IR 05000461/1979005

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-461/79-05 on 790508-11.No Noncompliance Noted.Major Areas Inspected:Review Replacement Nozzle Inlet safe-ends & Procedures for safety-related Structures
ML19247A001
Person / Time
Site: Clinton Constellation icon.png
Issue date: 06/06/1979
From: Erb C, Knop R, Westcott H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19247A000 List:
References
50-461-79-05, 50-461-79-5, NUDOCS 7907261011
Download: ML19247A001 (9)


Text

.

.

U.S.' NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-461/79-05

'

Docket No. 50-461 License No. CPPR-137 Licensee:

Illinois Power Company 500 South 27th Street Decatur, 4L 62525 Facility Name:

Clinton Power Station Unit 1 Inspection At:

Clinton Site, Clinton Illinois Inspection Conducted-fC '/[),w. )n May-11, 1979

) /

.-

' /f / 7i Inspectors:

H. M. Wescott (lli h/ -

C. Erb

- b!6 79 i (

<!lC R.C. Knop,Chieh'

lyg

~<

&

Approved By:

Projects Section Inspection Summary Inspection on May 8-11, 1979 (Report No. 50-461/79-05)

Areas Inspected:

Review replacement nozzle inlet saf e-ends ; hTE results bioshield steel; review procedures and NDT for safety related structures; weld material control; IE Bulletins and 50.55e reports; allegations. The inspection involved 52 inspector-hours by two h7C inspectors.

Results:

Of the six areas inspected, no items of noncompliance or deviations were identifed.

424 144 7 0 072S g ( o,J [

.

DE_ TAILS Persons Contacted Principal Licensee Employees

  • G.

M. Brashear, Site Manager

,

  • R.

J. Canfield, Director, Construction

-

  • J. R. llampton, QA Supervisor, Site
  • D. Korneman, Supervisor, Mechanical Construction
  • J.

O. McHood, Vice President - Project Manager

  • J.

S. Spencer, Supervisor, Field Engineering

  • S. Unks, Supervisor, QA Baldwin Associates J. Jackson, Weld Material Issue
  • J. F. Linehan, Manager, QC
  • A. Selva, Manager, Q&T.S.
  • J. Smart, Senior QA Engineer
  • T. Walker, Senior QC Engineer
  • S.

G. Hall, Site QC

  • D.

B. Powell, Resident Site Manager G. Smoot, Technical Specialist Reactor Controls _Inc.

  • C. J. Garner, QC Supervisor
  • J. W. Mays, Installation Supervisor Bristol Steel Co.

A. Whigham, Supervisor QA Hartford Steam Boiler Insurance Co.

  • M.

J. Kin, Authorized Nuclear Inspector

  • Denotes those attending the exit interview.

424 145-2-

.

.

.

Licensee Action Previous Inspection Findings

.

(Open) Tm dealer Used in Safety Related Ventilation Ducts (461/79-01-01)

In a '

. con with S&L, the Standby Gas Treatment and Control room

. +ionsystemswereidentifiedasrequiringcompliancegoReg.

buide 1.52.

S&L further established g requirement of 2 x 10 rads for the Standby Gas System and 1 x 10 rads for the Control room system.

These requirements must be met by American Filter Co. and

,

Zack Co., who should submit qualification information in gaskets to be used in the above systems.

(Closed) Unresolved Item (461/78-06-01) Safety related Burady/ Husky straight cable tray resistance welds were not being touched up with a zine rich paint.

The inspector reviewed an interoffice memo (DES 35-79), dated May 1, 1979, subject:

" Cable Tray Installation Spot Weld Touch-up" which stated that "...all spot welds on Husky furnished cable trays, installed as safety related, shall be touched-up with a zine rich paint as specified in K-2999 form 1895-E."

Also, Baldwin Associate Supplier Quality Control Activity Report No. C8204.8, dated May 3, 1979, item 3.b specifies galvanized touch-up per S&L specification K-2980 Form 1895C paragraph 2.5.1 riel used by

, _.

vendor - Galvanox No.

1.

Project Procedures (BAP) PCR-52-79 dated May 8, 1979, approved May 9, 1979, implementing the touch-up.

In addition, S&L cable tray specification K2980 article 301.13 was amended to require touch-up of tray with zine rich paint at the vendor for all future orders.

