Category:CORRESPONDENCE-LETTERS
MONTHYEARML20212J7481999-09-29029 September 1999 Forwards Insp Rept 50-133/99-02 on 990915.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program HBL-99-011, Forwards 10CFR50.59 Annual Rept of Changes,Tests & Experiments for 980101-981231, for Humboldt Bay Power Plant,Unit 31999-08-27027 August 1999 Forwards 10CFR50.59 Annual Rept of Changes,Tests & Experiments for 980101-981231, for Humboldt Bay Power Plant,Unit 3 HBL-99-014, Forwards Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates,1999-07-23023 July 1999 Forwards Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates, ML20209D9981999-07-0808 July 1999 Ack Receipt of Which Transmitted Rev 9 to Physical Security Plan for Humboldt Bay Power Plant,Under Provisions of 10CFR50.54(p).Changes Do Not Decrease Plan Effectiveness,So NRC Approval Is Not Required HBL-99-012, Forwards Rept of Rev 29 to Hbpp Emergency Plan,Effective 990610.Changes in Rev Do Not Decrease Effectiveness of Plan, Per 10CFR50.54(q).Plan Has Been Distributed to Region IV & Is Not Included as Part of Submittal1999-07-0707 July 1999 Forwards Rept of Rev 29 to Hbpp Emergency Plan,Effective 990610.Changes in Rev Do Not Decrease Effectiveness of Plan, Per 10CFR50.54(q).Plan Has Been Distributed to Region IV & Is Not Included as Part of Submittal ML18107A7011999-06-25025 June 1999 Requests Rev of NRC Records to Reflect Change of PG&E Address ML20207E7301999-05-27027 May 1999 Discusses Reorganization of Nrr,Effective 990328 & Forwards Organizational Chart HBL-99-008, Forwards Annual Rept of Occupational Radiation Exposure for 1998. Radiation Exposure Rept Provided on Encl Diskette in Electronic Format of Reg Guide 8.7.Without Encl1999-04-30030 April 1999 Forwards Annual Rept of Occupational Radiation Exposure for 1998. Radiation Exposure Rept Provided on Encl Diskette in Electronic Format of Reg Guide 8.7.Without Encl ML20205L9951999-04-0808 April 1999 Forwards Insp Rept 50-133/99-01 on 990222-25 & 0308.No Violations Identified HBL-99-006, Forwards Annual Radioactive Effluent Release Rept, Covering Period Jan-Dec 1998.Encl 2 Contains Revs 1 & 2 to Safstor ODCM as Required by Specification Section 4.2 of Safstor Offsite Dose Calculation Manual1999-03-31031 March 1999 Forwards Annual Radioactive Effluent Release Rept, Covering Period Jan-Dec 1998.Encl 2 Contains Revs 1 & 2 to Safstor ODCM as Required by Specification Section 4.2 of Safstor Offsite Dose Calculation Manual DCL-99-038, Forwards Decommissioning Funding Repts for Diablo Canyon Power Plant,Units 1 & 2 & Humboldt Bay Power Plant,Unit 3, Per Requirements of 10CFR50.75(f)1999-03-31031 March 1999 Forwards Decommissioning Funding Repts for Diablo Canyon Power Plant,Units 1 & 2 & Humboldt Bay Power Plant,Unit 3, Per Requirements of 10CFR50.75(f) HBL-99-003, Forwards Annual Facility Status & Survey Rept, for Jan-Dec 19981999-03-31031 March 1999 Forwards Annual Facility Status & Survey Rept, for Jan-Dec 1998 ML20202A9831999-01-18018 January 1999 Informs That Modesto Irrigation District No Longer Seeking Addl Interconnection with Pacific Gas & Electric Co at Pittsburg,Ca & Matters First Addressed in 980429 Comments in Opposition to Restructuring of Util Have Now Become Moot HBL-98-021, Forwards Rept Change (Rev 28) to Hbpp Emergency Plan, Effective 981126.Updated Emergency Plan,Not Included as Part of Submittal1998-12-18018 December 1998 Forwards Rept Change (Rev 28) to Hbpp Emergency Plan, Effective 981126.Updated Emergency Plan,Not Included as Part of Submittal ML20195H7631998-11-20020 November 1998 Forwards Insp Rept 50-133/98-04 on 980901-03,1012-17 & 20-22.No Violations Noted.Insp Focused on Activities Associated with Removal of 250 Feet Ventilation Stack HBL-98-013, Forwards 10CFR50.59 Annual Rept of Changes,Tests & Experiments for Jan-Dec 1997. Encl Annual Rept Provides Brief Description of 10CFR50.59 Facility Design Changes, Including Summary of Each SE1998-11-10010 November 1998 Forwards 10CFR50.59 Annual Rept of Changes,Tests & Experiments for Jan-Dec 1997. Encl Annual Rept Provides Brief Description of 10CFR50.59 Facility Design Changes, Including Summary of Each SE ML20154G4441998-10-0101 October 1998 Ack Receipt of Which Transmitted Rev 8 to Physical Security Plan for Humboldt Bay Power Plant,Under Provisions 10CFR50.54.Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required DCL-98-123, Submits Listed Address Changes for NRC Service Lists for Listed Individuals1998-09-0909 September 1998 Submits Listed Address Changes for NRC Service Lists for Listed Individuals HBL-98-015, Forwards Rev 2 to DSAR for Humboldt Bay Power Plant,Unit 3, to Comply W/Decommissioning Rule.Dsar Was Formerly Known as Safstor Decommissioning Plan.Encl 1 Identifies & Describes Rept Changes1998-08-28028 August 1998 Forwards Rev 2 to DSAR for Humboldt Bay Power Plant,Unit 3, to Comply W/Decommissioning Rule.Dsar Was Formerly Known as Safstor Decommissioning Plan.Encl 1 Identifies & Describes Rept Changes DCL-98-108, Submits 90-day Response to NRC GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants. Util Has Pursued & Continuing to Pursue Year 2000 Readiness Program Similar to That Outlined in Nei/Nusmg 97-07, Nuclear Util Year..1998-08-0707 August 1998 