IR 05000390/2026010

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000390/2026010 and 05000391/2026010
ML26078A364
Person / Time
Site: Watts Bar  
(NPF-090, NPF-096)
Issue date: 03/20/2026
From: Christopher Even
NRC/RGN-II/DORS/EB1
To: Erb D
Tennessee Valley Authority
Shared Package
IR 2026010 List:
References
IR 2026010
Download: ML26078A364 (0)


Text

SUBJECT:

WATTS BAR NUCLEAR PLANT - NRC INSPECTION REPORT 05000390/2026010 AND 05000391/2026010

Dear Delson C. Erb:

On February 26, 2026, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Watts Bar Nuclear Plant and discussed the results of this inspection with William C. Reneau and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Christopher J. Even, Acting Chief Engineering Branch 1 Division of Operating Reactor Safety Docket Nos.: 05000390 and 05000391 License Nos.: NPF-90 and NPF-96

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000390 and 05000391

License Numbers:

NPF-90 and NPF-96

Report Numbers:

05000390/2026010 and 05000391/2026010

Enterprise Identifier:

I-2026-010-0025

Licensee:

Tennessee Valley Authority

Facility:

Watts Bar Nuclear Plant

Location:

Spring City, TN

Inspection Dates:

February 09, 2026 to February 26, 2026

Inspectors:

P. Alier, Reactor Inspector

P. Braaten, Senior Reactor Inspector

P. Braxton, Reactor Inspector

M. Carothers, Reactor Inspector

L. Day, Reactor Inspector

S. Hamilton, Resident Inspector

B. Stuckart, Reactor Inspector

Approved By:

Christopher J. Even, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a NRC inspection at Watts Bar Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP Section 03.01) (5 Samples)

For each component sample, the inspectors reviewed the licensing and design bases including:

(1) the Updated Final Safety Analysis Report (UFSAR);
(2) the Technical Specifications (TS); and
(3) the Technical Requirements Manual (TRM). The inspectors reviewed a sample of operating procedures (including normal, abnormal, and emergency procedures) and overall system/component health (including condition reports and operability evaluations, if any). The inspectors performed visual inspections of the accessible components to identify potential hazards and/or signs of degradation. Additional component specific design attributes reviewed by the inspectors are listed below.
(1) Control room heating, ventilation, and air conditioning system
  • Seismic and Structural Integrity
(2) Unit 1 480V shutdown board 1A1-A ( 1BD-212-A1-A)
  • Protection and coordination
  • Protective relays calibrations and breakers maintenance
(3) Unit 1 6.9kV shutdown board 1A-A ( 1-BD-211-A-A) and breakers
  • Protection and coordination
  • Protective relays calibrations and breakers maintenance
(4) Unit 1 safety injection
(5) Chemical volume and control system (high head injection portion)
  • Emergency operating procedures and abnormal operating procedures operational implementation

Modifications (IP Section 03.02) (2 Samples)

(1) WBN-21-074, Main steam dump valve control upgrade
(2) WBN-21-055-03/04/05/06/09, Pressurizer heater transformer replacements 10 CFR 50.59 Evaluations/Screening (IP Section 03.03) (7 Samples)
(1) WBN-24-075, Replace main control room A chiller oil pump starter
(2) WBN-20-1243-03, Emergency diesel generator governor actuators replacement
(3) WBN-18-255, Intake security upgrade
(4) WBN-19-759, Replace unit 1 inadequate core cooling monitor
(5) WBN-22-019-01/2, Replace 500kV feeder differential relay set
(6) WBN-21-074, Main stem dump valve control upgrade
(7) WBN-24-077, Main feed pump trip to bypass

Operating Experience Samples (IP Section 03.04) (1 Sample)

(1) OpE Smart Sample 2023/01 - Digital instrumentation and controls

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On February 26, 2026, the inspectors presented the NRC inspection results to William C. Reneau and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CDQ0000682022000000

NEDP-2-1

Anchorage Design For Category I Transformers in the

Auxiliary Building

EPMGRS022693

Evaluation of System 63 Safety Injection Pump Suction

Components for Increased System Design Pressure

Rev. 04

EPMIW052490

Air handling units structural integrity

05/31/1990

EPMJKJ013088

SIS Operating Modes

Rev. 10

EPMLCP110689

MCR normal and emergency pressurization equipment

performance adequacy

EPMSNM043092

Failure Modes and Effects Analysis for Safety Injection

System

Rev. 11

MDQ00106320060110

CCP, SIP, CSP, and RHR Pump NPSH Analysis

Rev. 5

NEDP-9-1(1-LUB-

TX17484S)

S/SQ Review/ Approval: Hitachi Energy USA Test Report

for Transformer Seismic Certification.

