IR 05000003/2025003

From kanterella
Jump to navigation Jump to search
International, LLC, Indian Point Energy Center, Units 2 and 3 - NRC Inspection Report Nos. 05000003/2025003, 05000247/2025003, 05000286/2025003, Independent Spent Fuel Storage Installation Inspection Report 07200051/2024001,
ML26014A190
Person / Time
Site: Indian Point  
Issue date: 01/20/2026
From: Eve E
Decommissioning, ISFSI, and Reactor Health Physics Branch
To: Trice K
Holtec Decommissioning International
References
IR 2024001, IR 2025003
Download: ML26014A190 (0)


Text

January 20, 2026

SUBJECT:

HOLTEC DECOMMISSIONING INTERNATIONAL, LLC, INDIAN POINT ENERGY CENTER UNITS 1, 2 AND 3 - NRC INSPECTION REPORT NOS.

05000003/2025003, 05000247/2025003, 05000286/2025003, INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200051/2024001, AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Kelly Trice:

On December 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Indian Point Energy Center (IPEC) Units 1, 2 and 3. The results of the inspection were discussed with Matthew Johnson, Acting Site Vice President, and other members of your staff on January 8, 2026, and are described in the enclosed inspection report.

The NRC identified a violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 72.48, paragraphs (c)(1), (c)(2), and (d)(1), and provisions of 10 CFR 72.212 that resulted from a Certificate of Compliance (CoC) holders failure to comply with 10 CFR 72.48 for a CoC holder-generated change for the Holtec continuous basket shim multi-purpose canister variant design. However, an Interim Enforcement Policy issued in August 2025 is applicable to this violation. Specifically, Enforcement Policy Section 9.4, Enforcement Discretion for General Licensee Adoption of Certificate of Compliance (CoC) Holder-Generated Modifications under 10 CFR Part 72.48, provides enforcement discretion to not issue an enforcement action for this violation. The licensee will be expected to comply with 10 CFR 72.212 provisions after the NRC dispositions the noncompliance for a CoC holder-generated change that affects the General Licensee.

No other violations of more than minor safety significance were identified during this inspection. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elise Eve, Acting Chief Decommissioning, ISFSI, and Reactor Health Physics Branch Division of Radiological Safety and Security

Docket Nos. 05000003, 05000247, 05000286, and 07200051 License Nos. DPR-5, DPR-26, and DPR-64

cc w/encl: Distribution via ListServ

Enclosure:

Inspection Report Nos.

05000003/2025003, 05000247/2025003, 05000286/2025003, and 07200051/2024001 ELISE EVE Digitally signed by ELISE EVE Date: 2026.01.20 06:15:22 -05'00'

SUBJECT:

HOLTEC DECOMMISSIONING INTERNATIONAL, LLC, INDIAN POINT ENERGY CENTER UNITS 1, 2 AND 3 - NRC INSPECTION REPORT NOS.

05000003/2025003, 05000247/2025003, 05000286/2025003, INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200051/2024001, AND EXERCISE OF ENFORCEMENT DISCRETION DATED JANUARY 20, 2026

DISTRIBUTION:

MFerdas, DRSS EEve, DRSS BBickett, DRSS SVeunephachan, DRSS KWarner, DRSS OFont, RDB R1ORAMAIL Resource

ADAMS A

Inspection Report

Docket Nos.

05000003, 05000247, 05000286, and 07200051

License Nos.

DPR-5, DPR-26, and DPR-64

Report Nos.

05000003/2025003, 05000247/2025003, 05000286/2025003, and

07200051/2024001

Enterprise Identifiers:

I-2025-002-0074 and I-2024-001-0110

Licensee:

Holtec Decommissioning International, LLC (HDI)

Facility:

Indian Point Energy Center, Units 1, 2, and 3

Location:

Buchanan, NY

Inspection Dates:

July 1, 2025, to December 31, 2025

Inspectors:

S. Veunephachan, Senior Health Physicist

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

B. Edwards, Health Physicist

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

N. Harmon, Health Physicist

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

A. Kostick, Health Physicist

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

Approved By:

Elise Eve, Acting Chief

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) conducted a routine inspection of problem

identification and resolution, fire protection, decommissioning performance and status reviews,

occupational radiation exposure, and solid radioactive waste management and transportation.