Submits 90-day Response to NRC GL 98-01, Yr 2000 Readiness of Computer Sys at Nuclear Power Plants. Util Has Pursued & Continuing to Pursue Year 2000 Readiness Program Similar to That Outlined in Nei/Nusmg 97-07, Nuclear Util Year.. HBL-98-009, Submits Info Describing site-specifc Decommissioning Cost Estimates1998-08-0505 August 1998 Submits Info Describing site-specifc Decommissioning Cost Estimates ML20236G0691998-06-19019 June 1998 Forwards Endorsement 123 to Neila Policy NF-228,Endorsement 145 to Neila Policy NF-113,Endorsement 124 to Neila Policy NF-228 & Endorsement 89 to Maelu Policy MF-103 L-98-027, Forwards Rev 8 to Physical Security Plan.Encl 1 Identifies & Describes Plan Changes,Which Indicated W/Rev Bars in Left Margin of Physical Security Plan.Rev Withheld,Per 10CFR2.790(d)1998-06-11011 June 1998 Forwards Rev 8 to Physical Security Plan.Encl 1 Identifies & Describes Plan Changes,Which Indicated W/Rev Bars in Left Margin of Physical Security Plan.Rev Withheld,Per 10CFR2.790(d) HBL-98-011, Forwards Rept of Rev 27 to Hbpp Emergency Plan,Effective 980507,per 10CFR50.4 & 10CFR50.54(q).Updated Plan Has Already Been Distributed to NRC Region IV IAW Hbpp Procedures.W/O Rept1998-06-0404 June 1998 Forwards Rept of Rev 27 to Hbpp Emergency Plan,Effective 980507,per 10CFR50.4 & 10CFR50.54(q).Updated Plan Has Already Been Distributed to NRC Region IV IAW Hbpp Procedures.W/O Rept ML20247R9091998-05-26026 May 1998 Forwards Copy of Transcript of Public Meeting Held by NRC W/Participation by PG&E on 980429 in Eureka,California Re Decommissioning of Humboldt Bay Power Plant ML20236E7681998-05-22022 May 1998 Forwards Insp Rept 50-133/98-03 on 980427-30.No Violations Noted.Insp Included Plans for Future Decommissioning of Facility,Including Removal of Unit 3 Stack & Eventual Dry Cask Storage of Unit 3 Spent Fuel ML20247L3571998-05-18018 May 1998 Clarifies Remark Re Discharge Through Existing Ventilation Stack to Avoid Confusion.Remark Was in Response to Question Re Purpose of Dismantlement & Replacement of Existing Ventilation Stack ML20247F9241998-05-14014 May 1998 Forwards Insp Rept 50-133/98-02 on 980414-15.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program.Determined That Physical Security Program Was Properly Implemented ML20216B7291998-05-12012 May 1998 Expresses Appreciation for Support Provided for Recent Public Meeting Held at Eureka Inn on Decommissioning of Humboldt Bay Power Plant ML20216B6801998-05-11011 May 1998 Expresses Appreciation for Outstanding Support Staff Provided for Recent Public Meeting Held at Eureka Inn on Decommissioning of Humboldt Bay Power Plant ML20217H1161998-04-21021 April 1998 Forwards Annual Rept of Occupational Radiation Exposure, for Employees & Visitors Monitored at Humboldt Bay Power Plant During CY97.Rept on Diskette.W/O Encl ML20216C8681998-04-0808 April 1998 Forwards Amend 32 to License DPR-7 & Safety Evaluation. Amend Revises TS to Implement GL 89-01 & to Incorporate Requirements of Revised 10CFR20 & App I to 10CFR50 HBL-98-008, Forwards Annual Radioactive Effluent Release Rept for 970101-1231. Rept Contains Comparison of Max Calculated Dose to Individual Members of Public W/Numerical Guidelines of 10CFR50 App I1998-03-31031 March 1998 Forwards Annual Radioactive Effluent Release Rept for 970101-1231. Rept Contains Comparison of Max Calculated Dose to Individual Members of Public W/Numerical Guidelines of 10CFR50 App I HBL-98-006, Forwards Annual Facility Status & Survey Rept for 1997. Section a Addresses Facility Status & Section B Presents Results of Monitoring Performed for Radiological Environ Monitoring Program1998-03-31031 March 1998 Forwards Annual Facility Status & Survey Rept for 1997. Section a Addresses Facility Status & Section B Presents Results of Monitoring Performed for Radiological Environ Monitoring Program HBL-98-003, Forwards Corrected TSs Re LAR 96-02,in Entirety W/ Affected Pages Retyped1998-03-13013 March 1998 Forwards Corrected TSs Re LAR 96-02,in Entirety W/ Affected Pages Retyped HBL-98-002, Submits Updated Post-Shutdown Decommissioning Activities Rept for Humboldt Bay Power Plant,Unit 3. Safstor Decommissioning Plan Will Be Considered FSAR for Hbpp1998-02-27027 February 1998 Submits Updated Post-Shutdown Decommissioning Activities Rept for Humboldt Bay Power Plant,Unit 3. Safstor Decommissioning Plan Will Be Considered FSAR for Hbpp ML20203K9691998-02-27027 February 1998 Forwards Insp Rept 50-133/98-01 on 980126-29.No Violations Noted.Major Areas Reviewed as Part of Insp Included Compliance W/Selected TS of License,Review of 1997 Annual Exercise & Evaluation of Facility Re Decommissioning Plan HBL-98-001, Informs That Existing Hbpp PM Program Adequately Meets Requirements of Maint Rule.Summary of Program & Basis for Determining Maint Rule Compliance at Plant,Encl1998-01-26026 January 1998 Informs That Existing Hbpp PM Program Adequately Meets Requirements of Maint Rule.Summary of Program & Basis for Determining Maint Rule Compliance at Plant,Encl ML20198J4791998-01-0707 January 1998 Informs That LL Wheeler Assumed Project Mgt Responsibilities for Humboldt Bay on 971229.LL Wheeler Can Be Contacted at Listed E-mail Address ML20199B3851997-11-13013 November 1997 