IR 05000259/2017407

From kanterella
Jump to navigation Jump to search
Nuclear Regulatory Commission Material Control and Accounting Inspection Report 50-259/2017-407, 50-260/2017-407, and 50-296/2017-407 (Public)
ML17292A043
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 10/18/2017
From: Alan Blamey
Reactor Projects Region 2 Branch 6
To: James Shea
Tennessee Valley Authority
References
IR 2017407
Download: ML17292A043 (4)


Text

UNITED STATES ober 18, 2017

SUBJECT:

BROWNS FERRY NUCLEAR PLANT - NUCLEAR REGULATORY COMMISSION MATERIAL CONTROL AND ACCOUNTING INSPECTION REPORT 50-259/2017-407, 50-260/2017-407, AND 50-296/2017-407

Dear Mr. Shea:

On September 20, 2017 the U.S. Nuclear Regulatory Commission (NRC) completed a material control and accounting inspection at your Browns Ferry Nuclear Plant, Units 1, 2, and 3. The enclosed inspection report documents the inspection results, which were discussed on September 22, 2017, with Mr. G. Pry and other members of your staff.

This inspection examined activities conducted under your licenses as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

The NRC inspectors did not identify any findings or violations of more than minor significance.

However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance Enclosure (s) transmitted herewith contain(s) SUNSI. When separated from Enclosure(s),

this transmittal document is decontrolled. with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Should you have any questions concerning this letter, please contact us.

Sincerely,

/RA/

Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos. 50-259, 50-260, 50-296 License Nos. DPR-33, DPR-52, DPR-68 Enclosure:

NRC Material Control and Accounting Inspection Report 50-259/2017-407, 50-260/2017-407, and 50-296/2017-407 w/Attachment: Supplemental Information (OUO)

cc (See page 3) cc:

S.M. Bono Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000, NAB 2A-BFN Decatur, AL 35609 Glenn E. Pry Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 POB 2C-BFN Decatur, AL 35609 Jamie L. Paul Manager, Site Licensing Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000, SAB 2B-BFN Decatur, AL 35609 ____________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII/ DRP RII/ DRP SIGNATURE DED AJB3 NAME D. Dumbacher A. Blamey DATE 10/ 13 /2017 10/ 18 /2017