TAC:MF5798, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B (Approved, Closed) |
|
MONTHYEARL-14-106, License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b2014-03-25025 March 2014 License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b Project stage: Request L-14-271, Request for Licensing Action to Amend Technical Specification 3.8.4, DC Sources - Operating2014-11-24024 November 2014 Request for Licensing Action to Amend Technical Specification 3.8.4, DC Sources - Operating Project stage: Request ML15002A3262015-01-0909 January 2015 Acceptance Review Concerning Revision to Battery Surveillance Test Frequencies (TAC No. MF5298)(L-14-271) Project stage: Acceptance Review ML15103A0062015-04-0909 April 2015 NRR E-mail Capture - NRC Staff'S LIC-109 Acceptance Review Results for Turkey Point Unit 3 Relief Request No. 1, Revision 1 - 5th 10-Year ISI Interval Project stage: Acceptance Review ML15096A0512015-04-13013 April 2015 Unit, No. 1 - Request for Additional Information Concerning Battery Surveillance Test Frequencies Project stage: RAI L-15-146, Response to Request for Additional Information Re Request to Amend Technical Specification 3.8.4, DC Sources - Operating.2015-05-12012 May 2015 Response to Request for Additional Information Re Request to Amend Technical Specification 3.8.4, DC Sources - Operating. Project stage: Response to RAI ML15103A4022015-05-26026 May 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15222A5332015-08-10010 August 2015 Regulatory Audit in Support of Relief Request 1, Revised, for Fifth Ten-Year Inservice Inspection Interval Project stage: Other ML15231A3912015-08-17017 August 2015 NRR E-mail Capture - Request for Additional Information Re. Turkey Point Unit 3 Relief Request No. 1, Revision 1 for 5th ISI Interval Project stage: RAI ML15201A5292015-08-17017 August 2015 Issuance of Amendment Concerning Technical Specification 3.8.4 DC Sources - Operating (TAC No. MF5298) (L-14-271) Project stage: Approval L-2015-225, Inservice Inspection Plan - Fifth Inspection Interval Relief Request No. 1, Response to Request for Additional Information2015-09-15015 September 2015 Inservice Inspection Plan - Fifth Inspection Interval Relief Request No. 1, Response to Request for Additional Information Project stage: Response to RAI ML15271A3252015-10-14014 October 2015 Safety Evaluation for Relief Request No. 1, Revision 1 for Fifth 10-Year Inservice Inspection Interval - Repair of Pressurizer Stainless Steel Heater Sleeve Without Flaw Removal Project stage: Approval 2015-04-09
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23173A0812023-07-17017 July 2023 Supplement to Regulatory Audit Plan in Support of Review of License Amendment Request Supporting Digital Instrumentation & Control Modernization Project (EPID L-2022-LLA-0105) - Non-Proprietary ML22322A1812022-12-15015 December 2022 Audit Plan for Turkey Point Digital I&C License Amendment Request (Public Version) ML22321A3232022-11-18018 November 2022 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement ML22213A1172022-07-28028 July 2022 Regulatory Audit Plan in Support of Review of Defense in Depth and Diversity Evaluation (EPID L-2022-LLT-0002) - Non-Proprietary ML18232A5762018-08-21021 August 2018 Plan for On-Site Regulatory Audit Regarding the Subsequent License Renewal Application Review ML18173A0872018-07-0505 July 2018 Plan for the Irradiated Concrete Technical Issue Regulatory Audit Regarding the Subsequent License Renewal Application Review ML18178A1522018-07-0303 July 2018 in Office Regulatory Audit Plan Regarding Severe Accident Mitigation Alternatives in the Subsequent License Renewal Application Review ML18158A3352018-06-13013 June 2018 License Renewal Environmental Site Audit Regarding the Turkey Point Nuclear Generating Units 3 and 4 Subsequent License Renewal Application ML18136A8282018-06-0505 June 2018 Audit Plan and Setup of Online Reference Portal for License Amendment Request to Revise Technical Specifications to Address Non-Conservative Actions for Containment and Control Room ML18086A7052018-04-26026 April 2018 Plan for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16036A3072016-02-18018 February 2016 Regulatory Audit Plan in Support of the License Amendment Requests to Implement Risk-Informed Technical Specifications Initiative 4b ML15222A5332015-08-10010 August 2015 Regulatory Audit in Support of Relief Request 1, Revised, for Fifth Ten-Year Inservice Inspection Interval ML15188A5072015-07-0808 July 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 2023-08-03
[Table view] Category:Memoranda