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-133/97-02 on 971001 HBL-97-016, Responds to NRC Re Violations Noted in Insp Rept 50-133/97-02.Corrective Actions:Correctly Reset Process Water Monitor Warning High & Low Alarms & re-educated All Operators on Proper Method to Set Process Water Monitor1997-10-27027 October 1997 Responds to NRC Re Violations Noted in Insp Rept 50-133/97-02.Corrective Actions:Correctly Reset Process Water Monitor Warning High & Low Alarms & re-educated All Operators on Proper Method to Set Process Water Monitor HBL-97-015, Submits Inventory Changes at Unit 3 from 970401-0930 for Matls Re Enriched U Fuel,Plutonium in Fuel,Fission Counters & Incore Flux Detectors.Encl 2 Provides Data Required by Form DOE/NRC-741.W/o Encl1997-10-0909 October 1997 Submits Inventory Changes at Unit 3 from 970401-0930 for Matls Re Enriched U Fuel,Plutonium in Fuel,Fission Counters & Incore Flux Detectors.Encl 2 Provides Data Required by Form DOE/NRC-741.W/o Encl ML20217D6191997-10-0101 October 1997 Forwards Insp Rept 50-133/97-02 on 970513-0828 & Nov.Nrc Will Use Licensee Response to NOV to Determine Whether Further Enforcement Action Necessary HBL-97-012, Forwards Rept of Rev 26 to Plant Emergency Plan,Effective 970801.Changes Do Not Decrease Effectiveness of Plan1997-08-28028 August 1997 Forwards Rept of Rev 26 to Plant Emergency Plan,Effective 970801.Changes Do Not Decrease Effectiveness of Plan ML20210H4671997-08-0202 August 1997 Requests That NRC Suspend Investigation & Review of Issues Raised by Modesto Irrigation District & Transmission Agency of Northern CA Re Contention That PG&E Had Violated Nuclear License Conditions Known as Stanislaus Commitments ML20149K8321997-07-25025 July 1997 Ack Receipt of Transmitting Rev 7 to Physical Security Plan,Submitted Under Provisions of 10CFR50.54(p). Changes Do Not Decrease Effectiveness of Plan & No NRC Approval Is Required HBL-97-009, Provides Addl Justification to Support TS Change Request Contained in LAR 96-02 ,re Establishment of Radiological Effluents Control Program & in Response to 970416 Telcon1997-06-12012 June 1997 Provides Addl Justification to Support TS Change Request Contained in LAR 96-02 ,re Establishment of Radiological Effluents Control Program & in Response to 970416 Telcon L-97-035, Forwards Info Re Changes to Humboldt Bay Power Plant,Unit 3 Physical Security Plan.Changes Do Not Decrease Safeguards Effectiveness of Plan & Are Submitted Per 10CFR50.54(p). Encls Withheld Per 10CFR2.790(d)1997-04-0909 April 1997 Forwards Info Re Changes to Humboldt Bay Power Plant,Unit 3 Physical Security Plan.Changes Do Not Decrease Safeguards Effectiveness of Plan & Are Submitted Per 10CFR50.54(p). Encls Withheld Per 10CFR2.790(d) L-97-033, Confirms Final Disposition of Specific Hazardous Wastes Shipped to IT Corp Panoche & Vine Hill Facilities from Plant in Jul 19861997-04-0202 April 1997 Confirms Final Disposition of Specific Hazardous Wastes Shipped to IT Corp Panoche & Vine Hill Facilities from Plant in Jul 1986 HBL-97-003, Documents Utils Understanding of Results in Discussions from Meeting W/Nrc Personnel to Discuss Application of New Decommissioning Rule to Hbpp1997-02-20020 February 1997 Documents Utils Understanding of Results in Discussions from Meeting W/Nrc Personnel to Discuss Application of New Decommissioning Rule to Hbpp 1999-09-29
[Table view] Category:NRC TO UTILITY
MONTHYEARML20059C0381990-08-22022 August 1990 Advises That 880826 & 900717 Rev 2 to Physical Security Plan Consistent W/Provisions of 10CFR50.54(p) & Acceptable ML20055H4661990-07-13013 July 1990 Forwards Insp Rept 50-133/90-02 on 900618-21.No Violations Noted IR 05000133/19890021989-09-28028 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations in Insp Rept 50-133/89-02 IR 05000133/19890031989-08-28028 August 1989 Forwards Safeguards Insp Rept 50-133/89-03 on 890814-24.No Violations Noted.Rept Withheld (Ref 10CFR73.21 & 2.790(d)) ML20246M1151989-08-22022 August 1989 Forwards Exemption from Property Damage Insurance Requirement,Per 890609 Request ML20246D2811989-08-11011 August 1989 Forwards Insp Rept 50-133/89-02 on 890717-20 & Notice of Violation ML20206K6001988-11-18018 November 1988 Forwards Temporary Exemption from Schedular Requirements of Property Insurance Rule 10CFR50.54(w)(5)(i) Re Insurance Policies That Prioritize Insurance Proceeds for Stabilization & Decontamination After Accident ML20205T7301988-11-0303 November 1988 Notifies of 890110 Meeting W/Region V in San Francisco,Ca to Discuss NRC Reactor Operator Licensing Program in Region ML20154P5851988-09-16016 September 1988 Forwards Insp Rept 50-133/88-01 on 880829-0902.No Violations Noted ML20151U7621988-08-11011 August 1988 Informs of NRC Interpretation of Section 10CFR50.74(a) Re Changes in Operator or Senior Operator Status ML20151U3741988-08-11011 August 1988 Informs of NRC Interpretation of 10CFR50.74(a) Re Changes in Operator or Senior Operator Status ML20151U0111988-08-0404 August 1988 Advises That Rev 1 to Plant Emergency Plan for Safstor Meets Stds in 10CFR50.47(b) & Requirements of 10CFR50,App E & Acceptable ML20151G2141988-07-19019 July 1988 Forwards Amend 23 to License DPR-7 & Safety Evaluation. Amend Deletes Certain Conditions Re Seismic Mods Required