The inspection consisted of observations by the inspectors, interviews with site personnel, a

review of procedures and records, and site walk-downs. The U.S. Nuclear Regulatory

Commissions (NRCs) program for overseeing the safe decommissioning of a permanently

shutdown nuclear power reactor is described in Inspection Manual Chapter (IMC) 2561,

Decommissioning Power Reactor Inspection Program.

Additionally, this inspection report includes a review of Independent Spent Fuel Storage

Installation (ISFSI) dry cask activities. The NRCs program for overseeing the operation of dry

storage of spent fuel at an ISFSI is described in IMC 2690, Inspection Program for Dry Storage

of Spent Reactor Fuel at Independent Spent Fuel Storage Installations and for Title 10 of the

Code of Federal Regulations (CFR) Part 71 Transportation Packagings.

List of Violations

No violations of more than minor significance were identified. One violation was identified for

which enforcement discretion was granted.

Additional Tracking Items

Type

Issue Number

Title

Report

Section

Status

URI

07200051/2023004-01

Use of Holtec Multipurpose

Canister Continuous Basket Shim

Variant

60855

Closed

EDG

EAF-NMSS-2025-0225

Noncompliance Related to a

General Licensees Use of Non-

Qualified Spent Fuel Casks

(IEP 9.4)

60855

Closed

SITE STATUS

Indian Point Units 1, 2, and 3 were inspected under the Actively Decommissioning (DECON),

No Fuel in the Spent Fuel Pool category. The categories of decommissioning are described in

IMC 2561.

The inspectors performed on-site decommissioning inspection activities on July 21 - 24,

September 8 - 11, and December 8 - 11, 2025 supplemented by in-office reviews and periodic

phone calls. The inspection consisted of observations by the inspectors, interviews with site

personnel, a review of procedures and records, and site walk-downs.

HDI continued reactor vessel internal segmentation for Unit 2 and Unit 3. The site continued

segmentation in Unit 1, including the 12 and 13 boilers. HDI continued conventional demolition

including the access building. HDI continued to package and ship radioactive waste offsite

during the inspection period. HDI began steam generator segmentation on 21 steam

generators.

INSPECTION SCOPES

The inspection was conducted using the appropriate portions of the Inspection Procedures

(IPs). Currently approved IPs are located and may be viewed on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

The inspectors reviewed select procedures and records, observed activities, and interviewed

personnel to assess licensee performance and compliance with Commission rules and

regulations, license conditions, site procedures, and standards. The inspections were declared

complete when the objectives of the IPs were met, consistent with Inspection Manual Chapters

(IMCs) 2561, Decommissioning Power Reactor Inspection Program. and 2690 Inspection

Program for Storage of Spent Reactor Fuel and Reactor-Related Greater-than-Class C Waste

at Independent Spent Fuel Storage Installations (ISFSI) and for 10 CFR Part 71 Transportation

Packagings.

IP 71801 - Decommissioning Implementation and Status

Status of Decommissioning (IP Section 03.01)

The inspectors attended select management meetings, including station oversight committee

and management review committee meetings.