MONTHYEARML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML22276A2302022-10-0606 October 2022 Summary of September 13, 2022, Public Meeting with FPL Concerning Supplemental Information Needed for Acceptance of License Amendment Request to Replace Instrumentation with Digital Systems on Turkey Point, Units 3 and 4 ML22238A3142022-08-0707 August 2022 Documentation of Approval for Longer Review Period for Turkey Point Digital Instrumentation and Control License Amendment Requests Acceptance Review ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21159A1352021-06-0808 June 2021 Public Meeting Summary Regarding the Saint Lucie Nuclear Plant, Units 1 and 2, Docket No. 50-335 and 389, and the Turkey Point Nuclear Generating Station Units 3 and 4, Docket No. 50-250 and 50-251; Meeting Number 20210505 ML20315A2642020-12-14014 December 2020 November 5, 2020, Summary of Drop-In Meeting with Nextera-Florida Power and Light to Discuss Pending Submittals Related to Digital Instrumentation and Controls and Improved Standard Technical Specifications ML20150A4732020-05-29029 May 2020 EOC Meeting Summary ML19330G0542019-11-22022 November 2019 Reconciliation - Analysis of EDO Response to ACRS Ltr - Response to ACRS Report on the Safety Aspects of the SLR Application of the Turkey Point Nuclear Generating Units 3 & 4 - December 2019 Fc Meeting ML19121A6072019-05-0101 May 2019 Summary of Public Meeting with Turkey Point Nuclear Plant to Discuss Annual Assessment of the Turkey Point Nuclear Plant with Public for Period of January 1, 2018 - December 31, 2018 ML18360A4452018-12-26026 December 2018 06/18/18 Summary of Interagency Meeting Related to Subsequent License Renewal for Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML18221A2652018-08-0909 August 2018 Referral Memorandum from the Secretary to the Atomic Safety and Licensing Board Panel ML18144A1242018-05-24024 May 2018 Summary of Public Meeting Concerning Annual Assessment of Turkey Point Nuclear Generating Station Unit 3 and Unit 4, for Period of January 1, 2017 December 31, 2017 ML18074A2522018-04-12012 April 2018 Status of Subsequent License Renewal Application ML17082A5102017-04-0606 April 2017 Verbal Authorization of Relief Request No. 5 for Repair of High Head Safety Injection Recirculation Test Line - Fifth 10-Year Inservice Inspection Interval ML18187A0332016-07-19019 July 2016 County Resolution to Seek a Commitment from FPL to Discontinue Use of the Cooling Canal System at the Turkey Point Power Plant ML16097A1402016-04-0404 April 2016 March 30, 2016, Summary of Public Meeting Turkey Point Nuclear Plant ML23333A0162016-03-0707 March 2016 Att H - MDC Report on Biscayne Bay Wq at Turkey Point CCS (March 4, 2016)-1 ML15222A5332015-08-10010 August 2015 Regulatory Audit in Support of Relief Request 1, Revised, for Fifth Ten-Year Inservice Inspection Interval ML14156A2212014-06-0404 June 2014 Public Meeting Summary - Turkey Point Nuclear Generating Station Docket Nos. 50-250 and 50-251 ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML1117101092011-06-22022 June 2011 Independent Spent Fuel Storage Installation Physical Security Plan and Verification of ASM Incorporation ML11160A0482011-06-10010 June 2011 Notice of Forthcoming Meeting with Florida Power & Light, to Discuss Turkey Point Extended Power Uprate License Amendment Request Currently Under Review ML1107405982011-03-16016 March 2011 Notice of Forthcoming Meeting with Florida Power & Light, Turkey Point, Units 3 & 4, to Discuss Extended Power Uprate License Amendment Request That Is Currently Under Review ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML1100704852011-02-0404 February 2011 Close-out of National Fire Protection Association Frequently Asked 07-0030 on Establishing Recovery Actions ML1031205002010-11-10010 November 2010 Notice of Forthcoming Teleconference with Florida Power & Light to Discuss Differences Between the Turkey Point Spent Fuel Pool Criticality Analysis License Amendment Request Currently Under Review & Draft Division of Safety Systems Interim ML1030502252010-11-0505 November 2010 Verbal Authorization of Relief Request No. 9, Visual Examination of Containment Liner Repair ML1030100892010-11-0505 November 2010 Verbal Authorization of Relief Request No. 8, Transfer Canal Drain Line Piping Repairs ML1025601362010-09-0707 September 2010 Notice of Meeting with Florida Power & Light Company to Discuss the Florida Power & Light Company'S Forthcoming Applications for the Extended Power Uprates of St. Lucie Units 1 & 2 and Turkey Point Units 3 & 4, Focusing on the Topic of Spen ML1019405202010-07-14014 July 2010 Notice of Conference