Before NRC Would Authorize Return to Power Operation.Notice of Issuance Also Encl ML20196B2331988-06-21021 June 1988 Forwards Request for Addl Info Re Use of Tamper Indicating Security Seals on Spent Fuel Storage Pool to Allow Change from Present Annual Inventories of SNMs to Inventories Every 5 Yrs,In Response to ML20195E3301988-06-16016 June 1988 Informs That Portions of Rev 2 to Nov 1986 Physical Security Plan Consistent w/10CFR50.54(p) & Acceptable.Util Instructed to Follow Previously Approved Plan for Noted Inconsistent Portion,Per 10CFR73.57.Encl Withheld (Ref 10CFR73.21) ML20236Y2981987-12-0404 December 1987 Advises That 870430 Rev 1 to Physical Security Plan Consistent W/Provisions of 10CFR50.54(p) & Acceptable ML20236J4791987-10-23023 October 1987 Forwards Insp Rept 50-133/87-05 on 870928-1001.No Violations Noted ML20236D5351987-07-23023 July 1987 Forwards Safeguards Insp Rept 50-133/87-03 on 870714-16.No Violations Noted ML20236D4941987-07-23023 July 1987 Forwards Request for Addl Info Re Tech Specs on Insp Programs for Decommissioning.Necessary Changes to Tech Specs Also Encl.Response Requested within 30 Days of Ltr Date ML20235D1691987-06-23023 June 1987 Forwards Insp Rept 50-133/87-02 on 870602-05 & Notice of Violation ML20215L9441987-05-0606 May 1987 Forwards Fes Re Decommissioning of Facility.Notice of Issuance Forwarded to Ofc of Fr for Publication ML20210C5081987-04-29029 April 1987 Forwards SER Re Proposed Decommissioning of Facility.Ser Evaluates 840730 Application to Delete Certain License Conditions Re Seismic Mods Before NRC Would Authorize Return to Power & to Extend License DPR-7 to 151109 IR 05000133/19870011987-03-0404 March 1987 Forwards Insp Rept 50-133/87-01 on 870209-13.No Violations Noted ML20211C5301987-02-11011 February 1987 Forwards Amend 22 to License DPR-7 & Safety Evaluation. Amend Establishes Physical Security Requirements for Unit Shut Down.Security Plan Reflects possess-but-not-operate Status of License ML20210E9591987-02-0404 February 1987 Advises of 870311 Workshop on NRC Incident Investigation Program (Iip) in Walnut Creek,Ca to Provide Info Re NRC Process for Investigating Potential Significant Incidents. Agenda Encl.W/O Iip Procedures ML20210F2641987-02-0404 February 1987 Forwards Two Copies of Emergency Plan Std Operating Procedure III.25 for State of CA Mens Colony,Per 870113 Request to Withdraw Procedure in Accordance w/10CFR2.790(c). Third Copy of Procedure Destroyed ML20207F1131986-12-30030 December 1986 Forwards Request for Addl Info Re Emergency Planning for Safstor,To Support 850404 & 860612 Proposed Decommissioning Plan.Response Requested by 870120 ML20212A4541986-12-0808 December 1986 Forwards Insp Rept 50-133/86-03 on 861117-21.No Violations Noted ML20212N4791986-08-26026 August 1986 Forwards Amend 21 to License DPR-7 & Safety Evaluation. Amend Revises Tech Specs to Upgrade Requirements for Stack Gas Monitoring Sys & Reduce Required Number of Condensate Demineralizer Beds ML20202H9291986-07-14014 July 1986 Informs That State of CA Has Jurisdiction Over Disposal of Low Level Radwaste,In Response to 860617 Request for Approval to Dispose of Sludge & Firebox Waste Containing Very Low Levels of Radioactivity ML20199J5181986-06-27027 June 1986 Forwards Fr Notice of Consideration of Issuance of Amend to License DPR-7 & Opportunity for Prior Hearing,On 840730 Application,Deleting License Conditions Re Seismic Investigation Analysis & Mods ML20211K1311986-06-23023 June 1986 Forwards Insp Rept 50-133/86-02 on 860602-06.No Violation Noted ML20206L5521986-06-18018 June 1986 Advises That Rev 2 to Safstor QA Plan Continues to Satisfy Requirement That QA Program Description Provide Adequate Assurance That Decommissioning Will Be Conducted in Controlled Manner.Plan Acceptable ML20206H1471986-06-16016 June 1986 Forwards Amend 20 to License DPR-7 & Safety Evaluation.Amend Deletes License Condition E.2.e Re Reinstatement & Operation of Microseismic Monitoring Network,Per Util 831216 Request as Supplemented on 860307 ML20210E1971986-03-11011 March 1986 Forwards Insp Rept 50-133/86-01 on 860219-21.No Violation Noted ML20137L4961986-01-21021 January 1986 Advises That Revised 851022 Physical Security Plan Satisfies NRC Requirements & Acceptable.Guard Training & Qualification & Safeguards Contingency Plans Still Need to Be Submitted for Review & Approval ML20138R0021985-12-20020 December 1985 Discusses 840620 Rev to 10CFR170 Re Billing Procedures. Bills Recently Issued Under Category 1 for Cycle Ending 841222.Billing Categories 2-5 Can Expect Bills for First Cycle Shortly.Future Notice Prior to Billing Will Not Occur ML20138A3071985-10-0404 October 1985 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Listed in 850826 Notice of Violation. Corrective Actions Will Be Reviewed in Next Physical Security Insp ML20133G4311985-09-27027 September 1985 Forwards Insp Rept 50-133/85-04 on 850826-30 & 0918-22.No Violations Noted ML20135B0521985-09-0303 September 1985 Forwards Environ Assessment Accepting 850425 Request Re Transfer of Sludge from Wastewater Treatment Ponds Offsite. Approval from Relevant State & Local Agencies May Be Necessary for Implementation,Per 10CFR150 IR 05000133/19850031985-08-26026 August 1985 Forwards