22:00 May 15, 2017 | |
Title | Valid Emergency Diesel Generator Signal Generated Upon Loss of 4160V Power |
Event Description | On May 15, 2017 at 1800 hours0.0208 days <br />0.5 hours <br />0.00298 weeks <br />6.849e-4 months <br /> EDT, the '2A3' 4.16 KV safety related bus unexpectedly de-energized. The '2A' emergency diesel generator (EDG) system received a valid start signal from the undervoltage condition on the '2A3' bus but did not start as the EDG had been removed from service for maintenance. Loss of the '2A3' 4.16 KV bus resulted in a valid actuation of the undervoltage protection relays. The direct cause of the de-energization was determined to be failed secondary side potential transformer fuses. The 'B' train safety related electrical busses were unaffected by the event.
The '2A3' 4.16 KV bus was reenergized at 2340. This event was determined to be reportable pursuant to 10CFR50.72(b)(3)(iv)(A). During the electrical transient, the licensee briefly entered Technical Specification 3.0.3 but plant conditions were restored, all required LCOs were satisfied, and Technical Specification 3.0.3 was exited before the plant was required to downpower. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
Saint Lucie Florida (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+2.28 h0.095 days <br />0.0136 weeks <br />0.00312 months <br />) | |
Opened: | Tom Plower 00:17 May 16, 2017 |
NRC Officer: | Howie Crouch |
Last Updated: | May 16, 2017 |
52757 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 52757\u003C/a\u003E - \u003Ca href=\"/Saint_Lucie\" title=\"Saint Lucie\"\u003ESaint Lucie\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EValid Emergency Diesel Generator Signal Generated Upon Loss of 4160V Power\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 52757 - Saint Lucie\n","link":"","lat":27.348672222222223,"lon":-80.24639722222223,"icon":"/w/images/9/9b/NextEra_Energy_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 560872022-09-03T02:48:0003 September 2022 02:48:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Loss of Feed Pump ENS 550782021-01-20T23:22:00020 January 2021 23:22:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Trip of Motor Control Center ENS 530362017-10-26T06:12:00026 October 2017 06:12:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Following a Loss of Load ENS 527572017-05-15T22:00:00015 May 2017 22:00:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Valid Emergency Diesel Generator Signal Generated Upon Loss of 4160V Power ENS 521912016-08-21T23:37:00021 August 2016 23:37:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unusual Event - Loss of Offsite Power ENS 514232015-09-17T16:22:00017 September 2015 16:22:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Valid Actuation of Uv Relays Following Loss of Unit 2 Startup Transformer ENS 513022015-08-10T02:15:00010 August 2015 02:15:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip During Testing ENS 506072014-11-12T20:48:00012 November 2014 20:48:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Lowering Steam Generator Water Level ENS 495362013-11-14T17:18:00014 November 2013 17:18:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Low Level in the 2B Steam Generator ENS 483882012-10-08T01:40:0008 October 2012 01:40:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Essential Bus Deenergized While Defueled ENS 483692012-10-03T12:43:0003 October 2012 12:43:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Failure of Startup Transformer Caused Undervoltage Condition on Essential Bus ENS 479152012-05-11T07:55:00011 May 2012 07:55:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Feedwater Control Valve Failure ENS 476572012-02-10T06:34:00010 February 2012 06:34:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Maintenance Activities Cause an Inadvertent Emergency Diesel Generator Start ENS 469282011-06-06T07:29:0006 June 2011 07:29:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Error During Reactor Protection System Surveillance Leads to Reactor Trip ENS 458432010-04-15T19:39:00015 April 2010 19:39:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Manual Reactor Trip ENS 453742009-09-21T17:34:00021 September 2009 17:34:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Manual Reactor Trip During Reactor Startup ENS 449522009-04-01T22:05:0001 April 2009 22:05:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Manual Reactor Trip ENS 442762008-06-07T12:18:0007 June 2008 12:18:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Following the Trip of a Condensate Pump ENS 438742007-12-29T06:31:00029 December 2007 06:31:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip When Five Control Rods Unexpectedly Dropped 20 Inches ENS 419112005-08-11T14:48:00011 August 2005 14:48:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip on a Condensate Pump Bus Lockout ENS 417152005-05-19T00:59:00019 May 2005 00:59:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Inadvertent De-Energization of 4160 V Safety Related A.C. Bus with Edg Auto Start ENS 412932004-12-25T11:52:00025 December 2004 11:52:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 2 Manually Tripped to Remove Failing Condensate Pump from Service ENS 410722004-09-26T03:56:00026 September 2004 03:56:00 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unusual Event Declared Due to a Loss of Offsite Power ENS 404032003-12-20T14:49:00020 December 2003 14:49:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Rps Actuation Due to Loss of Turbine Generator Excitation 2022-09-03T02:48:00 | |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_52757&oldid=420540"