(Closed) Unresolved Item (461/79-01-04) Calibration Procedure No.008 specified 150 to 350 F temperature for the weld rod hold ovens.

The inspector reviewed revision 3 dated May 10, 1979 to Procedure No. 008 that changed the minimum and maximum temperature to 250 F and 450 F per BTS-402 as required by the AWS.

(Closed) Qualification Papers for L2KDE Inspector (461/79-04-01)

During the last inspection, an inspector for Reactor Controls, Inc.

did not have his qualification record onsite. The inspector verified during this inspection, that his papers were in order and onsite.

-3-424 146

.

~

Section I

.

Prepared by C. W. Erb Reviewed by D. H. Danielson, Chief Engineering Support Section 2

,

Functional Areas Inspected 1.

Replacement Program For Recirculation Inlet Nozzle Safe Ends Fitup or welding is underway on 8 of the 10 safe ends. Eight of the 10 thermal sleeves which will attach the safe ends to the inlet pipes for the jet pumps are onsite.

Outboard end is prepped for welding but the other end is not so that the proper length can be established prior to prepping the inboard end.

The following Product Quality Certification (PQC'S) were examined.

PQC No.

Item Supplier Mat'l GG-211 Cons. Insert Ring Grinnell Inconel RR-ll4 Inlet Safe End Assoc. Pipe s.s. 316 spec.

& Eng.

RR-226 Thermal Sleeve Calif. Pacific 316L Fab.

Material certification, test results and deviations were included in the above PQC's.

The following weld procedure specifications were examined.

WPS No.

Materials Root W/8/8-0TS-2 Rev. I s.s. to s.s.

open butt W43/43-CTS-1 Rev. 3 Inconel to Inconel.

cons. insert W43/43-0TS-1 Rev. 1 Inconel to Inconel open butt W8/8-CTS-2 Rev.

s.s. to s.s.

cons. insert Process sheets for welding were stamped with hold points for ANI inspection and also indicated nonconforming situations together with the corrective action. An example of this was-4-424 147

.

FDDR-LHI-013-74 Rev. I which related to a burn through on a consumable insert, repaired by using a qualifie_d open butt procedure.

No item of noncompliance or deviations were identified.

2.

Feed Water Safe Ends and Control Rod Return Line Cap Four feedwater safe-ends were received in PQC-EE-339. These

-

were manufactured by Chicago Bridge & Iron Nuclear (CBIN) and two deviations were identified and accepted by the customer.

These were made of carbon steel to specification SA-508 class 1 and were buttered with inconel on one end and stainless steel on the other.

No radiography of finished welds had been made.

ASME Section III, 1974 edition, summer 1976 addenda is applicable to these safe ends.

The Control Rod Drive (CRD) return line cap is an inconel forging received on PQC-BB685. This material was procured to SB-166, Grade 600 and was manufactured by Coulter Steel Co.

ASMI Code Section III, 1974 edition, winter 1975 addenda is applicable to this part.

No items of noncompliance or deviations were identified.

3.

Safety Relief Valve (SRV) quenchers Drawing No. M27-1000-OlA Rev A was examined and indicates the 16SRV quenchers will be distributed 4 per quadrant. Each quencher will have 4 cross arms which will be about 5 feet above the suppression pool floor. While bracing will be to the floor, the materials or details of the bracing was not availatie.

This area will be examined on a future inspection.

Tne inspector en a previous inspection had noted considerable water on the tuppression pool floor under the protective layer of plywood.

The licensee has taken action to inspect the stainless steel floor and sample the water on a monthly basis.

Bal(win QC and the Central Lab are responsible for this activity, which should minimize any pitting problems.

No items of noncompliance or deviations were identified.

4.

Bio Shield Steel Welds Radiography The inside horizontal ring 1 to ring 2, identification M27RS591H has a weld about 1" thick. The inspector examined-5-424 148

.

.

12 radiographs which had an unground surface. The roughness and space between passes in some cases made evaluation difficult.

Close visual inspection together with the radiographs is necessary for evaluation. This weld was radiographed 100%. Identification M27RS61 weld was required to have a magnetic particle inspection of each layer. This was done to specification, VST-MTC-1 Rev 3 using a Model Y-6, SN111 equipment with 4" to 6" prod spacing. This weld was made to the requirements of

,

ASME Section III 1974 edition, 1975 addenda, paragraph NB5000.