Safeguards Insp Rept 50-133/85-03 on 850731-0820 & Notice of Violation.Encls Withheld (Ref 10CFR2.790 & 73.21) IR 05000133/19850021985-07-25025 July 1985 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-133/85-02.Steps Identified at 850718 Meeting Include Measures to Address Radiation Protection Program Concerns ML20128M6451985-07-16016 July 1985 Forwards Amend 19 to License DPR-7 & Safety Evaluation.Amend Modifies License to possess-but-not-operate Status ML20127N6621985-06-12012 June 1985 Forwards Insp Rept 50-133/85-02 on 850513-16 & Notice of Violation ML20128L8811985-05-21021 May 1985 Requests Fee for 850425 Application for Amend to License DPR-7,authorizing Disposal of 5,000 Cubic Ft of Low Level Wastes IR 05000133/19840021984-06-12012 June 1984 Discuss IE Safeguards Insp Rept 50-133/84-02 Conducted on 840523-25.No Noncompliance Noted.Major Areas Inspected:Exams of Procedures & Records & Interviews W/Personnel.Rept Withheld (Ref 10CFR2.790 & 73.21) ML20054M1801982-07-0202 July 1982 Advises of Acceptability of Changes to Security Plan, Transmitted by .Encl to Ltr Being Withheld (Ref 10CFR73.21) ML20058D1451982-07-0202 July 1982 Forwards IE Safeguards Insp Rept 50-133/82-02 on 820621-24. No Noncompliance Noted ML20132A9061979-08-13013 August 1979 Forwards IE Bulletin 79-21, Temp Effects on Level Measurements. No Action Required ML20062H1461979-05-11011 May 1979 Forwards IE Bulletin 79-10, Requalification Training Program Statistics. Written Response Required 1990-08-22
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20212J7481999-09-29029 September 1999 Forwards Insp Rept 50-133/99-02 on 990915.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program ML20209D9981999-07-0808 July 1999 Ack Receipt of Which Transmitted Rev 9 to Physical Security Plan for Humboldt Bay Power Plant,Under Provisions of 10CFR50.54(p).Changes Do Not Decrease Plan Effectiveness,So NRC Approval Is Not Required ML20207E7301999-05-27027 May 1999 Discusses Reorganization of Nrr,Effective 990328 & Forwards Organizational Chart ML20205L9951999-04-0808 April 1999 Forwards Insp Rept 50-133/99-01 on 990222-25 & 0308.No Violations Identified ML20195H7631998-11-20020 November 1998 Forwards Insp Rept 50-133/98-04 on 980901-03,1012-17 & 20-22.No Violations Noted.Insp Focused on Activities Associated with Removal of 250 Feet Ventilation Stack ML20154G4441998-10-0101 October 1998 Ack Receipt of Which Transmitted Rev 8 to Physical Security Plan for Humboldt Bay Power Plant,Under Provisions 10CFR50.54.Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML20247R9091998-05-26026 May 1998 Forwards Copy of Transcript of Public Meeting Held by NRC W/Participation by PG&E on 980429 in Eureka,California Re Decommissioning of Humboldt Bay Power Plant ML20236E7681998-05-22022 May 1998 Forwards Insp Rept 50-133/98-03 on 980427-30.No Violations Noted.Insp Included Plans for Future Decommissioning of Facility,Including Removal of Unit 3 Stack & Eventual Dry Cask Storage of Unit 3 Spent Fuel ML20247F9241998-05-14014 May 1998 Forwards Insp Rept 50-133/98-02 on 980414-15.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program.Determined That Physical Security Program Was Properly Implemented ML20216B7291998-05-12012 May 1998 Expresses Appreciation for Support Provided for Recent Public Meeting Held at Eureka Inn on Decommissioning of Humboldt Bay Power Plant ML20216B6801998-05-11011 May 1998 Expresses Appreciation for Outstanding Support Staff Provided for Recent Public Meeting Held at Eureka Inn on Decommissioning of Humboldt Bay Power Plant ML20216C8681998-04-0808 April 1998 Forwards Amend 32 to License DPR-7 & Safety Evaluation. Amend Revises TS to Implement GL 89-01 & to Incorporate Requirements of Revised 10CFR20 & App I to 10CFR50 ML20203K9691998-02-27027 February 1998 Forwards Insp Rept 50-133/98-01 on 980126-29.No Violations Noted.Major Areas Reviewed as Part of Insp Included Compliance W/Selected TS of License,Review of 1997 Annual Exercise & Evaluation of Facility Re Decommissioning Plan ML20198J4791998-01-0707 January 1998 Informs That LL Wheeler Assumed Project Mgt Responsibilities for Humboldt Bay on 971229.LL Wheeler Can Be Contacted at Listed E-mail Address ML20199B3851997-11-13013 November 1997 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-133/97-02 on 971001 ML20217D6191997-10-0101 October 1997 Forwards Insp Rept 50-133/97-02 on 970513-0828 & Nov.Nrc Will Use Licensee Response to NOV to Determine Whether Further Enforcement Action Necessary ML20149K8321997-07-25025 July 1997 Ack Receipt of Transmitting Rev 7 to Physical Security Plan,Submitted Under Provisions of 10CFR50.54(p). Changes Do Not Decrease Effectiveness of Plan & No NRC Approval Is Required ML20138H4121996-12-31031 December 1996 Final Response to FOIA Request for Documents.Forwards Documents Listed in App C.Documents Encl Available in PDR ML20133A6131996-12-24024 December 1996 Discusses Withdrawal of Amend Request for Plant,Unit 3 for License DPR-7.Notice of Withdrawal for Amend to FOL Encl ML20129J4001996-10-18018 October 1996 Forwards Order Approving Corporate Restructuring by Establishment of Holding Company & Safety Evaluation IR 05000133/19930041993-12-0202 December 1993 Forwards Insp Rept 