IR 05000269/2019013

From kanterella
(Redirected from IR 05000287/2019013)
Jump to navigation Jump to search
NRC Temporary Instruction 2515/194 Open Phase Condition Inspection Report 05000269/2019013 and 05000270/2019013 and 05000287/2019013
ML19318G943
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 11/14/2019
From: Steven Rose
NRC/RGN-II
To: Burchfield J
Duke Energy Carolinas
Archer L
References
IR 2019013
Download: ML19318G943 (11)


Text

November 14, 2019

SUBJECT:

OCONEE NUCLEAR STATION - NRC TEMPORARY INSTRUCTION 2515/194 OPEN PHASE CONDITION INSPECTION REPORT 05000269/2019013 AND 05000270/2019013 AND 05000287/2019013

Dear Mr. Burchfield,

Jr.:

On October 10, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station Units 1, 2, and 3 and discussed the results of this inspection with Mr.

Paul Fisk and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Steven D. Rose, Chief Construction Inspection Branch 2 Division of Construction Oversight

Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000269, 05000270 and 05000287

License Numbers:

DPR-38, DPR-47 and DPR-55

Report Numbers:

05000269/2019013, 05000270/2019013 and 05000287/2019013

Enterprise Identifier: I-2019-013-0008

Licensee:

Duke Energy Carolinas, LLC

Facility:

Oconee Nuclear Station

Location:

Seneca, SC

Inspection Dates:

October 07, 2019 to October 10, 2019

Inspectors:

G. Crespo, Sr. Construction Inspector

Approved By:

Steven D. Rose, Chief

Construction Inspection Branch 2

Division of Construction Oversight

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an NRC Temporary Instruction 2515/194 Open Phase Condition Inspection at Oconee Nuclear Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

This inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession No.

ML17137A416), dated October 31, 2017. The inspectors reviewed the licensees implementation of Nuclear Energy Institute (NEI) voluntary industry initiative (VII) in compliance with Commission guidance. The inspector discussed the licensees open phase condition system design and ongoing implementation plans with plant staff. The inspectors reviewed licensee documentation, vendor documentation, and performed system walkdowns to verify that the installed equipment was supported by the design documentation. These reviews were also made to determine if the licensee had completed the installation and testing of equipment, installed and tested alarming circuits both local and in the control room, and analyzed potential impacts associated with the design implementation on the current licensing basis. The inspectors reviewed the status of indication lamps in the front of the individual system cabinets to verify the status of the system tripping functions. These tripping functions of the system had not been activated or wired to date pending resolution of decision if to activate the function.

The objective of TI 2515/194 was to verify that licensees had appropriately implemented the NEI VII (ADAMS Accession No. ML15075A454), dated March 16, 2015, including updating their licensing basis to reflect the need to protect against OPCs.

Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01) (1 Sample)

(1) Temporary Instruction 2515/194-03.01 - VII (Part 1)

Oconee Nuclear Station, Units 1, 2, and 3 selected the open phase detection system designed and manufactured by Power System Sentinel Technologies, LLC. At the end of this inspection, the system remained in the monitoring mode of operation to facilitate continued data gathering of grid perturbations for evaluation of alarm and trip setpoints. The equipment was installed on start-up transformers CT-1, CT-2, CT-3, CT-5 and the Keowee Main Step Up (KMSU). The licensee is scheduled to transition the open phase detection system to full implementation including trip functions, if so decided, by December

INSPECTION RESULTS

Assessment 2515/194 Detection, Alarms, and General Criteria: TI 2515/194-03.01 - VII (Part 1)

Based on discussions with the licensee staff, review of available design, testing, grid data monitoring results documentation, and walkdowns of installed equipment, the inspectors had reasonable assurance the licensee appropriately implemented the VII. The inspectors determined:

(1) Open phase conditions will be detected and alarmed in the control rooms on the 1SA14 common annunciator panel for CT-1, 2SA14 common annunciator panel for CT-2, 3SA19 common annunciator panel for CT-3, SA8 common annunciator panel for CT-5, and Keowee Transformer #1 common annunciator panel for Keowee KMSU.
(2) Detection circuits will be sensitive enough to identify an open phase condition for all credited loading conditions for installed equipment.
(3) No Class-1E circuits were being replaced with non-Class 1E circuits in the design.
(4) The updated final safety analysis report (UFSAR) has been prepared to discuss the design features and analyses related to the effects of, and protection for, and open phase condition (OPC) design vulnerability.