WBNAPS2032

Water Hammer Analysis of SIS Piping due to Check

Valve Closure on Pump Trip

Rev. 5

WBNOSG4095

Selection Criteria for Motor Operated Valves Requiring

Thermal Overload Bypass

Rev. 22

Calculations

WBNOSG4099

MODERATE ENERGY LINE BREAK FLOODING

STUDY (Flood Calculations Including Rooms 782-A1, -

A2, -A3 and -A4)

Corrective Action

Documents

CR 2008999

CR 2009000

CR 2034774

Condition Reports that specifically were a result from the

execution of the WOs for the WBN-21-055 Child Change

Packages.

CR 2066982

26 NRC CETI - Bolt on 1A SI Pump Shaft Shroud

Needs to be Tightened

2/10/2026

CR 2067005

26 CETI Inspection - Potential Leak on Threaded

Connection

2/10/2026

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 2067014

26 CETI Inspection - Capillary Tubing Needs Protected 02/10/2026

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR 2067180

26 NRC CETI Inspection - Oil Level High on 1A and

1B SI Pumps

2/11/2026

CR 2067263

26 NRC CETI - Vendor Manual WBN-VTD-P318-1430

has incorrect number in header

2/11/2026

CR 2067546

26 NRC CETI - Copper Wire NRC Identified

2/12/2026

CR 2067546 - Copper

Wire

CR 2067568

CR 2067584

Condition Reports for Loose Bolts found on 480 V

Transformers and Extra Pieces of Copper Conduit during

Plant Walkdown in Auxiliary building

CR 2067568

26 NRC CETI - Loose bolt on 2-DXF-68-341H

2/12/2026

CR 2067584

26 NRC CETI - Loose Bolts on 2-DXF-68-341A

2/12/2026

1-45W724-1

Wiring Diagram, 6900 Shutdown Board 1A-A

Rev. 35

1-45W749-1

Wiring Diagram, 480V Shutdown Board 1A1-A Single

Line

Rev. 69

Drawings

WBN-0-47E235-5-CC

006760411

Auxiliary Building Units 1 & 2 Environmental Data EL

2.0

WBN-0-2024-205-001

480 V Turbine Building Lighting Boards Temporary

Power Commercial Change Package.

WBN-055-03

WBN-055-04

WBN-055-05

WBN-055-06

WBN-055-09

Design Equivalent Change Packages: Child Packages for

WBN-21-055 Design Equivalent Change Package for

Replacement of 480 V Transformers (PZR HTR and Turb

Bldg Transformers).

Rev 1

WBN-18-255,

H.5

Intake Pumping Station Upgrades

Rev. 00

WBN-19-759

Design Change Package for Replacement of Unit 1

ICCM and 50.59 Screening.

WBN-20-1243

EDG Governor Annunciator Removal 1BB

Engineering

Changes

WBN-21-055

Design Equivalent Change Package, Parent Package:

Replacement of 480 V Transformers

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WBN-21-055 10CFR

50.59 Screening

SCREENING REVIEW/50.59 EVALUATION for ECP

WBN-21-055 Parent Package.

WBN-21-074

Main Steam Dump Valve Controls Upgrade

Rev. 02

WBN-22-019

Design Equivalent Change Package and 50.59

Screening

WBN-24-075

Replace MCR A Chiller Obsolete Oil Pump Motor Starter

PER 02-002116-000

Performance Evaluation Report for Oil Level Identification

and Resolution

2/20/2002

Engineering

Evaluations

Surveillance Test Risk-

Informed Documented

Evaluation (STRIDE)

STRIDE to Extend the Frequency for the Pressurizer

Heater Capacity Check Evaluation

CNL-20-016

(ML20174A546)

LAR Application to Modify WBN Unit 1 Tech Specs 3.3.3

PAMS (WBN-TS-19-23)