Call with Florida Power and Light Company to Discuss Draft Responses to NRC Requests for Additional Information for Generic Letter 2004-02 ML1018806202010-07-0808 July 2010 Notice of Forthcoming Meeting with Florida Power & Light, to Discuss with Representatives of Florida Power & Light Company (FPL) the Turkey Point, Units 3 and 4 Proposed Extended Power Uprate License Amendment Request ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML1014501902010-05-26026 May 2010 Notice of Meeting with Florida Power & Light to Discuss the Turkey Point Alternative Source Term License Amendment Request That Is Currently Under Review ML1009105332010-04-0505 April 2010 U.S. Nuclear Regulatory Commission Staff Review of the Department of Homeland Security Consultation Reports ML1001900112010-01-19019 January 2010 Notice of Conference Call with Florida Power & Light Concerning Turkey Point Generic Letter 2004-02 Response ML1000800922010-01-0808 January 2010 Notice of Meeting with Florida Power & Light - Turkey Point Units 3 and 4, to Discuss Proposed License Amendment Request to Update Turkey Point Unit 3 Spent Fuel Pool Licensing Basis ML0934911442009-12-16016 December 2009 Summary of Category 2 Public Meeting with Nuclear Energy Institute to Discuss Health Physics Issues for New Reactors ML0925404602009-09-10010 September 2009 Summary of Phone Call with Industry to Issues Related to Eccentricity of the Steam Generator Tube-to-Tubesheet Joints in the Finite Element Model Used for the Technical Basis of the Permanent Alternate Repair Criteria License Amendment Requ ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy IR 05000250/20090032009-07-30030 July 2009 IR 05000250-09-003, 05000251-09-003, on 04/01/2009 - 06/30/2009; Turkey Point Nuclear Power Plant, Units 3 and 4; Equipment Alignment, Fire Protection, Maintenance Effectiveness, Plant Modifications, Refueling and Other Outage Activities ML0910302212009-04-13013 April 2009 Meeting Notice, Meeting with Florida Power & Light Company Turkey Point Nuclear Plant, Units 3 and 4 ML0832502332008-12-0202 December 2008 Summary of Public Meeting with Operators of Vogtle Units 1 & 2, San Onofre Units 2 & 3, St. Lucie Unit 1, Turkey Point Unit 3, Indian Point Units 2 & 3, Nuclear Energy Institute, and Alion Science and Technology ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0706400412007-03-0606 March 2007 Commitment Lists for Renewed Operating License (ROL) Plants with No Commitment Appendix Attached to Its ROL Sers/Nuregs for Use with IP-71003 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0614505922006-05-26026 May 2006 Wits 200600198 - Actions to Be Taken in Response to Hurricane Lessons Learned Task Report ML0518904892005-07-14014 July 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0506300702005-03-0202 March 2005 January Monthly Report on the Status of Open TIAs Assigned to NRR 2023-06-15
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 10, 2015 MEMORANDUM TO: Shana R. Helton, Chief Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Audrey. Klett; Project Manager ~---
Plant Licensing Branch 11-2
- Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
TURKEY POINT NUCLEAR GENERATING UNIT NO. 3-REGULATORY AUDIT IN SUPPORT OF RELIEF REQUEST 1, REVISED, FOR FIFTH TEN-YEAR INSERVICE INSPECTION INTERVAL (TAC NO. MF5798)
Staff from the U.S. Nuclear Regulatory Commission's (NRC's) Office of Nuclear Reactor Regulation, Division of Engineering and Division of Operating Reactor Licensing will conduct an audit to support its review of the Turkey Point Nuclear Generating Unit No. 3 Relief Request 1, Revision 1, for the fifth 10-year inservice inspection interval. The audit will occur at the Westinghouse Electric Company, LLC, office in Rockville, Maryland on August 11, 2015. The audit plan is enclosed.
Docket No. 50-250
Enclosure:
As stated
REGULATORY AUDIT PLAN BY THE OFFICE OF NUCLEAR REACTOR REGULATION TURKEY POINT NUCLEAR GENERATING UNIT NO. 3 DOCKET NO. 50-250
1.0 BACKGROUND
By application dated March 2, 2015 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML15077A213), Florida Power & Light Company (the licensee) submitted Relief Request No. 1, Revision 1, for the Fifth lnservice Inspection Interval.
The licensee needs the proposed alternative authorized by the NRC before its refueling outage in October 2015. The NRC staff needs to review proprietary calculations performed by the licensee's cor:itractor, Westinghouse Electric Company, LLC. The staff determined that the most efficient manner to review the calculations was to review them at the contractor's office in Rockville, Maryland.