Two Baldwin welding procedures N588-588-BA-L Rev 0 and N588-588-F-L are used to weld this structure.

N-588-588-F-L is qualified to Section IX for groove, socket and fillet welds in 588-C steel materials, Flux cored are welding (FCAW) shall be used for all layers when using a backing ring or strip.

Base filter r2re shall be to SFA5.20 and/or 5.20-69 or E70T-1.

The protective gas shall be welding grade Argon 75% and carbon dioxide 25% at a minimum flow of 35CFH. The N588-588--BAL-L is qualified for usage of GTAW and/or SMAW.

No items of noncompliance or deviations were identified.

-6-k2k

Section II

.

Prepared by H. M. Wescott Reviewed by R. C. Knop, Chief Projects Section s

1.

Weld Material Control The inspector reviewed weld material control as a result of two allegations tha' were made by a former emnloyee of Baldwin Associates Technical Services. The allegations are concerned with (1) issue of weld fillter material to nonqualified welders and (2) destroying weld rod issue slips.

The inspector reviewed records and interviewed personnel as follows:

a.

Randomly selected forty two (42) welders names and I.D.

numbers from " Weld Material Field Requistions" (Form BTS 030) located in the four " Weld Material Field Control Centers" and verified that all welders were qualified.

b.

Randomly selected five travelers from the records storage area. These travelers contained the welders I.D. and the serial numbers of the weld material field requisitions that identify the welder and the weld material used for a specific weld.

Following is a list of travelers selected.

(1) F-ISX-029-0105 (2) F-ISX-03BA30-C (3) F-ISX-BA30-E (4) F-ISX-03BB30 (5) F-ISX-10AA18-B Twenty three weld material field requisition numbers were randomly selected from the above travelers. The requisi-tions ranged in dates from September 1977 through February 1979. All were on file with the exception of one, (S/N A 0000-19047). The inspector verified that the welders name and I.D. corresponded to that on the traveller and further verified that the welders were qualified at the time the welding was performed.

424 150

~'~

.

.

c.

Review of Baldwin Associates " Procedure Specification for the Procurement, Storage, and Control of Welding Filler Material", BTS 402, Revision 12, dated April 6, 1979.

d.

Discussion with the Manager, Technical Services.

e.

Interview of the individual substituting in the weld material control center.

,

Comment, discussion and interviews established that in the event that a welder is absent from work or for some reason he did not pick up his assigned weld rod the weld rod was returned to the hold oven and the weld material field requisition was destroyed. Also, through discussion and reviewing welder qualification records, it was learned that many carpenters, electricians, pipe fitters and steel workers had been qualified to weld. This could pcssibly explain the allegations.

f.

Review of the alleger qualification records g.

Review of the qualification records of the individual substituting in the weld material control center.

No items ofnoncompliance or deviations were noted in this area of the inspection.

2.

IE Bulletins 50.55e Reports The inspector reviewed IE Bulletins at Illinois Power Company, Decatur, Illinois offices, as follows:

a.

78-01

"Flamable Contact Arm Retainers in GE CR102 Relays" 78-02

" Terminal Block Qualification" 78-04

" Environment Quality of Certain Stem Mounted Limit Switches Inside Reactor Containment" 78-05

" Malfunctioning of Circuit Breaker Auxiliary Contact Mech GE Model CR105X" 78-06

" Defective Cutler-Hammer Type 'M'

Relays with DC Coils" 78-10

"Bergen Patterson HYD Suppressor Accumulator Spring Coils" 79-02

" Pipe Support Base Plate Designs Using Concrete Anchor Bolts"

-8-424 151

,

b.

Two 50.55e r6 ports (1) Improper contrci of procunement piping, August

'

.

1977.

(2) Dryvell wall liner plate welding indications, January 1, 1979.

-

No items of noncompliance or deviations were noted in this area of the inspection.

Exit Inte rview The inspectors met with site staff representatives (denoted in the persons contacted paragraph) at the conclusion of the inspection on May 11, 1979. The inspectors summarized the scope and findings of the inspection.

The licensee acknowledged the findings.

424 152-9-