50-133/93-04 on 931115-18.No Violations Noted.Encl Withheld (Ref 10CFR2.790) ML20057C6451993-08-26026 August 1993 Forwards Insp Rept 50-133/93-03 on 930817.No Violations Noted ML20057C5091993-08-26026 August 1993 Forwards Insp Rept 50-133/93-02 on 930817-20.No Violations Noted ML20056G0041993-06-25025 June 1993 Submits Info Re Implementation of Training Rule 10CFR50.120 for Licensees of Plant in Decommissioning Process ML20059C0381990-08-22022 August 1990 Advises That 880826 & 900717 Rev 2 to Physical Security Plan Consistent W/Provisions of 10CFR50.54(p) & Acceptable ML20055H4661990-07-13013 July 1990 Forwards Insp Rept 50-133/90-02 on 900618-21.No Violations Noted IR 05000133/19890021989-09-28028 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations in Insp Rept 50-133/89-02 IR 05000133/19890031989-08-28028 August 1989 Forwards Safeguards Insp Rept 50-133/89-03 on 890814-24.No Violations Noted.Rept Withheld (Ref 10CFR73.21 & 2.790(d)) ML20246M1151989-08-22022 August 1989 Forwards Exemption from Property Damage Insurance Requirement,Per 890609 Request ML20246D2811989-08-11011 August 1989 Forwards Insp Rept 50-133/89-02 on 890717-20 & Notice of Violation ML20245B4531989-06-0808 June 1989 Forwards Encl Listed Info on Decommissioned & Shutdown Reactors Requested During Discussions at Saxton on 890511 ML20206K6001988-11-18018 November 1988 Forwards Temporary Exemption from Schedular Requirements of Property Insurance Rule 10CFR50.54(w)(5)(i) Re Insurance Policies That Prioritize Insurance Proceeds for Stabilization & Decontamination After Accident ML20205T7301988-11-0303 November 1988 Notifies of 890110 Meeting W/Region V in San Francisco,Ca to Discuss NRC Reactor Operator Licensing Program in Region ML20154P5851988-09-16016 September 1988 Forwards Insp Rept 50-133/88-01 on 880829-0902.No Violations Noted ML20151U7621988-08-11011 August 1988 Informs of NRC Interpretation of Section 10CFR50.74(a) Re Changes in Operator or Senior Operator Status ML20151U3741988-08-11011 August 1988 Informs of NRC Interpretation of 10CFR50.74(a) Re Changes in Operator or Senior Operator Status ML20151U0111988-08-0404 August 1988 Advises That Rev 1 to Plant Emergency Plan for Safstor Meets Stds in 10CFR50.47(b) & Requirements of 10CFR50,App E & Acceptable ML20151G2141988-07-19019 July 1988 Forwards Amend 23 to License DPR-7 & Safety Evaluation. Amend Deletes Certain Conditions Re Seismic Mods Required Before NRC Would Authorize Return to Power Operation.Notice of Issuance Also Encl ML20196B2331988-06-21021 June 1988 Forwards Request for Addl Info Re Use of Tamper Indicating Security Seals on Spent Fuel Storage Pool to Allow Change from Present Annual Inventories of SNMs to Inventories Every 5 Yrs,In Response to ML20195E3301988-06-16016 June 1988 Informs That Portions of Rev 2 to Nov 1986 Physical Security Plan Consistent w/10CFR50.54(p) & Acceptable.Util Instructed to Follow Previously Approved Plan for Noted Inconsistent Portion,Per 10CFR73.57.Encl Withheld (Ref 10CFR73.21) ML20236Y2981987-12-0404 December 1987 Advises That 870430 Rev 1 to Physical Security Plan Consistent W/Provisions of 10CFR50.54(p) & Acceptable ML20236J4791987-10-23023 October 1987 Forwards Insp Rept 50-133/87-05 on 870928-1001.No Violations Noted ML20235B3081987-09-21021 September 1987 Responds to FOIA Request for Documents,Including AEC to ACRS Forwarding Safety Evaluation Re Zimmer.App a Documents Cannot Be Located.App B Documents in Pdr.App C & D Documents Withheld (Ref 10CFR2.790) ML20236D4941987-07-23023 July 1987 Forwards Request for Addl Info Re Tech Specs on Insp Programs for Decommissioning.Necessary Changes to Tech Specs Also Encl.Response Requested within 30 Days of Ltr Date ML20236D5351987-07-23023 July 1987 Forwards Safeguards Insp Rept 50-133/87-03 on 870714-16.No Violations Noted ML20235M4251987-07-13013 July 1987 Partial Response to FOIA Request for Documents Re Acrs. Forwards Documents for Categories One & Three of FOIA Request.Review of 21 Addl ACRS Documents Continuing ML20234E4571987-06-23023 June 1987 Partial Response to FOIA Request for 771026 Minutes of ACRS Subcommittee on Fluid/Hydraulic Dynamic Effects Meeting in Portland,Or & Addl ACRS Documentation.Documents Identified on App H & Addl ACRS Documents Encl ML20235D1691987-06-23023 June 1987 Forwards Insp Rept 50-133/87-02 on 870602-05 & Notice of Violation ML20214K9931987-05-26026 May 1987 Responds to FOIA Request for GE Repts NEDE-10182 & GEAP-3143.Forwards Rept GEAP-3143, Test Rept for Pressure Suppression,Development Program ML20214M6631987-05-22022 May 1987 Forwards Revised NRC Form 398.Rev Reflects Changes to 10CFR55 Effective on 870526.Revised Form Requires New Applications to Complete Each Category Including Educ, Training & Experience.Changes Detailed in Encl 2 1999-09-29
[Table view] |
Text
I/3 JUL 25 E3 Docket No. 50-133 Pacific Gas and Electric Company 77 Beale Street, Room 1451 San Francisco, California 94106 Attention: Mr. J. D. Shiffer, Vice President Nuclear Power Generation, Licensing Gentlemen:
Subject: Response to Notice of Violation Thank you for your letter dated July 12, 1985, informing us of the steps you have taken to correct the items which we brought to your attention in our letter dated June 12, 1985.