Assessment 2515/194 Protective Actions Criteria: TI 2515/194-03.01 - VII (Part 1)

Based on discussions with the licensee staff, review of available design, testing, grid data monitoring results documentation, and walkdowns of installed equipment, the inspectors had reasonable assurance the licensee appropriately implemented the VII. The inspectors determined:

(1) Five transformers were susceptible to an open phase condition and the licensee had installed detection and mitigating equipment for all five.
(2) With an open phase condition present and with or without an accident condition signal, the open phase design would not adversely affect the function of important-to-safety systems, structures, or components. The licensees open phase condition design solution added two Power System Sentinel Technologies systems on the start-up transformers CT-1, CT-2, CT-3, CT-5 and KMSU. The trip function, if and when enabled, will provide an additional input to the associated transformer output breakers and input switches to CT-5. The credited plant response is unaffected and will be the same regardless of the conditions that generated the trip of the transformer output breakers.

Assessment 2515/194 Detection, Alarms, and General Criteria Exceptions: TI 2515/194-03.01 - VII (Part 1)

The inspectors identified the following exceptions to the Temporary Instruction criteria resulting from the operating status of the design modifications:

(1) The licensees design was operating in the monitoring mode with already established setpoints and gathering data to ensure the open phase condition design and protective schemes would minimize mis-operation, or spurious actions in the range of voltage unbalance normally expected in the transmission system. The licensee developed engineering calculations applied to the open phase detection and protection (OPDP) system to protect important-to-safety equipment during an open phase condition. These calculations are included in calculations OSC-11621, Oconee Nuclear Station Open Phase Vulnerability Analysis, Rev 003 and OSC-4300, (ELEC) Protective Relay Settings, Rev. 034.
(2) A draft of the proposed changes to the Units 1, 2, and 3 and Keowee Hydro Generating Plant UFSARs were available for the inspectors review and included information related to open phase conditions that describe the functions of the OPDP system.

Assessment 2515/194 Protective Actions Criteria Exceptions: TI 2515/194-03.01 - VII (Part 1)

The inspectors identified the following exceptions to the Temporary Instruction criteria resulting from the operating status of the design modifications:

(1) The licensees open phase condition design solution uses Power System Sentinel Technologies systems to detect, alarm, and provide a trip signal input to the associated startup transformers CT-1, CT-2, and CT-3, KMSU, and the 100 kV Auxiliary Transformer CT-

5. Upon open phase trip signal, if enabled, the existing undervoltage relays would operate to

initiate starting of the alternate power sources to restore power to the bus.

The trip function input to the transformer load side breakers have not been installed and remained deactivated and disconnected during the onsite system implementation inspection and that design function was not able to be demonstrated.

(2) Periodic tests, calibrations, setpoint verifications or inspections (as applicable) have been established for system operations at present. The surveillance requirements have been maintained for the plant technical specifications (TSs) in compliance with the provisions of 10 CFR 50.36.

Observation: OPC NRC Inspection Comments 2515/194 The inspectors identified the following observations:

(1) The trip function capabilities for all OPDP systems on CT-1, CT-2, CT-3 and KMSU have not been enabled by the positioning of the OPDP cabinet trip output knife switches (FT1-1 and FT1-2) and by missing final connections to the transformer output breaker trip signal wiring not run into 4.16kV switchgear specific breaker compartments.
(2) During the NRC inspection, testing had been performed by the transmission line system controllers, which caused a 230 kV and 100 kV lines disturbance that propagated throughout the grid system and caused:

a) Open Phase Detection Protection system alarms in both channels of CT-1 and CT-2.

b) Open phase Alarm Lockout Relay in channel 2 on CT-3.

c) Open phase Alarm Lockout Relay in channel 1 on KMSU.

d) Injection abnormal alarm light of channels 1 and 2 on CT-5.

All alarms were reset after operations was able to investigate and establish the alarms were not an actual open phase condition at the site.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2515/194

Calculations

OSC-11621

Oconee Nuclear Station Open Phase Vulnerability Analysis

Rev. 003

OSC-11632

Evaluation of Oconee Keowee Motor Protective Device Trip

Times During Open Phase Conditions

Rev. 000

OSC-11665

Evaluation of Oconee Motor Protective Device Trip Times

During Open Phase Conditions

Rev. 001

OSC-11804

Evaluation of Oconee Motor Protective Device trip Times

During Open Phase Conditions

Rev. 001

OSC-4300

(ELEC) Protective Relay Settings

Rev. 034

Corrective Action

Documents

2198906

Unit 3 Start-Up Transformer (CT3) Open Phase Protection

Equipment Installation & Tie-Ins (EC 407343)

Rev. 003

2199933

Unit 1 Start-Up Transformer (CT1) Open Phase Protection

Equipment Installation & Tie-Ins (EC 407344)

