ENS 55894
ENS Event | |
|---|---|
22:14 May 11, 2022 | |
| Title | |
| Event Description | The following information was provided by the licensee via email:
During performance of High Pressure Coolant Injection (HPCI) Pump and Valve Operability surveillance in accordance with procedure 24.202.01, the turbine tripped without operator action. The plant was operating in Mode 1 at 10 percent power with the HPCI turbine running in a test mode at 5100 gpm with all surveillance criteria met. The surveillance was near completion at the point where the HPCI turbine is manually tripped. Before the manual trip was performed, the HPCI turbine tripped without operator action. Prior to performance of the surveillance, HPCI was provisionally operable with only satisfactory completion of Post Maintenance Testing (PMT) surveillance remaining to declare HPCI operable. HPCI surveillance testing was performed at low reactor pressure (165 psig) in Mode 2 satisfactorily. Investigation into the cause of this trip is in progress. HPCI has been declared inoperable from the time of release of the surveillance. Reactor Coolant Isolation Cooling (RCIC) was verified to be operable prior to and after the surveillance in accordance with Technical Specifications 3.5.1 condition E.1. This report is being made pursuant to 10 CFR 50.72(b)(3)(v)(D) based on an unplanned HPCI inoperability. There was no impact on the health and safety of the public or plant personnel. The NRC Resident Inspector has been notified. |
| Where | |
|---|---|
| Fermi Michigan (NRC Region 3) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
| LER: | 05000341/LER-2022-002 Unexpected High Pressure Coolant Injection Turbine Trip |
| Time - Person (Reporting Time:+0.18 h0.0075 days <br />0.00107 weeks <br />2.46564e-4 months <br />) | |
| Opened: | Whitney R. Hemingway 22:25 May 11, 2022 |
| NRC Officer: | Brian P. Smith |
| Last Updated: | May 11, 2022 |
| 55894 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 55894\u003C/a\u003E - \u003Ca href=\"/Fermi\" title=\"Fermi\"\u003EFermi\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EHigh Pressure Coolant Injection Inoperable\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 55894 - Fermi\n","link":"","lat":41.96295277777778,"lon":-83.25779444444444,"icon":"/w/images/5/5b/DTE_Energy_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (10 %) |
| After | Power Operation (10 %) |