Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
Text
UNITE D S TATE S NUC LEAR RE GULATOR Y C OMMI S SI ON ary 23, 2014
SUBJECT:
DIABLO CANYON POWER PLANT - TEMPORARY INSTRUCTION 2515/186, "INSPECTION OF PROCEDURES AND PROCESSES FOR RESPONDING TO POTENTIAL AIRCRAFT THREATS"; INSPECTION REPORT NO. 05000275/2013405 AND 05000323/2013405
Dear Mr. Halpin:
On January 14, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Diablo Canyon Power Plant facilities using Temporary Instruction 2515/186, Inspection of Procedures and Processes for Responding to Potential Aircraft Threats. The enclosed inspection report documents the results of the inspection, which were preliminarily discussed on November 21, 2013, with you and other members of your staff. After discussing the results with the Office of Nuclear Security and Incident Response (NSIR) and the Office of Nuclear Reactor Regulation (NRR), exit communications were completed on January 14, 2014.
The objective of this inspection was to assess the implementation procedures and processes of the Diablo Canyon Power Plant that are required by Title 10 of the Code of Federal Regulations (CFR) 50.54(hh)(1), which provides the requirements for responding to a potential aircraft threat. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States, will be used to evaluate the U.S.
nuclear industrys readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted.
The inspection examined activities conducted under your license as they relate to the implementation of 10 CFR 50.54(hh)(1), your compliance with the Commissions rules and regulations, and with the conditions of your operating licenses. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel. Based on results of this inspection, no NRC-identified or self-revealed findings were identified.
Two observations related to basis documentation for site procedures were identified by the inspectors which required additional clarification and attention by the licensee. The observations were of very low safety significance and were determined not to be violations of regulatory requirements.
If you contest any finding or the subject in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Diablo Canyon Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1).
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Should you have any questions regarding this inspection, we will be pleased to discuss the issues with you.
Sincerely,
/RA/
Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety Docket No. 50-275, 50-323 License No. DPR-80, DPR-82 Nonpublic Enclosure:
Inspection Report 05000275/2013405 and 05000323/2013405 w/Attachment:
Supplemental Information cc: Electronic Distribution for Diablo Canyon ML14024A690 Cover Letter Only ML Non Sensitive Publicly Available VGG SUNSI Review Complete Sensitive SDH Non-Publicly Available Entire Report ML Non Sensitive Publicly Available Keyword: Sensitive SDH Non-Publicly Available VGG MD 3.4 Non-Public A.3 OE:OB SOE:OB C:DRP/A C:OB SHedger COsterholtz WWalker RDA for VGaddy
/RA/ /RA/ /RA/ /RA/
1/16/14 1/22/14 1/22/14 1/23/14