Rev. 002

219641

Transformer (CT5) Open Phase Protection Equipment

Installation & Tie-ins

Rev. 000

230308

Unit 2 Start-Up Transformer (CT2) Open Phase Protection

Equipment Installation & Tie-Ins (EC 408968)

Rev. 004

232693

Open Phase OE - Vendor issue requires a change in design

09/24/2019

287757

CT1 Channel 2 Open Phase Trouble Alarm

08/20/2019

288239

Open Phase Setting Adjustments based on AR 02287320

08/22/2019

289311

Keowee Open Phase High Temp Alarm

08/28/2019

290657

CT2 Open Phase Trouble Common Alarm In

09/07/2019

295815

2019 NRC TI-194 OPP - Drawing Change to O-700

10/07/2019

296030

Open Phase Relay Alarms Received CT1, CT2, CT3, CT5,

and KHU

10/08/2019

296110

No guidance in the ARG's to reset invalid Open Phase

alarms

10/09/2019

Drawings

K-0700

One Line Diagram - Relays & Meters - 13.8 to 230 kV

Rev. 044

KEE-0017-01-A

Elementary Diagram Transformer Differential (Keowee Hydro

Station)

Rev. 3A

O-0700

One Line Diagram - Relays & Meters - 19 kV

Rev. 039

O-0800-E

One Line Diagram AC Elementary Diagram 3 Line Conn.

Diag. Transf. Nos. CT5 & OCB, #101

Rev. 020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

O-1700

One Line Diagram - Relays & Motors - 19 kV

Rev. 040

O-2700

VTO One Line Diagram - Relays & Meter 19 kV

Rev. 030

OEE-71-1A

Elementary Diagram Start-Up Transf. No. CT2 Diff. Lock-Out

Rev. 8C

OEE-71-3

Elementary Diagram Contact Development Start-Up Transf.

No. CT3 Diff. Lock-Out

Rev. 13C

OEE-71-A

Elementary Diagram Start-Up Transf. No. CT1 Diff. Lock-Out

Rev. 5C

OEE-79-1

Elementary Diagram Transf. No. CT5 Diff. Lockout

Rev. 5C

Engineering

Changes

EC 404830

30 Figure 1. CT5 OPP Power Supply One Line

Rev. 003

EC 404830

34 Short Circuit Analysis

Rev. 003

EC 410355

Keowee Open Phase Protection Equipment Installation &

Tie-Ins

Rev. 010

EC 411894

CT5 Open Phase UPS

Rev. 003

EC 411894

Figure 1 - Simplified One-Line of the OPP System Power

Circuit (Attachment 5)

Rev. 001

Miscellaneous

EC 404830

UFSAR Markup Chapter 8 (Section 8.2.2 - CT5)

Rev. 000

IEGR-MN-1602

Analog Open Phase Protection (OPP) System Operating and

Maintenance Manual Oconee

11/28/2018

OSC -11739

ONS Unit 3 Startup Transformer (CT3) Open Phase

Protection (OPP) Failure Modes and Effects Analysis

(FMEA) and Single Failure Analysis (SFA)

Rev. 002

OSC-11664

ONS Unit 2 Startup Transformer (CT2) Open Phase

Protection (OPP) Failure Modes And Effects Analysis

(FMEA) And Single Failure Analysis (SFA)

Rev. 002

OSC-11740

ONS Unit 1 Startup Transformer (CT1) Open Phase

Protection (OPP) Failure Modes and Effects Analysis

(FMEA) and Single Failure Analysis (SFA)

Rev. 002

OSC-11763

Keowee Main Step-Up Transformer (KMSU) Open Phase

Protection (OPP) Failure Modes and Effects

Rev. 001

Procedures

OP/0/A/2000/043

KHS Shift Turnover And Rounds

Rev. 052

OP/2/A/1102/020

D

SSF and Outside Rounds

Rev. 091

Work Orders

209404

500KCMIL Cable from H0 Bushing to OPP SYS (41), SAT

Testing (77), Commissioning (80), 500 KCMIL Cable from

05/13/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OPP Cabinets to Ground (82).

219890

Connect Neutral/Gnd. Cable to Ground Mat (50), Connect

500 MCM Cable at CT5 HO Bushing (51), Perform Trip

Functional Verifications (84), Alarm Functional Verification

(85), Regression Testing (86), Circuit Interface Verification

(87).

01/02/2019

224441

EC407344-Assist PSS Tech with SAT Testing (61),

Commissioning (86), Voltage Checks for CT-1 (89)

6/27/2019

20320883

EC411891 - Alarm Testing Of CT-1 UPS/OPP System (63),

Test UPS Time Delay (44, 63), Energized Functional Testing

of CT-1 (61)

09/11/2019