IR 05000498/1985022
| ML20136G425 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 11/06/1985 |
| From: | Milhoan J, Parkhill R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
| To: | |
| Shared Package | |
| ML20136G423 | List: |
| References | |
| 50-498-85-22, NUDOCS 8511220345 | |
| Download: ML20136G425 (5) | |
Text
.
'
.-
B e
U.S. NUCLEAR REGULATORY COP #1ISSION OFFICE OF INSPECTION AND ENFORCEMENT
'
Division of Quality Assurance, Vendor, and Technical Training Center Programs Quality Assurance Branch
.
Report No.:
50-498/85-22 Docket No.:
50-498 Licensee:
Houston Light & Power Company Facility Name:
South Texas Project Unit 1
'
Inspection At:
Stone & Webster Engineering Corporation, Boston, MA Inspection Conducted:
October 15-17, 1985 Inspection Team Members:
Team Leader:
R.W. Parkhill, Inspection Specialist, IE Electrical /I&C:
S.V. Athavale Inspection Specialist, IE G. Morris, Consultant, WESTEC Services
/?9VA $ h l'/5~/r5~
R.W. Parkhill D&te Team Leader, IE
.
Approved by:
[ 7 Y~,
//
/J'~
,.
/EJamesL.Milhoan
'Da'te Section Chief Quality Assurance Branch, IE 8511220345 851118 PDR ADOCK 05000498 G
-
-
-
-
- -
- - - - -
-
-
-
-
- - -
-
-
-
-
- -
'
.
.
,
SOUTH TEXAS PROJECT - UNIT 1 INSPECTION OF AUDIT RESULTS; TASK-85-3 OCTOBER 15, 1985, THROUGH OCTOBER 17, 1985 1.
Background On March 1, 1984, representatives of Houston Lighting and Power Company (HL&P) presented to the NRC the details of the Engineering Assurance Program (EAP) being conducted on the South Texas Project (STP).
As a result of this meeting and additional information provided by HL&P, the NRC determined that this program, if properly implemented, could provide the additional assurances of design adequacy normally provided by an Independent Design Verification Program (IDVP).
Formal acceptance of the EAP as a substitute for an IDVP was provided via letter to HL&P dated August 20, 1984.
The NRC decided to monitor the STP Engineering Assurance Program in three phases for Task 85-1, Control Room HVAC, Task 85-2, Component Cooling Water System and Task 85-3, Offsite AC Power and Medium Voltage AC Power Supply Systems:
(1) implementation of program plan and procedures, (2) review and evaluation of audit results and (3) followup of corrective actions.
The first phase of inspection was accomplished at the headquarters of Stone and Webster Engineering Co. (SWEC) in Boston during the week of April 23, 1985.
The report of this inspection (No. 50-498/85-09) was forwarded to HL&P on July 12, 1985. The second phase of inspection for Tasks 85-1 and 85-2 was accomplished at SWEC's headquarters at Coston during July 22, 1985 through July 26, 1985 and report of this inspection (No. 50-498/85-14)
was forwarded to HL&P on August 28, 1985.
2.
Purpose The purpose of this inspection was to review and evaluate audit results for Task 85-3, Offsite AC Power and Medium Voltage AC Power Systems.
Specifically, the objectives of the inspection were:
(a) to verify that task 85-3 was performed in sufficient technical depth to achieve objectives of the EA program; (b) to verify that the background documentation supported the findings and conclusion of the reports and (c) to review the status of items identified by NRC in Inspection Reports No. 50-498/85-09 and 50-448/85-14 that relate to Task 85-,_
_-
-__
!
,
3.
Personnel Contacted:
The following is a brief list of key personnel contacted during this inspection:
Name Position R. A. Frazar HL&P EA Program Manager S. R. Basu HL&P EA Program staff C. R. Allen
-
HL&P Project Engineer G. D. Manasco HL&P Project Engineer D. Root HL&P Supervisor, Project Engineering A. Banerjee SWEC STP EA Project Manager
.
