IR 05000373/2004006

From kanterella
Jump to navigation Jump to search
IR 05000373-04-006 & 05000374-04-006, on 03/08/2004 Through 03/12/2004, for Exelon Generation Co. LLC, LaSalle County Station; Emergency Preparedness Specialist Report
ML040820839
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 03/19/2004
From: Kenneth Riemer
Division of Reactor Safety III
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-04-006
Download: ML040820839 (13)


Text

rch 19, 2004

SUBJECT:

LASALLE COUNTY STATION, UNITS 1 AND 2 NRC EMERGENCY PREPAREDNESS INSPECTION REPORT 05000373/2004006(DRS); 05000374/2004006(DRS)

Dear Mr. Crane:

On March 12, 2004, the NRC completed an inspection at your LaSalle County Station. The enclosed report documents the inspection findings, which were discussed on March 12, 2004, with Mr. G. Barnes and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, this inspection focused on emergency preparedness, including your staffs determinations of performance indicators for the Emergency Preparedness Cornerstone.

On the basis of the results of this inspection, no findings of significance were identified.

In accordance with 10 CFR Part 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Kenneth Riemer, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure: Inspection Report 05000373/2004006(DRS);

05000374/2004006(DRS)

See Attached Distribution

SUMMARY OF FINDINGS

IR 05000373/2004006(DRS) and 05000374/2004006(DRS); 03/08/2004 - 03/12/2004; LaSalle

County Station; Emergency Preparedness Specialist Report.

The report covers a one-week baseline inspection by two regional emergency preparedness inspectors and a resident inspector. The inspection focused on the Emergency Preparedness Cornerstone in the Reactor Safety strategic performance area during the biennial emergency preparedness exercise. This inspection also included a review of records related to the three emergency preparedness performance indicators for the period April 1, 2003 through December 31, 2003. No findings of significance were identified.

The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A. Inspector-Identified and Self-Revealed Findings None.

Licensee-Identified Violations

None.

REPORT DETAILS

REACTOR SAFETY

Cornerstone: Emergency Preparedness

1EP1 Exercise Evaluation

a. Inspection Scope

The inspectors reviewed the March 2004 biennial emergency preparedness exercises objectives and scenario to ensure that the exercise would acceptably test major elements of the licensees emergency plan and to verify that the exercises simulated problems provided an acceptable framework to support demonstration of the licensees capability to implement its plan. The inspectors also reviewed a summary of an emergency preparedness drill, which was conducted in February 2004, to determine whether that scenario was sufficiently different from the scenario used in the March 10, 2004 exercise.

The inspectors evaluated the licensees exercise performance, focusing on the risk-significant activities of emergency classification, notification, and protective action decision making, as well as implementation of accident mitigation strategies in the following emergency response facilities:

  • Control Room Simulator (CRS);
  • Operations Support Center (OSC); and
  • Emergency Operations Facility (EOF).

The inspectors also assessed the licensees recognition of abnormal plant conditions, transfer of responsibilities between facilities, internal communications, interfaces with offsite officials, readiness of emergency facilities and related equipment, and overall implementation of the licensees emergency plan.

The inspectors attended post-exercise critiques in the TSC, OSC, and EOF to evaluate the licensees initial self-assessment of its exercise performance. The inspectors later met with the licensees lead exercise evaluators to obtain the licensees refined assessments of its exercise participants performances. These self-assessments were then compared with the inspectors independent observations and assessments to assess the licensees ability to adequately critique station performance during the exercise.

b. Findings

No findings of significance were identified.

1EP4 Emergency Action Level and Emergency Plan Changes

a. Inspection Scope

The inspectors reviewed Revision 15 of the Exelon Nuclear Standardized Emergency Plan to determine if changes identified in this revision reduced the Plans effectiveness for the licensees operating nuclear stations in Illinois, pending on-site inspection of the implementation of these changes.

b. Findings

No findings of significance were identified.

OTHER ACTIVITIES

4OA1 Performance Indicator (PI) Verification

a. Inspection Scope

The inspectors reviewed the licensees records associated with each of the three emergency preparedness PIs to verify that the licensees program was implemented consistent with the industry guidelines in Nuclear Energy Institute publication No. 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 2, and related licensee procedures. Specifically, licensee records related to the performance of the Alert and Notification System (ANS), key Emergency Response Organization (ERO)members drill participation, and Drill and Exercise Performance (DEP) were reviewed to verify the accuracy and completeness of the PI data submitted to NRC for the period from April 2003 through December 2003. The following PIs were reviewed:

Common

  • ERO Drill Participation; and
  • Drill and Exercise Performance.

b. Findings

No findings of significance were identified.

4OA6 Meetings

.1 Exit Meeting

An exit meeting was conducted for:

  • Emergency Preparedness with Mr. G. Barnes and other members of licensee management and staff at the conclusion of the inspection on March 12, 2004.

The licensee acknowledged the information presented. No proprietary information was identified.

.2 Public and Media Briefing

  • On March 12, 2004, an inspector summarized the NRCs preliminary conclusions on the licensees exercise and critique performances at a public and media briefing hosted by Federal Emergency Management Agency staff in Ottawa, Illinois.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

G. Barnes, Site Vice President
L. Coyle, Operations Director
D. Czufin, Engineering Director
J. Eggart, Emergency Preparedness Coordinator
S. Fatora, Radiation Protection Department Manager
A. Ferko, Nuclear Oversight Manager
B. Kapellas, Radiation Protection Manager
B. Lindsy, Acting Training Director
S. Marik, Shift Operations Supervisor
S. McCain, Corporate Emergency Preparedness Manager
D. Rhodes, Work Management Director
W. Riffer, Emergency Preparedness Manager

Illinois Emergency Management Agency

J. Yesinowski, Resident Inspector

LIST OF ITEMS

OPENED, CLOSED AND DISCUSSED

Opened and Closed

None.

Discussed

None.

LIST OF DOCUMENTS REVIEWED