The inspectors performed plant walk-downs of the following locations to assess field

conditions and decommissioning activities:

1) Unit 1, 2, and 3 containments

2) Unit 2 primary auxiliary building

3) Unit 3 primary auxiliary building

Implementation of Regulatory and Licensing Requirements (IP Section 03.02)

The inspectors reviewed 50.59 screenings to determine if changes made by HDI required

prior NRC approval. The reviews included:

1) EC IPC-2024-014, Class B/C Waste Onsite Transport and Storage - IP2

2) EN-LI-100 for SAO-703 R39

The inspectors reviewed the following licensing basis documents and regulatory required

documents:

1) 10 CFR 50.75(g) file

2) Offsite Dose Calculation Manual (ODCM), Revision 8

IP 83750 - Decommissioning Occupational Radiation Control

Radiological Work Planning and Execution (IP Section 03.01)

The inspectors reviewed Radiation Work Permits (RWPs) and As Low As Reasonably

Achievable (ALARA) work plans and observed Radiation Protection (RP) activities associated

with the following:

1) Unit 2 primary auxiliary building

2) Unit 2 steam generator segmentation

3) Steam generator segmentation in the steam generator mausoleum

Occupational Radiation Exposure Topical Areas (IP Section 03.02)

Dosimetry (IP Section 03.02a)

The inspectors verified the 2025 National Voluntary Laboratory Accreditation Program

certification.

Airborne and Contamination Controls (IP Section 03.02b)

The inspectors observed the following activities for contamination control:

1) Workers exiting of the radiologically controlled area (RCA) for Unit 1, 2, and 3.

2) Radiation Protection (RP) technicians surveying and decontaminating material for

release from the RCA

3) Walk downs and observations of continuous air monitors and grab samplers

located in:

  • Unit 2 95 elevation by roll-up door, AMS-4, S/N: 11724 on September 10, 2025
  • Unit 2 95 elevation near D-Ring entrance, AMS-4, S/N: 11521 on September 10, 2025
  • Steam generator mausoleum, low flow air sampler, S/N: 10504 on December 10, 2025

Source Term Characterization

The inspectors reviewed the following source term characterization to ensure the licensee was

using appropriate instruments commensurate with the characterized radiation types and

energies:

1) Unit 3 spent fuel pool racks dry active waste

2) Unit 2 segmentation TN filters

3) Unit 1 primary system components decayed

IP 84750 - Decommissioning Radioactive Waste Treatment, and Effluent and Environmental

Monitoring

Annual Effluent and Environmental Reports (IP Section 03.02)

The inspectors verified the annual Radiological Effluent Release Report and Radiological

Environmental Operating Report were submitted as required and reported doses are below

regulatory requirements.

Implementation of the Radiological, Effluent, and Groundwater Protection Initiative Programs

(IP Section 03.03)

Radioactive Gaseous and Liquid Effluent Treatment (Section 03.03a)

The inspectors performed walkdowns on the following effluent radiation monitors to ensure

adequate material condition:

1) U3 Plant Vent

2) R-27

3) U3 Rams Vent

Radiological Environmental Monitoring Program (Section 03.03b)

The inspectors conducted walkdowns of the following thermoluminescent dosimeter

monitoring stations to ensure they were located as stated in the ODCM and to determine

adequate material condition on July 23, 2025:

1) OSL-7, City Water Tank

2) OSL-8, Main Entrance, bus stop

3) OSL-36, Lower South Street & Franklyn

4) OSL-5, Bleakly entrance

The inspectors conducted walkdowns of the following air sampling stations to determine they

were located as stated in the ODCM and to determine adequate material condition on

July 24, 2025:

1) Meteorological tower location

2) Algonquin

Groundwater Protection Initiative (IP Section 03.03c)

The inspectors performed walkdowns of the following groundwater wells to assess adequate

material condition and location:

1) MW-32

2) MW-33

3) MW-37

4) MW-42

5) MW-43

6) MW-55

7) MW-58

8) MW-60

9) MW-66

10) U3-4D

11) U3-4S

12) U3-T1

IP 86750 - Decommissioning Solid Radioactive Waste Management, Demolition and

Transportation of Radioactive Materials

Radioactive Material Storage, Control, and Processing (IP Section 03.01)

Radioactive Sources (IP Section 03.01c)

The inspectors reviewed the leak tests and conducted walkdowns on July 23, 2025, for the

listed sealed sources to verify sources to be intact and located commensurate with licensee

records:

1) S/N: IP3-403

2) S/N: IP3-376

3) S/N: IP3-45

4) S/N: IP3-120

Transportation of Radioactive Materials (IP Section 03.02)

The inspectors reviewed the shipping manifests for the following radioactive waste

shipments:

1) 25-2-100, Mechanical Filter Liner, Radioactive Material, LSA-II

2) 25-3-043, TN Filter Liner, Radioactive Material, LSA-II

3) 25-3-091, Mechanical Filter Liner, Radioactive Material, LSA-II

IP 60855, Operation of an Independent Spent Fuel Storage Installation

The inspector conducted a periodic in-office follow-up that focused on the review of

the general licensees (GLs) implementation of the 10 CFR 72.48 process and

associated corrective actions related to Independent Spent Fuel Storage Installation

(ISFSI) activities.

The review included:

1) 72.48 Evaluations and Screenings: Reviewed the GLs 72.48 process and

associated evaluation associated with the adoption of the continuous basket

shim (CBS) variant

2) Corrective Action Program (CAP): Reviewed condition reports related to the

design change of the CBS variant

INSPECTION RESULTS

Enforcement

Discretion

Enforcement Action EAF-NMSS-2025-0225:

Noncompliance Related to a General Licensees Use of

Non-Qualified Spent Fuel Casks (IEP 9.4)

60855

Description: Holtec International (also referred to as the CoC [Certificate of Compliance]

Holder) implemented a design change to its Multi-Purpose Canister (MPC) fuel basket, known

as the continuous basket shim (CBS) variant, which altered the structural configuration from

welded to bolted shims. This change resulted in a departure from the method of evaluation

(MOE) described in the final safety analysis report (FSAR) used to establish the design basis

for tip-over events. Holtec did not fully evaluate the cumulative impact of the MOE changes or

apply them consistently with the licensing basis. As a result, the NRC issued three Severity

Level IV violations to Holtec for noncompliance with 10 CFR 72.48 requirements (see U.S.

Nuclear Regulatory Commission Inspection Report 07201014/2022-201, Holtec International,

Agencywide Documents Access and Management System [ADAMS] Accession No.

ML23145A175 and Holtec International, Inc. - Notice of Violation; The U.S. Nuclear

Regulatory Commission Inspection Report No. 07201014/2202-201, ADAMS Accession No.

ML24016A190).

When the General Licensee (GL) chooses to adopt a change the CoC holder made pursuant

to a CoC holder's change authority under 10 CFR 72.48 (referred to herein as a CoC holder-

generated change), the GL must perform a separate review using the requirements of 10 CFR 72.48(c). Accordingly, when the GL chooses to adopt a CoC holder-generated change,

and that change results in a non-conforming cask, there is a violation of 10 CFR 72.48 and

certain provisions of 10 CFR 72.212 by the GL, in addition to a CoC holder violation of 10 CFR 72.48. As it relates to the adoption of the continuous basket shim (CBS) variant casks,

the GL failed to recognize the noncompliance with 10 CFR 72.48 requirements made by the

CoC holders design change and subsequently loaded the CBS variant casks.

Corrective Actions: The GL entered this into its corrective action program with actions to

restore compliance with the 10 CFR 72.212 provisions that require each cask to conform to

the terms, conditions, and specifications of a CoC or an amended CoC listed in 72.214.

Corrective Action References: IR-IP2-1059

Enforcement:

Significance/Severity: This violation was dispositioned in accordance with Section 9.4,

Enforcement Discretion for General Licensee Adoption of CoC Holder-Generated Changes

Under 10 CFR 72.48, of the NRCs Enforcement Policy.

Specifically, as stated in the Policy, the NRC will exercise enforcement discretion and not

issue an enforcement action to a General Licensee, for a noncompliance with the

requirements of paragraphs (c)(1) and (2) and (d)(1) of 10 CFR 72.48 and with provisions of

10 CFR 72.212 that require GLs to ensure use of casks that conform to the terms,

conditions and specifications of a CoC listed in 10 CFR 72.214, when the noncompliance

results from a CoC holders failure to comply with 10 CFR 72.48 for a CoC holder-generated

change.