.
'
R. Matherwiez SWEC Electrical Engineer - Task Leader A. J. Murphy SWEC I/C Engineer - Task Leader S. F. Miller F. P. Walker Bechtel Senior Electrical Engineer SWEC Electrical Engineer H. E. McBreen SWEC Electrical Engineer K. J. Khunkhun R. Reed SWEC Electrical Engineer Jack Arden-SWEC/HL&P EA Program Staff SWEC I/C Engineer Doug Robinson W. Bonanno SWEC Senior Electrical Engineer SWEC I/C Engineer G. Gerth SWEC Electrical Systems 4.
General Comments There was evidence of substantial review by SWEC of design calcu-a.
lations, electrical diagrams (elementary, wiring, loops), logic diagrams, design specifications and other design documents.
<
In view of this review effort, the personnel interviewed (both HL&P and SWEC) and the number and type of deficiencies being uncovered by Engineering Assurance Program, the NRC inspection team is satisfied that Task 85-03 is acceptably completed, subject to the comments contained in this report.
b.
The two previous inspection reports associated with STP EAP, 50-498/85-09 and 50-498/85-14, closed various concerns based on SWEC's commitment to include item in their scope of review for Task 85-3.
The team reviewed these open items and was satisfied that SWEC had adequately addressed these items in their review of Task 85-3.
5.
Specific Comments In reviewing Task 85-3 the team identified the two following isolated concerns that will be reviewed as part of our inspection of corrective action for this task.
-
.
.
.
.
.
-
-
-
,
.
The SWEC review of calculation EC 5033, Protection of DC a.
System, failed to question the setting of the DC Bus breaker for the class 1E battery chargers.
These battery chargers are rated for 300 amperes DC.
The BEC calculations assumed a current limit for the charger output of 110% (330 amperes) and selected a breaker setting of 350 amperes.
The battery charger manufacturer's instruction manual indicates that the charger output will current limit in the 110 to 125% range.
A repro-duction of this instruction manual sheet was included as part of the calculation.
No production test data was reviewed by SWEC so that they could verify that the South Texas battery chargers would be limited to the lower current limit.
SWEC'could not complete their re.iew of calculation EC 5036, DC b.
Cable Sizing, because they had not reviewed all the backup information from BEC.
SWEC identified this as a Minor Concern (MC).
The team felt that this item should have been identified as Indeterminate (I) because information was lacking to permit SWEC to complete their review.
SWEC agreed to revise this to an I designation and to include the following cables in their review for adequate voltage drop.
1) DC feed to the Class 1E Inverters 2) Feeders to the Class 1E DC motor operated valves
.
b
e
,
.
J. H. Goldberg-3-DISTRIBUTJON:
DCS 016 7 j NRC PDR V local PDR '
QABReading/
,
i DQAVT Reading JMTaylor, IE v//
JGPartlow, IE
,
l GTAnkrum, IE JLM11hoan,IE/
I EVImbro,IEd RWParkhill, IE SVAthavale, E/
t l
HWang, IE WJDircks, DO /
i HRDenton, NRR /
PKadambi, NRR /
HThompson,NRR[
TMNovak, NRR V j WButler, NRR V /
EHylton,NRR /
AE00 Vj OELD v NMSS i
RES l
ACRS (10
NSIC\\/
l NTIS
,
Regional Administrators l
Regional Division Directors-l TSpeis, NRR v
,
ELJordan, IE V
'
JAxelrad, IE /
l TeamJ4 embers ', f l
HBoul OIA V
/
,
+u.wAA
,46.a s a
IE:QAVT:QAB IE:QAVT:QAB IE:QAVT:QAB IE:QAVT:QAB IE:QAVTQAB SVAthavale:my RWParkhill EVImbro et JLM11hoan GTAnkrum 11/5/
11/ 5 /85 11/c//85
/d/85 11/re/85 I
i.,
/
5