IR 05000250-05-005, & IR 05000251-05-005, on 01/27/2006, Preliminary White Finding Errata Letter, Turkey Point Nuclear Plant
ML060720341
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/13/2006
From: Joel Munday
NRC/RGN-II/DRP/RPB3
To: Stall J
Florida Power & Light Co
References
EA 06-027 IR-05-005
Download: ML060720341 (5)


Text

March 13, 2006 Florida Power and Light Company ATTN: Mr. J. A. Stall, Senior Vice President Nuclear and Chief Nuclear Officer P. O. Box 14000 Juno Beach, Florida 33408-0420 SUBJECT: TURKEY POINT NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000250/2005005 AND 05000251/2005005; PRELIMINARY WHITE FINDING ERRATA LETTER On January 27, 2006, the U. S. Nuclear Regulatory Commission (NRC) issued the subject inspection report for the Turkey Point Nuclear Plant. In reviewing this report, it was noted that the date was incorrect on the cover letter. Accordingly, we are providing a revised first page of the cover letter. Please replace the first page of the cover letter with the enclosed revision.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) components of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

I apologize for any inconvenience this error may have caused. If you have any questions, please contact me at (404) 562-4560.

Sincerely,

/RA/

Joel T. Munday, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos: 50-250, 50-251 License Nos. DPR-31, DPR-41 Enclosure: As stated

FP&L 2 cc w/encl:

T. O. Jones Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW 344th Street Florida City, FL 33035 Walter Parker Licensing Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW 344th Street Florida City, FL 33035 Michael O. Pearce Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW 344th Street Florida City, FL 30035 Mark Warner, Vice President Nuclear Operations Support Florida Power & Light Company P. O. Box 14000 Juno Beach, FL 33408-0420 Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P. O. Box 14000 Juno Beach, FL 33408-0420 M. S. Ross, Managing Attorney Florida Power & Light Company P. O. Box 14000 Juno Beach, FL 33408-0420

_________________________

OFFICE RII:DRP SIGNATURE JTM NAME JMunday DATE 03/13/06 3/ /2006 3/ /2006 3/ /2006 3/ /2006 3/ /2006 3/ /2006 ary 27, 2005

SUBJECT:

TURKEY POINT NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000250/2005005 AND 05000251/2005005; PRELIMINARY WHITE FINDING

Dear Mr. Stall:

On December 31, 2005, the US Nuclear Regulatory Commission (NRC) completed an inspection at your Turkey Point Units 3 and 4. The enclosed integrated inspection report documents the inspection findings which were discussed on January 12, 2006, with Mr. W. Webster and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This letter and the enclosed supporting documentation discuss a finding that appears to have low to moderate safety significance (White). This finding was assessed based on the best available information, including influential assumptions, using the applicable Significance Determination Process (SDP) and was preliminarily determined to be a White finding (i.e., a finding with some increased importance to safety, which may require additional NRC inspection).

This finding is characterized as an Apparent Violation (AV) of NRC requirements and is being considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs Web site at http://www.nrc.gov/what-we-do/regulatory/enforcement/enforce-pol.html.

ary 27, 2006

SUBJECT:

TURKEY POINT NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000250/2005005 AND 05000251/2005005; PRELIMINARY WHITE FINDING

Dear Mr. Stall:

On December 31, 2005, the US Nuclear Regulatory Commission (NRC) completed an inspection at your Turkey Point Units 3 and 4. The enclosed integrated inspection report documents the inspection findings which were discussed on January 12, 2006, with Mr. W. Webster and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This letter and the enclosed supporting documentation discuss a finding that appears to have low to moderate safety significance (White). This finding was assessed based on the best available information, including influential assumptions, using the applicable Significance Determination Process (SDP) and was preliminarily determined to be a White finding (i.e., a finding with some increased importance to safety, which may require additional NRC inspection).

This finding is characterized as an Apparent Violation (AV) of NRC requirements and is being considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs Web site at http://www.nrc.gov/what-we-do/regulatory/enforcement/enforce-pol.html.