Violation: Title 10 CFR 72.48 (c)(1) requires, in part, that a licensee or certificate holder may

make changes in the facility or spent fuel storage cask design as described in the FSAR (as

updated), without obtaining: (ii) CoC amendment submitted by the certificate holder

pursuant to § 72.244 if: (c) The change, test, or experiment does not meet any of the criteria

in paragraph (c)(2) of this section.

Title 10 CFR 72.48(c)(2) requires, in part, that a general licensee shall request that the

certificate holder obtain a CoC amendment, prior to implementing a proposed change, if the

change would: (viii) Result in a departure from an MOE described in the FSAR used in

establishing the design bases or in the safety analyses.

Title 10 CFR 72.48(d)(1) requires, in part, that the licensee shall have a written evaluation

which provides the bases for the determination that the change does not require a CoC

amendment pursuant to 72.48(c)(2).

Title 10 CFR 72.212(b)(3) requires, in part, a general licensee must ensure that each cask

used by the general licensee conforms to the terms, conditions, and specifications of a CoC

or an amended CoC listed in 72.214.

Contrary to the above, in August 2022, the licensee loaded the first CBS design variant and

failed to maintain records of changes in the spent fuel storage cask design made pursuant

to 72.48(c) that include a written evaluation which provided the bases for the determination

that the change did not require a CoC amendment. The licensee failed to request that the

certificate holder obtain a CoC amendment, prior to implementing a proposed change, if the

change would: (viii) result in a departure from an MOE described in the FSAR used in

establishing the design bases or in the safety analyses. Further, the licensee failed to

ensure each cask conformed to the terms, conditions, and specifications of a CoC or

amended CoC listed in 72.214.

Basis for Discretion: When a general licensee chooses to adopt a CoC holder-generated

change, and that change results in a non-conforming cask, there is a violation of 10 CFR 72.48 and certain provisions of 10 CFR 72.212 by the GL, in addition to a CoC holder

violation of 10 CFR 72.48. And, when a general licensee chooses to adopt a CoC holder-

generated change without performing a separate 10 CFR 72.48 analysis, the general

licensee is in violation of 10 CFR 72.48. These requirements could lead to enforcement

actions being issued against both the general licensee's 10 CFR 72.48 program (as well as

certain 10 CFR 72.212 violations) and the CoC holder's 10 CFR 72.48 program for changes

that originated with the CoC holder. The NRC has concluded that this enforcement

approach would be inconsistent with efficiency, which is one of the NRC's Principles of

Good Regulation, and NRC's mission of efficient and reliable oversight.

Since this violation meets the conditions of the NRCs Enforcement Policy Section 9.4,

Enforcement Discretion for General Licensee Adoption of Certificate of Compliance Holder-

Generated Changes under 10 CFR 72.48 (ML25224A097), and the licensee has entered the

noncompliance into the corrective action program, the NRC is exercising enforcement

discretion by not issuing an enforcement action for this violation.

The disposition of this violation closes URI: 07200051/2023004-001

IP 92702 - Follow-Up on Traditional Enforcement Actions Including Violations, Deviations,

Confirmatory Action Letters, and Orders

In accordance with guidance in Inspection Procedure (IP) 92702, Follow-Up on Traditional

Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, And Orders,

inspector conducted follow-up inspection, in-office, of corrective actions associated with Notice

of Violation; EA-24-010/EAF-RI-2025-0056.

The inspectors determined that the licensee has taken proper corrective actions in response to

the violations as presented in the Holtec Root Cause Evaluation IP-01668 and associated

corrective action plan.

EXIT MEETING

On January 8, 2026, the inspectors presented the inspection results to Matthew Johnson, Acting

Site Vice President, and other members of the IPEC organization. No proprietary information

was retained by the inspectors or documented in this report.