ENS 52204
ENS Event | |
---|---|
05:00 Aug 3, 2016 | |
Title | Part 21 - Safety Related Component Welding by an Unqualified Welder |
Event Description | The following was excerpted from a letter by Crane Nuclear, Inc.:
Shielded metal arc welding (SMAW) with F-5 filler metal was welded on safety related components by an unqualified welder. Crane Nuclear Quality Assurance Manual, 12th Edition Rev. 2, dated 8/8/16 requires that welder performance qualification shall conform to the requirements of ASME Section IX for processing ASME B&PV Section Ill and safety related valve and valve part orders. During processing of a safety related order, it was identified that one welder was missing the required qualification documentation to perform weld repairs with F-5 filler metals (as defined in ASME Section IX) using the shielded metal arc welding process (SMAW). The safety hazard which could be created by such a defect could be a potential weld failure. Crane Nuclear has completed a review of all applicable welding records based on the welder hire date of September, 2011. We identified a total of 10 orders that were supplied with welding performed by an unqualified welder. Notification has been made to the purchasers of the affected safety related orders on the same date as this notification. Should you have any questions regarding this matter, please contact Burt Anderson, Site Leader, at (630) 226-4990, Rosalie Nava, Director of Safety and Quality at (630) 226-4940, or Jason Klein, Engineering Manager at (630) 226-4953. The following facilities received these safety related orders: Duke-McGuire, Exelon-Byron, Duke-Brunswick, Entergy-ANO, Exelon-TMI, Exelon-Quad Cities, Exelon-Dresden.
The following information was received via fax: This letter is intended to inform the U.S. Nuclear Regulatory Commission of actions taken to complete the Part 21 evaluation on the above referenced item. All of the following actions have been completed: 1) The welder has been qualified on the SMAW process utilizing F-5 filler metal and documented in accordance with ASME Section IX requirements. 2) The affected purchasers were provided with an initial 10CFR21 notification on August 26, 2016. 3) The affected purchasers were provided with the documentation detailing the scope of the welding performed on the affected components. 4) The affected purchasers were provided an investigation summary closure letter. 5) Crane Nuclear, Inc. Corrective Action Report 16-35 generated to determine root cause and implement appropriate corrective actions to prevent recurrence was completed and closed on September 30, 2016. Should you have any questions regarding this matter, please contact, Rosalie Nava, Director Safety and Quality at (630) 226-4940, or Burt Anderson, Site Leader. at (630) 226-4990. Notified R1DO (Cook), R2DO (Desai), R3DO (Stone), R4DO (Groom), and the Part 21 Group (via e-mail). |
Where | |
---|---|
Crane Nuclear, Inc. Bolingbrook, Illinois (NRC Region 3) | |
Organization: | Crane Nuclear, Inc. |
Reporting | |
10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
Time - Person (Reporting Time:+565 h23.542 days <br />3.363 weeks <br />0.774 months <br />) | |
Opened: | Burt Anderson 18:00 Aug 26, 2016 |
NRC Officer: | Dong Park |
Last Updated: | Sep 30, 2016 |
52204 - NRC Website | |
Crane Nuclear, Inc. with 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
WEEKMONTHYEARENS 551262021-01-06T06:00:0006 January 2021 06:00:00
[Table view]10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Interim Part 21 Report - Weld Procedures Do Not Meet Asme Code ENS 532462017-12-17T06:00:00017 December 2017 06:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Undersized Packing Glands in Certain Crane Gate Valves ENS 528572017-06-05T05:00:0005 June 2017 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Defective Safety Related Valves ENS 522042016-08-03T05:00:0003 August 2016 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Safety Related Component Welding by an Unqualified Welder ENS 514962015-08-26T05:00:00026 August 2015 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Pressure Seal Valve Noncompliance ENS 503362014-08-01T05:00:0001 August 2014 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Safety-Related Valves Assembled with Non-Safety Related Levers 2021-01-06T06:00:00 | |