NRR's Office Instruction LIC-111 (ADAMS Accession No. ML082900195) states that a regulatory audit is a planned, licensed or regulation-related activity that includes the examination of primarily non-docketed information with the intent to gain understanding, to verify information, or to identify information that will require docketing to support the basis of the licensing or regulatory decision.
2.0 REGULATORY AUDIT BASIS The staff will perform this audit to support its evaluation of whether the licensee's proposed alternative can be authorized per 10 CFR 50.55a.
3.0 REGULATORY AUDIT SCOPE OR METHODOLOGY The staff will review calculations used to support the conclusions in the licensee's application.
4.0 INFORMATION AND OTHER MATERIAL NECESSARY FOR THE AUDIT The staff intends to review the following information during the audit:
- Reference 16 to WCAP-17973-NP, Westinghouse Calculation Note, CN-MRCDA-14-27, Revision 0, "Turkey Point Units 3 and 4 Pressurizer Heater Sleeve Stress Analysis,"
January 29, 2015.
- Reference 17 to WCAP-17973-NP, Westinghouse Calculation Note, CN-PAFM-15-1, Revision 0, "Turkey* Point Units 3 and 4 Pressurizer Heater Sleeve Penetration Half-Nozzle Repair Flaw Evaluation, February 11, 2015.
- Four spreadsheets from CN-PAFM-15-1 (p. 25, 26, and 29 of CN-PAFM-15-1 references the spreadsheets):
Enclosure
o Allow Flaw Size_LEFM_IWB_3612 Path 6_ 14.xlsx o Allow Flaw Size_LEFM_IWB_3612 Path 7_15.xlsx o FCG_Ferritic_in_WaterPath6_ 14.xlsm o FCG_Ferritic_in_WaterPath7_15.xlsm
- For the stress analysis in CN-MRCDA-14-27, the output is in the form of computer runs with multiple output files. The staff will review Computer Runs 50 and 51, which each have numerous output files. The listing is on pages 44-48 for Computer Run 50 and on pages 48-49 for Computer Run 51.
The staff will also review other documents or spreadsheets that Westinghouse identifies as being important.
5.0 TEAM ASSIGNMENTS The audit team consists of Ms. Audrey Klett, the NRC's Project Manager for Turkey Point 3 and 4; Mr. Jeffrey Poehler, Senior Materials Engineer; and Mr. David Dijamco, Materials Engineer.
6.0 LOGISTICS The audit will occur at the Westinghouse Electric Company, LLC, offices in Rockville, Maryland on August 11, 2015. The staff plans to hold a brief entrance meeting at 10:00 am and a brief exit meeting by close of business the same day.
7.0 SPECIAL REQUESTS The staff requests the licensee and its contractor to have the information listed in Section 4 readily available and accessible for the staff's review. The staff also requests that cognizant licensee and contractor staff be available to answer any questions from the staff and to track staff questions during the audit. Licensee staff can be available by telephone. The staff also requests the licensee and its contractor to provide a reasonable working space for the audit period at the audit site and the audit documents in paper as well as electronically available in a text searchable format.
8.0 DELIVERABLES After the audit, the staff will develop any additional requests for information, which it will provide to the licensee. The staff will issue an audit report by September 30, 2015.
August 10, 2015 MEMORANDUM TO: Shana R. Helton, Chief Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office.of Nuclear Reactor Regulation FROM: Audrey Klett, Project Manager /RA/
Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
TURKEY POINT NUCLEAR GENERATING UNIT NO. 3-REGULATORYAUDIT IN SUPPORT OF RELIEF REQUEST 1, REVISED, FOR FIFTH TEN-YEAR INSERVICE INSPECTION INTERVAL (TAC NO. MF5798)
Staff from the U.S. Nuclear Regulatory Commission's (NRC's) Office of Nuclear Reactor Regulation, Division of Engineering and Division of Operating Reactor Licensing will conduct an audit to support its review of the Turkey Point Nuclear Generating Unit No. 3 Relief Request 1, Revision 1, for the fifth 10-year inservice inspection interval. The audit will occur at the Westinghouse Electric Company, LLC, office in Rockville, Maryland on August 11, 2015. The audit plan is enclosed.
Docket No. 50-250
Enclosure:
As stated DISTRIBUTION:
PUBLIC LPL2-2 R/F RidsNrrDeEvib Resource RidsNrrLABClayton Resource RidsNrrDorlLpl2-2 Resource RidsNrrPMTurkeyPoint Resource DDijamco, NRR JPoehler, NRR DE/EVIB/BC DORL/LPLll-2/BC DORL/LPLll-2/PM JMcHale SHelton AKlett 08/07/15 08/07/15 08/10/15 OFFICIAL RECORD COPY