04-28028 April 2022 Annual Radiological Environmental Operating Report L-22-110, Response to Request for Additional Information Re 10CFR50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code Requirement2022-04-28028 April 2022 Response to Request for Additional Information Re 10CFR50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code Requirement L-22-105, Annual Radiological Effluent Release Report2022-04-27027 April 2022 Annual Radiological Effluent Release Report L-22-082, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-23023 March 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations L-22-056, Energy Harbor Nuclear Corp., Annual Notification of Property Insurance Coverage2022-03-22022 March 2022 Energy Harbor Nuclear Corp., Annual Notification of Property Insurance Coverage L-22-052, Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines2022-03-16016 March 2022 Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines L-22-073, Submittal of the Decommissioning Funding Status Report for Perry Nuclear Power Plant2022-03-16016 March 2022 Submittal of the Decommissioning Funding Status Report for Perry Nuclear Power Plant L-22-023, Retrospective Premium Guarantee2022-02-17017 February 2022 Retrospective Premium Guarantee L-21-280, 10 CFR 50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code Requirements2022-01-0505 January 2022 10 CFR 50.55a Request Number VR-12, Revision 0, Request for Relief from Containment Isolation Valve ASME OM Code Requirements L-21-282, Proposed Inservice Inspection Alternative IR-0632022-01-0505 January 2022 Proposed Inservice Inspection Alternative IR-063 L-21-259, 10 CFR 50.55a Requests Number VR-10 and VR-11, Inservice Valve Testing2021-12-28028 December 2021 10 CFR 50.55a Requests Number VR-10 and VR-11, Inservice Valve Testing L-21-287, Submittal of Revision 22 to Updated Safety Analysis Report (Supplement Letter)2021-12-20020 December 2021 Submittal of Revision 22 to Updated Safety Analysis Report (Supplement Letter) 2024-01-24
[Table view] |
Text
FENOCT Perry Nuclear Power Plant PO. Box 97 10 Center Road Perry, Ohio 44081 FirstEnergyNuclearOperatingCompany Ernest J. Harkness 440-280-5382 Vice President Fax: 440-280-8029 May 12, 2015 L-15-146 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 Response to Request for Additional Information Regarding a Request to Amend Technical Specification 3.8.4, "DC Sources - Operating" (TAC No. MF5298)
By correspondence dated November 24, 2014 (Accession No. ML14328A665),
FirstEnergy Nuclear Operating Company (FENOC) submitted a request to amend Technical Specification 3.8.4, "DC Sources - Operating," for the Perry Nuclear Power Plant.
By correspondence dated April 13, 2015 (Accession No. ML15096A051), the Nuclear Regulatory Commission (NRC) requested additional information to complete its review.
FENOC's response to this request is attached.
There are no regulatory commitments contained in this submittal. If there are any questions or additional information is required, please contact Mr. Thomas A. Lentz, Manager - Fleet Licensing, at (330) 315-6810.
I declare under penalty of perjury that the foregoing is true and correct. Executed on May P-, 2015.
Sincerely, Ernest J. Harkness
Attachment:
Response-to April 13, 2015 Request for Additional Information cc: NRC Region III Administrator NRC Resident Inspector NRC Project Manager Executive Director, Ohio Emergency Management Agency, State of Ohio (NRC Liaison)
ý- 6 61 Utility Radiological Safety Board tj fez
Attachment L-15-146 Response to April 13, 2015 Request for Additional Information Page 1 of 1 By correspondence dated November 24, 2014, FirstEnergy Nuclear Operating Company (FENOC) submitted a license amendment request for Nuclear Regulatory Commission (NRC) review and approval. By correspondence dated April 13, 2015, NRC staff requested additional information to complete its review. The requested information is presented below in bold type, followed by the FENOC response.
- 1. In Section 2.0 of the submittal dated November 24, 2014 (Agency Documents Access and Management System (ADAMS) Accession No. ML14328A665),
FENOC states:
[i]f the DC [direct current] batteries are the only available power source, the maintenance tie circuit breaker may be closed to allow the Unit I and Unit 2
[Class IE] batteries to be paralleled.
Address whether the impact of paralleling the Units I and 2 Class 1E batteries, such as contribution of additional short circuit current from the Unit 2 batteries, protection coordination, and protective devices ratings among other factors has been considered in the design of Unit 1,125 volts DC system.
Response
Yes, factors related to paralleling the Unit 1 and Unit 2 Class 1E batteries (for example, short circuit current, protection coordination, and protective device ratings) were considered in the design of the Unit 1, Class 1E, 125-volt DC battery system.