August 29, 2016

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 -

MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION

REPORT 05000317/2016405 AND 05000318/2016405

Dear Mr. Hanson:

On August 11, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Calvert Cliffs Nuclear Power Plant, Units 1 and 2. The inspection covered one of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on August 11, 2016, with Mr. George Gellrich, Site Vice President, and other members of your staff.

The inspection examined activities conducted under your licenses as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your licenses.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings were identified.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(3)(1) and its disclosure to unauthorized individuals

Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, the transmittal document is decontrolled. could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-317 and 50-318 License Nos. DPR-53 and DPR-69

Nonpublic Enclosure:

Inspection Report 05000317/2016405 and 05000318/2016405 w/Attachment: Supplemental Information

cc w/o encl; w/o OUO-SRI: Distribution via ListServ

cc w/encl; w/OUO-SRI T. Young, Director, Nuclear Security T. Levering, Director, Emergency Preparedness Planning

ML16243A053 (Cover letter)

ADAMS ACCESSION NUMBER: ML16243A047 (Cover letter w/enclosure)

Cover Letter:

SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available Cover Letter w/ Enclosure:

SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRS RI/DRP RI/DRS

NAME EBurket ADimitriadis MGray

DATE 8/18/16 8/23/16 8/29/16 Letter to Mr. Bryan Hanson from Mel Gray dated August 29, 2016

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 -

MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION

REPORT 05000317/2016405 AND 05000318/2016405

Distribution w/o encl; w/o OUO-SRI: (via E-mail)

DDorman, RA

DLew, DRA

MScott, DRP

DPelton, DRP

RLorson, DRS

PKrohn, DRS ADimitriadis, DRP ARosebrook, DRP RClagg, DRP, SRI CRoettgen, DRP, RI CFragman, DRP, AA JBowen, RI OEDO

RidsNrrPMCalvertCliffs Resource RidsNrrDorlLpl1-1 Resource ROPReports Resource

Distribution w/encl; w/OUO-SRI CJohnson, NSIR NSimonian, NSIR EWharton, NSIR BDesai, DRS, RII SOrth, DRS, RIII

MHaire, DRS, RIV

EBurket, DRS MGray, DRS ADimitriadis, DRP RClagg, DRP, SRI GTuttle, NMSS JRubenstone, NMSS