FAT-TVA-7495945

Factory Acceptance Test Report for WBN-21-074

Rev. 00

PR-WBN-21-055-01

PR-WBN-21-055-04

Procurement Requests for 480 V Transformers

WB-DC-30-28

Design Criteria Document - LOW AND MEDIUM

VOLTAGE POWER SYSTEMS

WBN-SDD-N3-63-4001

SIS QA Record

Rev. 41

WBN-VTD-A996-0010

Areva EOI 17, DS Breaker Reconditioning Process

Rev. 2

WBN-VTD-D245-0350

Operating & Maintenance Instructions for Dresser Pump

Division (Formerly Pacific Pumps) Model JHF Safety

Injection Pumps

Rev. 22

Miscellaneous

WBN-VTD-G080-0660

Magne-Blast Circuit Breaker 1200 AND 2000 Ampres

Rev. 8

0-GOI-7

Generic Equipment Operating Guidelines

Rev.16

0-MI-57.036

Electric Motor/Generator Replacement and Bearing

Maintenance

Rev. 06

Procedures

0-MI-57.036

Electric Motor/Generator Replacement and Bearing

Maintenance

Rev. 10

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-MI-57.036

Electric Motor/Generator Replacement and Bearing

Maintenance

Rev. 13

0-PI-OPS-1.0

Operator Aid Review Verification

Rev. 13

0-TI-100.006

Inservice Testing Program

Rev. 13

0-TI-78

Lubrication Program

Rev. 27

0-TI-SFCP-STI-WBN

Surveillance Test Interval (STI) Table

0032

1-AOI-15

Loss of Component Cooling Water

Rev. 09

1-AOI-20

Malfunction of Pressurizer Level Control System

Rev. 13

1-PI-OPS-1-AB_RW

Auxiliary Building / Radwaste AUO Work Station

Responsibilities

Rev. 24

1-SI-68-35 SI 18 /19 / 20 Surveillance Task Sheet (STS) Procedure 2-SI-68-35

PZR HTR Capacity (Surveillances: Completed every 18

months)

2-SI-68-35 SI 17 / 18 /

Surveillance Task Sheet (STS) for Procedure: 2-SI-68-

35, PZR HTR CAPACITY Surveillance (Conducted every

months)

E-0

Reactor Trip or SI

Rev. 35

E-1

Loss of Reactor or Secondary Coolant

Rev. 19

EAP-62-1

CVCS Emergency Abnormal Operations

Rev. 01

FR-S.1

Response to Nuclear Power Generation ATWS

Rev. 23

N3-30CB-4002

CONTROL BUILDING HEATING, VENTILATING, AIR

CONDITIONING, AND AIR CLEANUP SYSTEM

NEDP-5

Design Document Reviews

Rev. 16

NEPD-22

Operability Determinations and Functional Evaluations

Rev. 25

NISP-IP-ENG-001

Standard Design Process

Rev. 03

NPG-SPP-01.18

Emergent Issue Response and Resolution

Rev. 04

NPG-SPP-09.4

CFR 50.59 Evaluations of Changes, Tests, and

Experiments

Rev. 21

NPG-SPP-09.5

Temporary Modifications Temporary Configuration

Rev. 21

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Changes

OPDP-8

Operability Determination Process and Limiting

Conditions for Operation Tracking

Rev. 34

P.S.4.M.1.5

CLASSIFICATION, PROCUREMENT, RECEIPT AND

USE OF LUBRICANTS

Rev. 10

SDD-N3-68-4001 DOC

000050

System Description Document

REACTOR COOLANT SYSTEM: Unit 1 / Unit 2: QA

Record

0050

TVA-NQA-PLN89-A

Quality Assurance Program Description for

TVA Nuclear

Rev. 45

Shipping Records MEL-WBN-21-055-03-R

MEL-WBN-21-055-04-R

MEL-WBN-21-055-05-R

MEL-WBN-21-055-06-R

MEL-WBN-21-055-09-M

Component Update Requests for Transformer

Procurements.

21461932

Diesel generator engine inspection

04/19/2021

24969146

1-SI-63-901-B SAFETY INJECTION PUMP 1B-B

QUARTERLY PERFORMANCE TEST

09/19/2025

24969258

-SI-63-901 -A SAFETY INJECTION PUMP 1A-A

QUARTERLY PERFORMANCE TEST

09/09/2025

25690389

High Vibrations on CCP Room Cooler 2B-B

10/20/2025

Various

2771532, 121491708, 122772792, 121492327,

2772851, 124557984, 125146661, 120291038,

114561749, 120291045, 119825474, 122993817,

23119793, 124400950, 125186181, 121851494,

21659812, 125815273

Work Orders

WBN-21-055 Routine

WOs

WO 123852896 WBN-21-055, MOE, PMT TURN BLDG

Lighting BD TRANS 1

WO 123199641 WBN-21-055-06, MOE, PMT, PRESS

HTR, BACKUP GRP TRANS 2C

WO 123199637 WBN-21-055-05, MOE, PMT, PRESS

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HTR CONT GRP TRANS 2D

WO 123199633 WBN-21-055-04, MOE, PMT, PRESS

HTR BACKUP GRP TRANS 2B-B

WO 123199629 WBN-21-055-03, PMT, PRESS HTR

BACKUP GRP TRANS 2A-A

Site Acceptance Tests for Child Design Change

Packages.