We consider the meeting held at our office on July 18, 1985 to have been a beneficial discussion of radiation protection issues at PG&E, The steps you identified appear to include adequate measures to address our concerns regarding radiation protection programs.
Your corrective actions will be verified in a future inspection.
Your cooperation with us is appreciated.
Sincerely,
/C/
Ronn A. Scarano, Director Division of Radiation Safety and Safeguards cci Jim Knight, NRR P. A. Cranc, Attorney, PG&E S. D. Skidmore, PG&E E. Weeks, Plant Superintendent, PG6E
!itate of CA bcc: ItSil/ Document Control Desk (RIDS)
fir. hv NDs ~ '(Y
) L CSherman:dh GYuhan l'Wenn lavski Scarano 7/ 14 /8's 7/.f 4 /85 7/WP/85 07/ @ /85 0507300104 OD07PD PDH ADOCK 00000133 o PDH l l lh0
, _ _ _ _ . . _ -
1 -, G c
PACIFIC OAS AND E LE C T RIC C O M PANY bbU#3 l 77 BEALC StRECT . SAN FRANCISCO. CAUFORNI A 94106 . (415)781 4211 . TWX 910 372 6587 JAMES O. SHsPPEft IsWCLIA sa aafioso g July 12,1985 PGandE Letter No.: HB L-85-031
..
Mr. John B. Martin, Regional Administrator U. S. Nuclear Regulatory Commission, Region Y 1450 Maria Lane, Suite 210 i Walnut Creek , CA 94596-5368 Re: Docket No. 50-133, OL-DPR-7 Humboldt Bay Power Plant Unit No. 3 Response to IEIR 50-133/85-02 -- Notice of Violation
Dear Mr. Martin:
NRC Inspection Report 50-133/85-02, dated June 12, 1985, contained one Severity Level IV violation and two Severity Level V violations. PGandE's response to these notices of violation is enclosed.
Kindly acknowledge receipt of this material on the enclosed copy of this letter and return it in the enclosed addressed envelope.
Sincerel , ,
/
, v
. D. Shi 'y '
.
Enclosure cc: P. B. Erickson Service List
. 9
'
i t
gro4nR
'
1f
.
.
. i
-. - .. . - - _ _ . .-
,
, ..
.
[
I ENCLOSURE RESPONSE TO NOTICE CF VIOLATION IN ^
NRC INSPECTION REPORT NO. 50-133/85-02 l
On June 12, 1985, NRC Region V issued one Severity Level IV and two Severity Level V Notices of Violation (" Notices") as part of NRC Inspection Report 50-133,85-02 for Hunboldt Bay Power Plant Unit No. 3. The Notices ci ted: -
o Failure to comply with the re movements, (Severity Level Y)quirements of a procedure for fuel
.
,
'
l o Access to high radiation area was not equipped with a control device, alarm, or lock, (Severity Level IV).
o A concern that a survey around a radioactivo waste container and shield ring was not documented, (Severity Level V).
In the subject inspection report, the inspector stated that he was given the
" impression" by the licensee representatives that strict compliance with NRC l requirements was a matter of judgment. Compliance with NRC requirements is
- not now and has never been considered a matter of judgment or discretion. The staff of the Humboldt Bay Power Plant has always strived to comply with NRC requirements as they understood them.
,
l A. FAILURE TO COMPLY WITH PROCEDURAL RE0VIReiENTS STATD4ENT OF VIOLATION
" Technical Specification IX.F.1.b states in part that detailed written procedures shall be adhered to for fuel handling operations.
Plant Manual Temporary Procedure 5/9/85 No.1 states in part that only one assenbly at a time is permitter' in the fuel disassently statica and that the assembly is to be n,0ved to the out-of-stock *
warehouse before another is removed from the new fuel storage vault.
Contrary to the above procedure, on May 14, 1985 the inspector observed one disassembled fuel assenbly with 5 pins on the work table, the remainder of the assembly on a fork truck at the refueling building doors when a second fuel assenbly was removed from the new fuel storage vault and placed in the work fixture.
, .
f This is a Severity Level V Violation (Supplement VI)." s
'
EXPLANATION AND CORRECTIVE STEPS TAKEN l As part of efforts to return unirradiated fuel to the vendor, fuel I assemblics were disassembled and individual fuel rods were decontaminated l
l l
04025/0034K -1-
.
,
. . .
,
.
.
