I .

-

.

,. .*=

APPENDIX A NOTICE OF VIOLATION Northeast Nuclear Energy Company Docket No. 50-423 Millstone Nuclear Power Station, Unit 3 License No. CPPR-113 During routine inspection 50-412/85-16, the following violation was identified in accordance with the NRC Enforcement Policy (10 CFR 2, Appendix C).

10 CFR 50, Appendix B, Criterion V and the Northeast Utilities Quality Assur-ance Topical Report, Revision 6, require that activities affecting quality be prescribed by appropriate procedure Contrary to the above, on April 3,1985, an activity affecting quality was not prescribed by appropriate procedures in that maintenance activities, con-ducted as authorized, resulted in flooding in a part of the Control Buildin This is a Severity Level IV Violation (Supplement II).

Pursuant to 10 CFR 2.201, Northeast Nuclear Energy Company is required to submit to this office, within thirty days of the date of this letter transmitting this Notice, a written reply including: (1) corrective steps taken and results achieved; (2) corrective steps to be taken; and (3) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending this response tim The reply directed by this Notice is not subject to clearance by the Office of Management and Budget as otherwise required by the Paperwork Reduction Act of 1980, PL 96-51 G O h 05000423 PDR