.
and then placed on a " clean table." These activities were performed in one work area. When the results of a final radiation survey indicate that the rods are decontaminated, they are transferred from the work area to shipping containers. Contrary to the Technical Specification ,_
(TS) V.B.7 requirement that transfer of fuel assemblies within work ~
locations "shall be limited to one fuel assenbly in any location", a fuel assembly was moved from the new fuel storage vault into the disassembly area while 5 fuel pins from the previous assembly w'ere still on the
" clean table" awaiting survey results. The cause of the event was insufficient attention to the requirements of the Technical Specifications by personnel involved in the work. On June 13, 1985, PGandE submitted License Event Report 85-003-00 (Letter No. HBL-85-025)
concerning this incident.
Corrective. action included revising the temporary procedure to define the fuel disassently/ decontamination area and the " clean table" area as separate work locations and require that a ifcensed operator be present at each specific work location. In accordance with TS V.B.7, the revised procedure clearly specifies that only one fuel assembly at each work loca tion. Personnel involved in these efforts have been provided with additional training on the TS requirements.
CORRECTIVE STEPS WHICH WILL BE TAKEN
, Based on the actions described above, PGandE believes that adequate corrective actions have been taken. Therefore, no additional corrective steps are necessary.
DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED Full compliance has been achieved.
B. ACCESS TO HIGH RADIATION AREA STATEMENT OF VIOLATION
"10 CFR 20.203(c)(2) states that each access point to a high -
,,
radiation area shall be equipped with a control device, alarm or be maintained locked except when access is required with positive control over each entry.
Contrary to this requirement, on May 20, 1985 access to non tempcrary high radiation areas in the concentrated waste tank rooms #1 and #2 existed through fiberglass gratings which were not equipped with a t control device, alarm, or lock. Access to the #1 tank room was ?
controlled by a single bolt securing the grating.
This is a Severity Level IV Violation (Supplement IV)."
l
,
0402S/0034K -2-
>
}
..
.
.
.
..
EXPLANATION AND CORRECTIVE STEPS TAKEN Shield plugs on openings above the concentrated waste tanks (CWT) and a resin tank were removed in order to solidify and remove concentrated wastes from the CWTs. The openings are located on the roof of the '2 concrete vault which houses the tanks. Following solidification and disposal of the liquid concentrated wastes, a system was set up to transfer the residual sludge from #2 CUT to #1 CWT. ,,
The transfer system included hoses which were placed in the tanks through the vault opening. The opening was used only for such hoses during the transfer operation and at no time did personnel enter the vault. As a fixed barrier to unauthorized entrance, grating was installed around the hoses and bolted across the opening. The grating was not locked or alarmed since it was intended to be a fixed barrier and not an entrance to the vaults. Signs were posted on the grating to identify the vaults as high radiation areas.
On flay 20, 1985, it was discovered that the bolt for the grating over one of the tanks was missing. Apparently due to an oversight it had not been replaced by maintenance personnel who had performed work on the sludge transfer system. After discovery, a high radiation area was established around the entire Radwaste Treatment Facility roof with the entrance to the area locked. This barrier, which was posted as a high radiation area, enclosed the openings for the resin disposal tank and both CWTs.
Following completion of the waste solidification effort and transfer of the sludge from CWT #2 to CWT #1, the shield plugs were reinstalled in the openings and on June 14, 1985 the high radiation area disestablished.
Requirements concerning access to high radiation areas were reviesed with maintenance personnel.
CORRECTIVE STEPS WHICH WILL BE TAKEN The HBPP program for control of high radiation areas is under revision.
The new program will require the review of the Plant Staff Review '
Committee before a Temporary High Radiation Area may be converted to a ,,
Permanent High Radiation Area, This review will provide added assurance that access points to Permanent High Radiation Areas will comply with the requirements of 10 CFR 20.203(c)(2).
DATE WHEN FULL C0f1PLIANCE WILL BE ACHIEVED
, f A locked boundary was established on flay 24, 1985
[
C. 00CtHEHTATION OF SURVEYS STATE 1ENT OF VIOLATION
"10 CFR 20.401, ' Records of Surveys' states in part that each 0402S/0034K -3-
'
- a
. .
. \
.. . ,
a licensee shall maintain records showing the results of surveys required by 10 CFR 20.201(b). 10 CFR 20.201(b) states in part that each licensee shall make such survey as may be necessary to comply with the regulations in this part. g
- ,
Contrary to the above, on or about May 10, 1985, a survey was made in and around a large radioactive waste container and shield ring as necessary to comply with 10 CFR 20.201 and as of May 16,1985, no licensee record had been created to document the"results of this survey. The survey was necessary to establish posting and labeling requirements for this area. khen this matter was brought to the licensee's attention, at the exit interview, the inspector was informed that the radiation protection monitor made notes but failed to document the survey.
This is a Severity Level V Violation (Supplement IV)."
EXPLAffATION AND CORRECTIVE STEPS TAKEN When the container of solidified radioactive waste was placed inside the shield ring, a survey was performed. The dose rate was written on a high radiation area sign and the sign was posted on the side of the shield ring. It has been normal plant practice for the technician to document the survey on hand drawn maps and then transcribe the results to another map at a later time. Since the second map is prepared in the office, the technician can use drafting aids such as templates and scales to make a more informative and readable map.
As noted by the inspector in the inspection report, the survey described in the notice of violation was performed. The results were posted on the bulletin board in the Radiation Protection Department office. Therefore, the results of the survey were in fact available in that office.
However, due to other work requirements, the technician had not transferred the information from the hand drawn map to the formal survey map as of May 16, 1985.
Following the inspection, the survey results were transferred to another r
,
survey map which was filed in the plant survey records. All technicians -
were instructed to transfer survey information to the final survey maps as soon as possible after completing a survey.
CORRECTIVE STEPS WHICH WILL BE TAKEN PGandE believes the corrective actions described above,are adeauate to f address the violation. Therefore, no additional corrective steps are ,
necessary. ,
DATE WPEN FULL COMPLIANCE WILL BE ACHIEVED Full compliance has been achieved.
0402S/0034K -4-
.